App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
- 1.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show the score (b) check the answer (c) an avatar shop (d) show a question
- 2.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) share tasks to friends (b) see tasks by day (c) earn stickers (d) pick a theme colour
- 3.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) rate the driver (b) see where the bus is (c) a dark mode (d) change the bus icon
- 4.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) confetti effects (b) an avatar shop (c) show a question (d) background music
-
5.🗒️ Version 1 of a quiz app must be ready in 6 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 1 days
show the score: 2 days - 6.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) pie-chart colours (b) add money received (c) add money spent (d) show the balance
-
7.🗒️ Version 1 of a homework planner must be ready in 14 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 3 days
see tasks by day: 5 days - 8.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) log a glass of water (b) custom alert sounds (c) share your streak (d) water animations
- 9.🗒️ When should nice-to-have features be built? (a) never (b) before anything (c) on day one (d) after the must-haves
- 10.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show the score (b) background music (c) show a question (d) check the answer
- 11.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) see where the bus is (b) show arrival time (c) pick your bus stop (d) change the bus icon
- 12.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) background music (b) an avatar shop (c) confetti effects (d) show the score
-
13.🗒️ Version 1 of a water reminder must be ready in 12 days. How many days are left for extras after the must-haves?
set a reminder time: 4 days
log a glass of water: 3 days
see today’s total: 4 days - 14.🗒️ In MVP, the M stands for ___. (a) minimum (b) mobile (c) maximum (d) music
- 15.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) set a due date (b) share tasks to friends (c) add a homework task (d) see tasks by day
- 16.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) share tasks to friends (b) earn stickers (c) set a due date (d) pick a theme colour
- 17.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) set a due date (b) pick a theme colour (c) add a homework task (d) see tasks by day
- 18.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) water animations (b) set a reminder time (c) see today’s total (d) log a glass of water
- 19.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) earn stickers (b) share tasks to friends (c) add a homework task (d) pick a theme colour
- 20.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) water animations (b) share your streak (c) custom alert sounds (d) set a reminder time
- 21.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money received (b) savings stickers (c) show the balance (d) add money spent
- 22.🗒️ The first small, working version of an app is often called an ___. (a) FAQ (b) CPU (c) MVP (d) URL
-
23.🗒️ Version 1 of a bus tracker must be ready in 8 days. How many days are left for extras after the must-haves?
see where the bus is: 3 days
show arrival time: 1 days
pick your bus stop: 2 days -
24.🗒️ Version 1 of a pocket-money tracker must be ready in 11 days. How many days are left for extras after the must-haves?
add money received: 3 days
add money spent: 4 days
show the balance: 4 days - 25.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) custom alert sounds (b) share your streak (c) water animations (d) see today’s total
- 26.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money received (b) show the balance (c) export to a file (d) add money spent
- 27.🗒️ A to-do app with no “add a task” feature is ___. (a) ready to release (b) missing a must-have (c) a nice extra (d) well planned
- 28.🗒️ Why keep version 1 small? (a) to confuse users (b) to learn from users soon (c) to use up storage (d) to look bigger
- 29.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) see today’s total (b) set a reminder time (c) log a glass of water (d) custom alert sounds
- 30.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) export to a file (b) add money spent (c) savings stickers (d) pie-chart colours
-
31.🗒️ Version 1 of a water reminder must be ready in 14 days. How many days are left for extras after the must-haves?
set a reminder time: 2 days
log a glass of water: 4 days
see today’s total: 5 days -
32.🗒️ Version 1 of a homework planner must be ready in 5 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 1 days
see tasks by day: 3 days -
33.🗒️ Version 1 of a quiz app must be ready in 8 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 2 days
show the score: 4 days -
34.🗒️ Version 1 of a pocket-money tracker must be ready in 12 days. How many days are left for extras after the must-haves?
add money received: 1 days
add money spent: 3 days
show the balance: 2 days -
35.🗒️ Version 1 of a pocket-money tracker must be ready in 9 days. How many days are left for extras after the must-haves?
add money received: 1 days
add money spent: 2 days
show the balance: 3 days - 36.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) check the answer (b) show a question (c) confetti effects (d) show the score
-
37.🗒️ Version 1 of a homework planner must be ready in 12 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 4 days
see tasks by day: 2 days -
38.🗒️ Version 1 of a quiz app must be ready in 11 days. How many days are left for extras after the must-haves?
show a question: 3 days
check the answer: 1 days
show the score: 2 days -
39.🗒️ Version 1 of a homework planner must be ready in 6 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 1 days
see tasks by day: 2 days - 40.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) confetti effects (b) background music (c) an avatar shop (d) check the answer
Answer key
- an avatar shop
- see tasks by day
- see where the bus is
- show a question
- 2
- pie-chart colours
- 5
- log a glass of water
- after the must-haves
- background music
- change the bus icon
- show the score
- 1
- minimum
- share tasks to friends
- set a due date
- pick a theme colour
- water animations
- add a homework task
- set a reminder time
- savings stickers
- MVP
- 2
- 0
- see today’s total
- export to a file
- missing a must-have
- to learn from users soon
- custom alert sounds
- add money spent
- 3
- 0
- 1
- 6
- 3
- confetti effects
- 4
- 5
- 1
- check the answer