App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
- 1.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) see tasks by day (b) set a due date (c) add a homework task (d) pick a theme colour
-
2.🗒️ Version 1 of a pocket-money tracker must be ready in 12 days. How many days are left for extras after the must-haves?
add money received: 2 days
add money spent: 3 days
show the balance: 3 days - 3.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) change the bus icon (b) rate the driver (c) a dark mode (d) see where the bus is
- 4.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show the score (b) confetti effects (c) show a question (d) check the answer
- 5.🗒️ What is a must-have feature? (a) a nice extra (b) a sound effect (c) one the app cannot skip (d) a colour theme
-
6.🗒️ Version 1 of a water reminder must be ready in 12 days. How many days are left for extras after the must-haves?
set a reminder time: 3 days
log a glass of water: 4 days
see today’s total: 4 days - 7.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) a dark mode (b) change the bus icon (c) pick your bus stop (d) rate the driver
- 8.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money spent (b) add money received (c) pie-chart colours (d) show the balance
- 9.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) check the answer (b) show the score (c) background music (d) show a question
-
10.🗒️ Version 1 of a homework planner must be ready in 9 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 4 days
see tasks by day: 2 days - 11.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) set a reminder time (b) share your streak (c) see today’s total (d) log a glass of water
- 12.🗒️ The first small, working version of an app is often called an ___. (a) MVP (b) CPU (c) FAQ (d) URL
- 13.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) export to a file (b) savings stickers (c) add money received (d) pie-chart colours
- 14.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) share tasks to friends (b) pick a theme colour (c) earn stickers (d) add a homework task
-
15.🗒️ Version 1 of a water reminder must be ready in 9 days. How many days are left for extras after the must-haves?
set a reminder time: 2 days
log a glass of water: 4 days
see today’s total: 3 days - 16.🗒️ Why keep version 1 small? (a) to confuse users (b) to use up storage (c) to learn from users soon (d) to look bigger
-
17.🗒️ Version 1 of a homework planner must be ready in 8 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 4 days
see tasks by day: 2 days -
18.🗒️ Version 1 of a quiz app must be ready in 13 days. How many days are left for extras after the must-haves?
show a question: 4 days
check the answer: 4 days
show the score: 5 days -
19.🗒️ Version 1 of a bus tracker must be ready in 10 days. How many days are left for extras after the must-haves?
see where the bus is: 3 days
show arrival time: 1 days
pick your bus stop: 3 days - 20.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) a dark mode (b) see where the bus is (c) show arrival time (d) pick your bus stop
- 21.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) show the balance (b) export to a file (c) pie-chart colours (d) savings stickers
- 22.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) water animations (b) share your streak (c) see today’s total (d) custom alert sounds
-
23.🗒️ Version 1 of a homework planner must be ready in 11 days. How many days are left for extras after the must-haves?
add a homework task: 4 days
set a due date: 4 days
see tasks by day: 3 days - 24.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) earn stickers (b) pick a theme colour (c) share tasks to friends (d) set a due date
-
25.🗒️ Version 1 of a water reminder must be ready in 8 days. How many days are left for extras after the must-haves?
set a reminder time: 3 days
log a glass of water: 1 days
see today’s total: 3 days -
26.🗒️ Version 1 of a quiz app must be ready in 12 days. How many days are left for extras after the must-haves?
show a question: 3 days
check the answer: 3 days
show the score: 4 days - 27.🗒️ A to-do app with no “add a task” feature is ___. (a) a nice extra (b) missing a must-have (c) ready to release (d) well planned
- 28.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) change the bus icon (b) pick your bus stop (c) show arrival time (d) see where the bus is
- 29.🗒️ In MVP, the M stands for ___. (a) mobile (b) music (c) maximum (d) minimum
-
30.🗒️ Version 1 of a homework planner must be ready in 14 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 3 days
see tasks by day: 2 days - 31.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) an avatar shop (b) confetti effects (c) show a question (d) background music
-
32.🗒️ Version 1 of a bus tracker must be ready in 10 days. How many days are left for extras after the must-haves?
see where the bus is: 4 days
show arrival time: 3 days
pick your bus stop: 3 days -
33.🗒️ Version 1 of a quiz app must be ready in 12 days. How many days are left for extras after the must-haves?
show a question: 4 days
check the answer: 2 days
show the score: 2 days - 34.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) see where the bus is (b) show arrival time (c) rate the driver (d) pick your bus stop
- 35.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show the score (b) show a question (c) check the answer (d) an avatar shop
- 36.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) change the bus icon (b) rate the driver (c) show arrival time (d) a dark mode
-
37.🗒️ Version 1 of a quiz app must be ready in 4 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 1 days
show the score: 2 days - 38.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) set a reminder time (b) see today’s total (c) water animations (d) log a glass of water
-
39.🗒️ Version 1 of a water reminder must be ready in 12 days. How many days are left for extras after the must-haves?
set a reminder time: 2 days
log a glass of water: 4 days
see today’s total: 3 days - 40.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) share your streak (b) custom alert sounds (c) water animations (d) set a reminder time
Answer key
- pick a theme colour
- 4
- see where the bus is
- confetti effects
- one the app cannot skip
- 1
- pick your bus stop
- pie-chart colours
- background music
- 0
- share your streak
- MVP
- add money received
- add a homework task
- 0
- to learn from users soon
- 0
- 0
- 3
- a dark mode
- show the balance
- see today’s total
- 0
- set a due date
- 1
- 2
- missing a must-have
- change the bus icon
- minimum
- 6
- show a question
- 0
- 4
- rate the driver
- an avatar shop
- show arrival time
- 0
- water animations
- 3
- set a reminder time
Free app development lessons, practice and worksheets at talentjr.in/app-development-for-students