App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
-
1.🗒️ Version 1 of a quiz app must be ready in 4 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 1 days
show the score: 2 days - 2.🗒️ In MVP, the M stands for ___. (a) mobile (b) maximum (c) minimum (d) music
- 3.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) confetti effects (b) show a question (c) show the score (d) check the answer
-
4.🗒️ Version 1 of a bus tracker must be ready in 15 days. How many days are left for extras after the must-haves?
see where the bus is: 3 days
show arrival time: 4 days
pick your bus stop: 5 days - 5.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) show the balance (b) pie-chart colours (c) export to a file (d) savings stickers
- 6.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) an avatar shop (b) confetti effects (c) show the score (d) background music
-
7.🗒️ Version 1 of a pocket-money tracker must be ready in 13 days. How many days are left for extras after the must-haves?
add money received: 4 days
add money spent: 1 days
show the balance: 4 days - 8.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) check the answer (b) an avatar shop (c) confetti effects (d) background music
- 9.🗒️ The first small, working version of an app is often called an ___. (a) FAQ (b) MVP (c) CPU (d) URL
- 10.🗒️ When should nice-to-have features be built? (a) after the must-haves (b) before anything (c) never (d) on day one
-
11.🗒️ Version 1 of a bus tracker must be ready in 13 days. How many days are left for extras after the must-haves?
see where the bus is: 4 days
show arrival time: 4 days
pick your bus stop: 2 days - 12.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) custom alert sounds (b) see today’s total (c) share your streak (d) water animations
- 13.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show a question (b) show the score (c) check the answer (d) background music
- 14.🗒️ A to-do app with no “add a task” feature is ___. (a) a nice extra (b) ready to release (c) well planned (d) missing a must-have
-
15.🗒️ Version 1 of a homework planner must be ready in 16 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 4 days
see tasks by day: 3 days -
16.🗒️ Version 1 of a homework planner must be ready in 10 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 1 days
see tasks by day: 2 days - 17.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) pick a theme colour (b) earn stickers (c) share tasks to friends (d) set a due date
- 18.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) see where the bus is (b) show arrival time (c) pick your bus stop (d) change the bus icon
- 19.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) rate the driver (b) change the bus icon (c) a dark mode (d) pick your bus stop
- 20.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) set a due date (b) earn stickers (c) add a homework task (d) see tasks by day
-
21.🗒️ Version 1 of a quiz app must be ready in 8 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 1 days
show the score: 2 days -
22.🗒️ Version 1 of a bus tracker must be ready in 11 days. How many days are left for extras after the must-haves?
see where the bus is: 1 days
show arrival time: 1 days
pick your bus stop: 3 days - 23.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) a dark mode (b) change the bus icon (c) rate the driver (d) show arrival time
- 24.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) custom alert sounds (b) set a reminder time (c) share your streak (d) water animations
- 25.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) see where the bus is (b) a dark mode (c) pick your bus stop (d) show arrival time
-
26.🗒️ Version 1 of a homework planner must be ready in 8 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 2 days
see tasks by day: 5 days -
27.🗒️ Version 1 of a homework planner must be ready in 11 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 3 days
see tasks by day: 5 days - 28.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) export to a file (b) add money received (c) savings stickers (d) pie-chart colours
-
29.🗒️ Version 1 of a water reminder must be ready in 12 days. How many days are left for extras after the must-haves?
set a reminder time: 3 days
log a glass of water: 4 days
see today’s total: 3 days -
30.🗒️ Version 1 of a pocket-money tracker must be ready in 10 days. How many days are left for extras after the must-haves?
add money received: 1 days
add money spent: 4 days
show the balance: 3 days - 31.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) share tasks to friends (b) add a homework task (c) see tasks by day (d) set a due date
- 32.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) show a question (b) confetti effects (c) an avatar shop (d) background music
-
33.🗒️ Version 1 of a pocket-money tracker must be ready in 10 days. How many days are left for extras after the must-haves?
add money received: 2 days
add money spent: 3 days
show the balance: 2 days - 34.🗒️ Why keep version 1 small? (a) to use up storage (b) to look bigger (c) to learn from users soon (d) to confuse users
- 35.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) water animations (b) set a reminder time (c) log a glass of water (d) see today’s total
- 36.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) custom alert sounds (b) log a glass of water (c) water animations (d) share your streak
-
37.🗒️ Version 1 of a homework planner must be ready in 11 days. How many days are left for extras after the must-haves?
add a homework task: 4 days
set a due date: 4 days
see tasks by day: 3 days -
38.🗒️ Version 1 of a homework planner must be ready in 10 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 1 days
see tasks by day: 4 days -
39.🗒️ Version 1 of a homework planner must be ready in 10 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 4 days
see tasks by day: 3 days -
40.🗒️ Version 1 of a homework planner must be ready in 9 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 1 days
see tasks by day: 5 days
Answer key
- 0
- minimum
- confetti effects
- 3
- show the balance
- show the score
- 4
- check the answer
- MVP
- after the must-haves
- 3
- see today’s total
- background music
- missing a must-have
- 6
- 5
- set a due date
- change the bus icon
- pick your bus stop
- earn stickers
- 4
- 6
- show arrival time
- set a reminder time
- a dark mode
- 0
- 0
- add money received
- 2
- 2
- share tasks to friends
- show a question
- 3
- to learn from users soon
- water animations
- log a glass of water
- 0
- 2
- 0
- 0
Free app development lessons, practice and worksheets at talentjr.in/app-development-for-students