App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
- 1.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) confetti effects (b) an avatar shop (c) background music (d) show the score
-
2.🗒️ Version 1 of a bus tracker must be ready in 12 days. How many days are left for extras after the must-haves?
see where the bus is: 2 days
show arrival time: 4 days
pick your bus stop: 3 days -
3.🗒️ Version 1 of a water reminder must be ready in 9 days. How many days are left for extras after the must-haves?
set a reminder time: 1 days
log a glass of water: 1 days
see today’s total: 3 days - 4.🗒️ When should nice-to-have features be built? (a) on day one (b) never (c) before anything (d) after the must-haves
- 5.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) earn stickers (b) see tasks by day (c) pick a theme colour (d) share tasks to friends
-
6.🗒️ Version 1 of a pocket-money tracker must be ready in 9 days. How many days are left for extras after the must-haves?
add money received: 2 days
add money spent: 3 days
show the balance: 4 days - 7.🗒️ What is a must-have feature? (a) one the app cannot skip (b) a nice extra (c) a colour theme (d) a sound effect
- 8.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) export to a file (b) add money spent (c) show the balance (d) add money received
- 9.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) savings stickers (b) show the balance (c) export to a file (d) pie-chart colours
- 10.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) change the bus icon (b) rate the driver (c) a dark mode (d) see where the bus is
-
11.🗒️ Version 1 of a pocket-money tracker must be ready in 7 days. How many days are left for extras after the must-haves?
add money received: 1 days
add money spent: 1 days
show the balance: 4 days - 12.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) log a glass of water (b) see today’s total (c) set a reminder time (d) water animations
- 13.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) share tasks to friends (b) earn stickers (c) pick a theme colour (d) add a homework task
- 14.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) custom alert sounds (b) water animations (c) set a reminder time (d) share your streak
-
15.🗒️ Version 1 of a homework planner must be ready in 14 days. How many days are left for extras after the must-haves?
add a homework task: 4 days
set a due date: 1 days
see tasks by day: 3 days -
16.🗒️ Version 1 of a homework planner must be ready in 10 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 4 days
see tasks by day: 2 days - 17.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show a question (b) check the answer (c) show the score (d) confetti effects
- 18.🗒️ Why keep version 1 small? (a) to confuse users (b) to learn from users soon (c) to look bigger (d) to use up storage
- 19.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) custom alert sounds (b) share your streak (c) see today’s total (d) water animations
- 20.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) share your streak (b) log a glass of water (c) see today’s total (d) set a reminder time
-
21.🗒️ Version 1 of a homework planner must be ready in 11 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 2 days
see tasks by day: 2 days -
22.🗒️ Version 1 of a bus tracker must be ready in 8 days. How many days are left for extras after the must-haves?
see where the bus is: 1 days
show arrival time: 2 days
pick your bus stop: 4 days -
23.🗒️ Version 1 of a bus tracker must be ready in 12 days. How many days are left for extras after the must-haves?
see where the bus is: 4 days
show arrival time: 2 days
pick your bus stop: 5 days -
24.🗒️ Version 1 of a pocket-money tracker must be ready in 12 days. How many days are left for extras after the must-haves?
add money received: 2 days
add money spent: 3 days
show the balance: 3 days - 25.🗒️ The first small, working version of an app is often called an ___. (a) URL (b) CPU (c) FAQ (d) MVP
-
26.🗒️ Version 1 of a water reminder must be ready in 8 days. How many days are left for extras after the must-haves?
set a reminder time: 1 days
log a glass of water: 1 days
see today’s total: 3 days - 27.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) an avatar shop (b) check the answer (c) confetti effects (d) background music
- 28.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money spent (b) show the balance (c) add money received (d) pie-chart colours
- 29.🗒️ A to-do app with no “add a task” feature is ___. (a) a nice extra (b) ready to release (c) well planned (d) missing a must-have
- 30.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) show the balance (b) add money received (c) savings stickers (d) add money spent
-
31.🗒️ Version 1 of a quiz app must be ready in 13 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 4 days
show the score: 4 days - 32.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) add money spent (b) savings stickers (c) export to a file (d) pie-chart colours
-
33.🗒️ Version 1 of a bus tracker must be ready in 16 days. How many days are left for extras after the must-haves?
see where the bus is: 2 days
show arrival time: 4 days
pick your bus stop: 4 days - 34.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show a question (b) an avatar shop (c) show the score (d) check the answer
-
35.🗒️ Version 1 of a bus tracker must be ready in 13 days. How many days are left for extras after the must-haves?
see where the bus is: 1 days
show arrival time: 3 days
pick your bus stop: 5 days -
36.🗒️ Version 1 of a pocket-money tracker must be ready in 14 days. How many days are left for extras after the must-haves?
add money received: 4 days
add money spent: 3 days
show the balance: 4 days -
37.🗒️ Version 1 of a quiz app must be ready in 10 days. How many days are left for extras after the must-haves?
show a question: 3 days
check the answer: 2 days
show the score: 2 days -
38.🗒️ Version 1 of a pocket-money tracker must be ready in 14 days. How many days are left for extras after the must-haves?
add money received: 1 days
add money spent: 3 days
show the balance: 5 days - 39.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) log a glass of water (b) water animations (c) custom alert sounds (d) share your streak
-
40.🗒️ Version 1 of a quiz app must be ready in 14 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 2 days
show the score: 5 days
Answer key
- show the score
- 3
- 4
- after the must-haves
- see tasks by day
- 0
- one the app cannot skip
- export to a file
- show the balance
- see where the bus is
- 1
- water animations
- add a homework task
- set a reminder time
- 6
- 3
- confetti effects
- to learn from users soon
- see today’s total
- share your streak
- 6
- 1
- 1
- 4
- MVP
- 3
- check the answer
- pie-chart colours
- missing a must-have
- savings stickers
- 4
- add money spent
- 6
- an avatar shop
- 4
- 3
- 3
- 5
- log a glass of water
- 6
Free app development lessons, practice and worksheets at talentjr.in/app-development-for-students