App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
- 1.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) a dark mode (b) show arrival time (c) rate the driver (d) change the bus icon
- 2.🗒️ When should nice-to-have features be built? (a) on day one (b) never (c) after the must-haves (d) before anything
- 3.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) show the balance (b) add money spent (c) pie-chart colours (d) add money received
- 4.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) pie-chart colours (b) add money received (c) export to a file (d) savings stickers
- 5.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show a question (b) show the score (c) confetti effects (d) check the answer
- 6.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) set a reminder time (b) see today’s total (c) water animations (d) log a glass of water
- 7.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) see tasks by day (b) add a homework task (c) set a due date (d) share tasks to friends
-
8.🗒️ Version 1 of a homework planner must be ready in 9 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 1 days
see tasks by day: 2 days - 9.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) add money spent (b) savings stickers (c) pie-chart colours (d) export to a file
- 10.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money spent (b) show the balance (c) export to a file (d) add money received
-
11.🗒️ Version 1 of a pocket-money tracker must be ready in 11 days. How many days are left for extras after the must-haves?
add money received: 4 days
add money spent: 1 days
show the balance: 3 days - 12.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) earn stickers (b) share tasks to friends (c) pick a theme colour (d) add a homework task
-
13.🗒️ Version 1 of a homework planner must be ready in 11 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 4 days
see tasks by day: 5 days -
14.🗒️ Version 1 of a water reminder must be ready in 17 days. How many days are left for extras after the must-haves?
set a reminder time: 4 days
log a glass of water: 4 days
see today’s total: 4 days -
15.🗒️ Version 1 of a pocket-money tracker must be ready in 14 days. How many days are left for extras after the must-haves?
add money received: 1 days
add money spent: 3 days
show the balance: 4 days - 16.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) show the score (b) confetti effects (c) an avatar shop (d) background music
- 17.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) log a glass of water (b) see today’s total (c) custom alert sounds (d) set a reminder time
- 18.🗒️ In MVP, the M stands for ___. (a) minimum (b) maximum (c) music (d) mobile
- 19.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) show the balance (b) savings stickers (c) pie-chart colours (d) export to a file
- 20.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) pick your bus stop (b) rate the driver (c) see where the bus is (d) show arrival time
- 21.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) pick a theme colour (b) earn stickers (c) share tasks to friends (d) see tasks by day
-
22.🗒️ Version 1 of a homework planner must be ready in 9 days. How many days are left for extras after the must-haves?
add a homework task: 4 days
set a due date: 2 days
see tasks by day: 3 days -
23.🗒️ Version 1 of a homework planner must be ready in 13 days. How many days are left for extras after the must-haves?
add a homework task: 4 days
set a due date: 1 days
see tasks by day: 4 days - 24.🗒️ The first small, working version of an app is often called an ___. (a) MVP (b) URL (c) FAQ (d) CPU
-
25.🗒️ Version 1 of a bus tracker must be ready in 10 days. How many days are left for extras after the must-haves?
see where the bus is: 2 days
show arrival time: 3 days
pick your bus stop: 4 days - 26.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) background music (b) confetti effects (c) show a question (d) an avatar shop
- 27.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) share your streak (b) log a glass of water (c) see today’s total (d) set a reminder time
- 28.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) add a homework task (b) set a due date (c) see tasks by day (d) earn stickers
- 29.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) check the answer (b) show a question (c) show the score (d) background music
-
30.🗒️ Version 1 of a quiz app must be ready in 18 days. How many days are left for extras after the must-haves?
show a question: 4 days
check the answer: 4 days
show the score: 5 days -
31.🗒️ Version 1 of a quiz app must be ready in 14 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 3 days
show the score: 5 days - 32.🗒️ Why keep version 1 small? (a) to confuse users (b) to learn from users soon (c) to look bigger (d) to use up storage
- 33.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) a dark mode (b) pick your bus stop (c) see where the bus is (d) show arrival time
-
34.🗒️ Version 1 of a homework planner must be ready in 12 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 1 days
see tasks by day: 3 days - 35.🗒️ What is a must-have feature? (a) a colour theme (b) one the app cannot skip (c) a nice extra (d) a sound effect
-
36.🗒️ Version 1 of a pocket-money tracker must be ready in 16 days. How many days are left for extras after the must-haves?
add money received: 2 days
add money spent: 3 days
show the balance: 5 days -
37.🗒️ Version 1 of a pocket-money tracker must be ready in 8 days. How many days are left for extras after the must-haves?
add money received: 3 days
add money spent: 1 days
show the balance: 4 days -
38.🗒️ Version 1 of a water reminder must be ready in 9 days. How many days are left for extras after the must-haves?
set a reminder time: 2 days
log a glass of water: 1 days
see today’s total: 2 days -
39.🗒️ Version 1 of a quiz app must be ready in 11 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 3 days
show the score: 2 days -
40.🗒️ Version 1 of a homework planner must be ready in 12 days. How many days are left for extras after the must-haves?
add a homework task: 4 days
set a due date: 4 days
see tasks by day: 2 days
Answer key
- show arrival time
- after the must-haves
- pie-chart colours
- add money received
- confetti effects
- water animations
- share tasks to friends
- 5
- add money spent
- export to a file
- 3
- add a homework task
- 1
- 5
- 6
- show the score
- custom alert sounds
- minimum
- show the balance
- rate the driver
- see tasks by day
- 0
- 4
- MVP
- 1
- show a question
- share your streak
- earn stickers
- background music
- 5
- 5
- to learn from users soon
- a dark mode
- 5
- one the app cannot skip
- 6
- 0
- 4
- 5
- 2
Free app development lessons, practice and worksheets at talentjr.in/app-development-for-students