App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
-
1.🗒️ Version 1 of a pocket-money tracker must be ready in 10 days. How many days are left for extras after the must-haves?
add money received: 2 days
add money spent: 4 days
show the balance: 4 days - 2.🗒️ When should nice-to-have features be built? (a) never (b) after the must-haves (c) on day one (d) before anything
- 3.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) rate the driver (b) see where the bus is (c) a dark mode (d) change the bus icon
- 4.🗒️ The first small, working version of an app is often called an ___. (a) CPU (b) FAQ (c) URL (d) MVP
-
5.🗒️ Version 1 of a homework planner must be ready in 11 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 4 days
see tasks by day: 2 days - 6.🗒️ Why keep version 1 small? (a) to confuse users (b) to learn from users soon (c) to look bigger (d) to use up storage
- 7.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) share tasks to friends (b) set a due date (c) see tasks by day (d) add a homework task
-
8.🗒️ Version 1 of a homework planner must be ready in 11 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 4 days
see tasks by day: 3 days - 9.🗒️ In MVP, the M stands for ___. (a) music (b) maximum (c) minimum (d) mobile
-
10.🗒️ Version 1 of a homework planner must be ready in 13 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 2 days
see tasks by day: 4 days -
11.🗒️ Version 1 of a bus tracker must be ready in 13 days. How many days are left for extras after the must-haves?
see where the bus is: 1 days
show arrival time: 2 days
pick your bus stop: 5 days - 12.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) an avatar shop (b) show a question (c) check the answer (d) show the score
- 13.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) change the bus icon (b) pick your bus stop (c) rate the driver (d) a dark mode
- 14.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) earn stickers (b) add a homework task (c) share tasks to friends (d) pick a theme colour
-
15.🗒️ Version 1 of a quiz app must be ready in 7 days. How many days are left for extras after the must-haves?
show a question: 2 days
check the answer: 1 days
show the score: 2 days -
16.🗒️ Version 1 of a homework planner must be ready in 14 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 2 days
see tasks by day: 5 days - 17.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) see tasks by day (b) add a homework task (c) set a due date (d) pick a theme colour
-
18.🗒️ Version 1 of a quiz app must be ready in 11 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 2 days
show the score: 4 days - 19.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) share your streak (b) water animations (c) custom alert sounds (d) set a reminder time
-
20.🗒️ Version 1 of a pocket-money tracker must be ready in 12 days. How many days are left for extras after the must-haves?
add money received: 1 days
add money spent: 2 days
show the balance: 5 days - 21.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) see where the bus is (b) a dark mode (c) pick your bus stop (d) show arrival time
- 22.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) share tasks to friends (b) earn stickers (c) pick a theme colour (d) see tasks by day
- 23.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) water animations (b) custom alert sounds (c) share your streak (d) see today’s total
- 24.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) export to a file (b) pie-chart colours (c) savings stickers (d) add money received
- 25.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) pie-chart colours (b) savings stickers (c) export to a file (d) add money spent
- 26.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) set a reminder time (b) log a glass of water (c) see today’s total (d) water animations
- 27.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) savings stickers (b) pie-chart colours (c) show the balance (d) export to a file
- 28.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) show the score (b) an avatar shop (c) background music (d) confetti effects
- 29.🗒️ A to-do app with no “add a task” feature is ___. (a) well planned (b) ready to release (c) a nice extra (d) missing a must-have
-
30.🗒️ Version 1 of a pocket-money tracker must be ready in 14 days. How many days are left for extras after the must-haves?
add money received: 4 days
add money spent: 4 days
show the balance: 3 days - 31.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) check the answer (b) show a question (c) confetti effects (d) show the score
- 32.🗒️ What is a must-have feature? (a) a sound effect (b) a colour theme (c) a nice extra (d) one the app cannot skip
- 33.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) show the balance (b) export to a file (c) add money spent (d) add money received
- 34.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) see tasks by day (b) set a due date (c) add a homework task (d) earn stickers
-
35.🗒️ Version 1 of a quiz app must be ready in 9 days. How many days are left for extras after the must-haves?
show a question: 2 days
check the answer: 3 days
show the score: 4 days -
36.🗒️ Version 1 of a quiz app must be ready in 12 days. How many days are left for extras after the must-haves?
show a question: 4 days
check the answer: 4 days
show the score: 3 days - 37.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) change the bus icon (b) show arrival time (c) rate the driver (d) a dark mode
- 38.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show the score (b) show a question (c) check the answer (d) background music
-
39.🗒️ Version 1 of a bus tracker must be ready in 9 days. How many days are left for extras after the must-haves?
see where the bus is: 1 days
show arrival time: 1 days
pick your bus stop: 4 days - 40.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) set a due date (b) earn stickers (c) share tasks to friends (d) pick a theme colour
Answer key
- 0
- after the must-haves
- see where the bus is
- MVP
- 2
- to learn from users soon
- share tasks to friends
- 3
- minimum
- 5
- 5
- an avatar shop
- pick your bus stop
- add a homework task
- 2
- 6
- pick a theme colour
- 4
- set a reminder time
- 4
- a dark mode
- see tasks by day
- see today’s total
- add money received
- add money spent
- water animations
- show the balance
- show the score
- missing a must-have
- 3
- confetti effects
- one the app cannot skip
- export to a file
- earn stickers
- 0
- 1
- show arrival time
- background music
- 3
- set a due date