App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
- 1.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) export to a file (b) savings stickers (c) pie-chart colours (d) show the balance
- 2.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) show arrival time (b) see where the bus is (c) rate the driver (d) pick your bus stop
-
3.🗒️ Version 1 of a quiz app must be ready in 14 days. How many days are left for extras after the must-haves?
show a question: 4 days
check the answer: 3 days
show the score: 2 days - 4.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) show the balance (b) add money received (c) savings stickers (d) add money spent
-
5.🗒️ Version 1 of a water reminder must be ready in 10 days. How many days are left for extras after the must-haves?
set a reminder time: 2 days
log a glass of water: 2 days
see today’s total: 2 days - 6.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show a question (b) show the score (c) check the answer (d) confetti effects
- 7.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) change the bus icon (b) a dark mode (c) pick your bus stop (d) rate the driver
- 8.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) change the bus icon (b) a dark mode (c) rate the driver (d) show arrival time
- 9.🗒️ When should nice-to-have features be built? (a) before anything (b) on day one (c) after the must-haves (d) never
-
10.🗒️ Version 1 of a homework planner must be ready in 14 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 1 days
see tasks by day: 5 days -
11.🗒️ Version 1 of a pocket-money tracker must be ready in 10 days. How many days are left for extras after the must-haves?
add money received: 1 days
add money spent: 3 days
show the balance: 5 days - 12.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) show the balance (b) pie-chart colours (c) add money received (d) add money spent
-
13.🗒️ Version 1 of a homework planner must be ready in 8 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 1 days
see tasks by day: 2 days - 14.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) show the balance (b) add money received (c) export to a file (d) add money spent
-
15.🗒️ Version 1 of a water reminder must be ready in 12 days. How many days are left for extras after the must-haves?
set a reminder time: 2 days
log a glass of water: 3 days
see today’s total: 3 days -
16.🗒️ Version 1 of a quiz app must be ready in 12 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 4 days
show the score: 3 days - 17.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) export to a file (b) savings stickers (c) pie-chart colours (d) add money received
- 18.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) check the answer (b) show the score (c) background music (d) show a question
- 19.🗒️ The first small, working version of an app is often called an ___. (a) CPU (b) FAQ (c) MVP (d) URL
- 20.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) pick a theme colour (b) earn stickers (c) see tasks by day (d) share tasks to friends
- 21.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) background music (b) check the answer (c) confetti effects (d) an avatar shop
-
22.🗒️ Version 1 of a bus tracker must be ready in 11 days. How many days are left for extras after the must-haves?
see where the bus is: 2 days
show arrival time: 3 days
pick your bus stop: 4 days - 23.🗒️ Why keep version 1 small? (a) to use up storage (b) to confuse users (c) to look bigger (d) to learn from users soon
-
24.🗒️ Version 1 of a bus tracker must be ready in 6 days. How many days are left for extras after the must-haves?
see where the bus is: 1 days
show arrival time: 2 days
pick your bus stop: 3 days - 25.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) water animations (b) log a glass of water (c) set a reminder time (d) see today’s total
- 26.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) see tasks by day (b) add a homework task (c) share tasks to friends (d) set a due date
- 27.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) see today’s total (b) custom alert sounds (c) water animations (d) share your streak
-
28.🗒️ Version 1 of a bus tracker must be ready in 17 days. How many days are left for extras after the must-haves?
see where the bus is: 4 days
show arrival time: 4 days
pick your bus stop: 4 days -
29.🗒️ Version 1 of a quiz app must be ready in 10 days. How many days are left for extras after the must-haves?
show a question: 4 days
check the answer: 2 days
show the score: 4 days - 30.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) set a reminder time (b) see today’s total (c) custom alert sounds (d) log a glass of water
- 31.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) show arrival time (b) pick your bus stop (c) see where the bus is (d) a dark mode
- 32.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) water animations (b) share your streak (c) set a reminder time (d) custom alert sounds
- 33.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) log a glass of water (b) custom alert sounds (c) share your streak (d) water animations
- 34.🗒️ A to-do app with no “add a task” feature is ___. (a) missing a must-have (b) ready to release (c) well planned (d) a nice extra
-
35.🗒️ Version 1 of a bus tracker must be ready in 16 days. How many days are left for extras after the must-haves?
see where the bus is: 3 days
show arrival time: 2 days
pick your bus stop: 5 days -
36.🗒️ Version 1 of a pocket-money tracker must be ready in 12 days. How many days are left for extras after the must-haves?
add money received: 3 days
add money spent: 3 days
show the balance: 5 days -
37.🗒️ Version 1 of a pocket-money tracker must be ready in 13 days. How many days are left for extras after the must-haves?
add money received: 1 days
add money spent: 2 days
show the balance: 5 days - 38.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) pick a theme colour (b) see tasks by day (c) set a due date (d) add a homework task
-
39.🗒️ Version 1 of a quiz app must be ready in 12 days. How many days are left for extras after the must-haves?
show a question: 4 days
check the answer: 2 days
show the score: 5 days - 40.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) pick your bus stop (b) show arrival time (c) see where the bus is (d) change the bus icon
Answer key
- show the balance
- rate the driver
- 5
- savings stickers
- 4
- confetti effects
- pick your bus stop
- show arrival time
- after the must-haves
- 5
- 1
- pie-chart colours
- 3
- export to a file
- 4
- 4
- add money received
- background music
- MVP
- see tasks by day
- check the answer
- 2
- to learn from users soon
- 0
- water animations
- share tasks to friends
- see today’s total
- 5
- 0
- custom alert sounds
- a dark mode
- set a reminder time
- log a glass of water
- missing a must-have
- 6
- 1
- 5
- pick a theme colour
- 1
- change the bus icon
Free app development lessons, practice and worksheets at talentjr.in/app-development-for-students