App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
-
1.🗒️ Version 1 of a homework planner must be ready in 8 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 3 days
see tasks by day: 2 days - 2.🗒️ When should nice-to-have features be built? (a) on day one (b) after the must-haves (c) before anything (d) never
-
3.🗒️ Version 1 of a bus tracker must be ready in 14 days. How many days are left for extras after the must-haves?
see where the bus is: 1 days
show arrival time: 4 days
pick your bus stop: 4 days -
4.🗒️ Version 1 of a quiz app must be ready in 15 days. How many days are left for extras after the must-haves?
show a question: 3 days
check the answer: 1 days
show the score: 5 days - 5.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) show the balance (b) pie-chart colours (c) savings stickers (d) export to a file
-
6.🗒️ Version 1 of a pocket-money tracker must be ready in 9 days. How many days are left for extras after the must-haves?
add money received: 3 days
add money spent: 1 days
show the balance: 4 days -
7.🗒️ Version 1 of a pocket-money tracker must be ready in 12 days. How many days are left for extras after the must-haves?
add money received: 3 days
add money spent: 4 days
show the balance: 5 days - 8.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) water animations (b) set a reminder time (c) see today’s total (d) log a glass of water
- 9.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) confetti effects (b) show the score (c) an avatar shop (d) background music
- 10.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) water animations (b) set a reminder time (c) share your streak (d) custom alert sounds
- 11.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) share your streak (b) see today’s total (c) log a glass of water (d) set a reminder time
- 12.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) show a question (b) background music (c) confetti effects (d) an avatar shop
-
13.🗒️ Version 1 of a bus tracker must be ready in 12 days. How many days are left for extras after the must-haves?
see where the bus is: 4 days
show arrival time: 1 days
pick your bus stop: 4 days - 14.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) see tasks by day (b) set a due date (c) pick a theme colour (d) add a homework task
- 15.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) log a glass of water (b) see today’s total (c) set a reminder time (d) custom alert sounds
-
16.🗒️ Version 1 of a bus tracker must be ready in 9 days. How many days are left for extras after the must-haves?
see where the bus is: 4 days
show arrival time: 1 days
pick your bus stop: 2 days - 17.🗒️ A to-do app with no “add a task” feature is ___. (a) ready to release (b) missing a must-have (c) well planned (d) a nice extra
- 18.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) background music (b) confetti effects (c) check the answer (d) an avatar shop
-
19.🗒️ Version 1 of a bus tracker must be ready in 16 days. How many days are left for extras after the must-haves?
see where the bus is: 4 days
show arrival time: 4 days
pick your bus stop: 2 days - 20.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) show arrival time (b) pick your bus stop (c) see where the bus is (d) a dark mode
- 21.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) pie-chart colours (b) savings stickers (c) export to a file (d) add money received
-
22.🗒️ Version 1 of a bus tracker must be ready in 9 days. How many days are left for extras after the must-haves?
see where the bus is: 3 days
show arrival time: 2 days
pick your bus stop: 2 days - 23.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show a question (b) check the answer (c) show the score (d) background music
- 24.🗒️ Why keep version 1 small? (a) to learn from users soon (b) to look bigger (c) to confuse users (d) to use up storage
- 25.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money received (b) show the balance (c) pie-chart colours (d) add money spent
- 26.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) pick your bus stop (b) show arrival time (c) change the bus icon (d) see where the bus is
-
27.🗒️ Version 1 of a bus tracker must be ready in 6 days. How many days are left for extras after the must-haves?
see where the bus is: 2 days
show arrival time: 1 days
pick your bus stop: 2 days - 28.🗒️ The first small, working version of an app is often called an ___. (a) CPU (b) URL (c) FAQ (d) MVP
-
29.🗒️ Version 1 of a water reminder must be ready in 16 days. How many days are left for extras after the must-haves?
set a reminder time: 4 days
log a glass of water: 2 days
see today’s total: 4 days -
30.🗒️ Version 1 of a quiz app must be ready in 6 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 2 days
show the score: 2 days - 31.🗒️ In MVP, the M stands for ___. (a) mobile (b) music (c) minimum (d) maximum
-
32.🗒️ Version 1 of a pocket-money tracker must be ready in 12 days. How many days are left for extras after the must-haves?
add money received: 4 days
add money spent: 1 days
show the balance: 2 days - 33.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) add a homework task (b) pick a theme colour (c) earn stickers (d) share tasks to friends
-
34.🗒️ Version 1 of a bus tracker must be ready in 15 days. How many days are left for extras after the must-haves?
see where the bus is: 2 days
show arrival time: 3 days
pick your bus stop: 4 days - 35.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) a dark mode (b) rate the driver (c) pick your bus stop (d) change the bus icon
- 36.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) custom alert sounds (b) share your streak (c) water animations (d) see today’s total
-
37.🗒️ Version 1 of a pocket-money tracker must be ready in 14 days. How many days are left for extras after the must-haves?
add money received: 1 days
add money spent: 4 days
show the balance: 5 days - 38.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) earn stickers (b) see tasks by day (c) share tasks to friends (d) pick a theme colour
-
39.🗒️ Version 1 of a bus tracker must be ready in 11 days. How many days are left for extras after the must-haves?
see where the bus is: 2 days
show arrival time: 2 days
pick your bus stop: 5 days -
40.🗒️ Version 1 of a quiz app must be ready in 16 days. How many days are left for extras after the must-haves?
show a question: 4 days
check the answer: 3 days
show the score: 5 days
Answer key
- 2
- after the must-haves
- 5
- 6
- show the balance
- 1
- 0
- water animations
- show the score
- set a reminder time
- share your streak
- show a question
- 3
- pick a theme colour
- custom alert sounds
- 2
- missing a must-have
- check the answer
- 6
- a dark mode
- add money received
- 2
- background music
- to learn from users soon
- pie-chart colours
- change the bus icon
- 1
- MVP
- 6
- 1
- minimum
- 5
- add a homework task
- 6
- pick your bus stop
- see today’s total
- 4
- see tasks by day
- 2
- 4
Free app development lessons, practice and worksheets at talentjr.in/app-development-for-students