App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
- 1.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) water animations (b) custom alert sounds (c) set a reminder time (d) share your streak
- 2.🗒️ A to-do app with no “add a task” feature is ___. (a) ready to release (b) well planned (c) missing a must-have (d) a nice extra
- 3.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) export to a file (b) pie-chart colours (c) savings stickers (d) add money received
-
4.🗒️ Version 1 of a homework planner must be ready in 9 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 1 days
see tasks by day: 4 days - 5.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) confetti effects (b) background music (c) show the score (d) an avatar shop
-
6.🗒️ Version 1 of a homework planner must be ready in 11 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 3 days
see tasks by day: 3 days - 7.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) show a question (b) background music (c) confetti effects (d) an avatar shop
- 8.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) set a reminder time (b) log a glass of water (c) custom alert sounds (d) see today’s total
- 9.🗒️ The first small, working version of an app is often called an ___. (a) CPU (b) MVP (c) URL (d) FAQ
-
10.🗒️ Version 1 of a quiz app must be ready in 7 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 3 days
show the score: 2 days -
11.🗒️ Version 1 of a quiz app must be ready in 12 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 3 days
show the score: 3 days - 12.🗒️ When should nice-to-have features be built? (a) before anything (b) after the must-haves (c) never (d) on day one
- 13.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) share tasks to friends (b) pick a theme colour (c) earn stickers (d) set a due date
-
14.🗒️ Version 1 of a water reminder must be ready in 14 days. How many days are left for extras after the must-haves?
set a reminder time: 3 days
log a glass of water: 3 days
see today’s total: 2 days - 15.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money received (b) add money spent (c) show the balance (d) pie-chart colours
- 16.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) earn stickers (b) see tasks by day (c) add a homework task (d) set a due date
- 17.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) see tasks by day (b) add a homework task (c) pick a theme colour (d) set a due date
- 18.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) export to a file (b) savings stickers (c) pie-chart colours (d) add money spent
- 19.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) a dark mode (b) see where the bus is (c) rate the driver (d) change the bus icon
-
20.🗒️ Version 1 of a bus tracker must be ready in 11 days. How many days are left for extras after the must-haves?
see where the bus is: 3 days
show arrival time: 4 days
pick your bus stop: 3 days - 21.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) share tasks to friends (b) earn stickers (c) pick a theme colour (d) see tasks by day
- 22.🗒️ Why keep version 1 small? (a) to look bigger (b) to learn from users soon (c) to confuse users (d) to use up storage
- 23.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money spent (b) export to a file (c) show the balance (d) add money received
-
24.🗒️ Version 1 of a pocket-money tracker must be ready in 13 days. How many days are left for extras after the must-haves?
add money received: 3 days
add money spent: 2 days
show the balance: 2 days -
25.🗒️ Version 1 of a pocket-money tracker must be ready in 10 days. How many days are left for extras after the must-haves?
add money received: 4 days
add money spent: 2 days
show the balance: 2 days - 26.🗒️ What is a must-have feature? (a) one the app cannot skip (b) a sound effect (c) a nice extra (d) a colour theme
-
27.🗒️ Version 1 of a pocket-money tracker must be ready in 12 days. How many days are left for extras after the must-haves?
add money received: 2 days
add money spent: 2 days
show the balance: 4 days -
28.🗒️ Version 1 of a pocket-money tracker must be ready in 16 days. How many days are left for extras after the must-haves?
add money received: 4 days
add money spent: 1 days
show the balance: 5 days -
29.🗒️ Version 1 of a quiz app must be ready in 10 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 3 days
show the score: 4 days -
30.🗒️ Version 1 of a homework planner must be ready in 9 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 1 days
see tasks by day: 5 days - 31.🗒️ In MVP, the M stands for ___. (a) music (b) mobile (c) minimum (d) maximum
-
32.🗒️ Version 1 of a homework planner must be ready in 11 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 3 days
see tasks by day: 3 days -
33.🗒️ Version 1 of a homework planner must be ready in 14 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 3 days
see tasks by day: 5 days - 34.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) water animations (b) set a reminder time (c) see today’s total (d) log a glass of water
- 35.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) pick your bus stop (b) change the bus icon (c) a dark mode (d) rate the driver
- 36.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) pick a theme colour (b) share tasks to friends (c) earn stickers (d) add a homework task
-
37.🗒️ Version 1 of a pocket-money tracker must be ready in 8 days. How many days are left for extras after the must-haves?
add money received: 3 days
add money spent: 2 days
show the balance: 3 days -
38.🗒️ Version 1 of a pocket-money tracker must be ready in 12 days. How many days are left for extras after the must-haves?
add money received: 2 days
add money spent: 1 days
show the balance: 5 days -
39.🗒️ Version 1 of a homework planner must be ready in 15 days. How many days are left for extras after the must-haves?
add a homework task: 4 days
set a due date: 4 days
see tasks by day: 2 days - 40.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) background music (b) check the answer (c) an avatar shop (d) confetti effects
Answer key
- set a reminder time
- missing a must-have
- add money received
- 1
- show the score
- 3
- show a question
- custom alert sounds
- MVP
- 1
- 5
- after the must-haves
- set a due date
- 6
- pie-chart colours
- earn stickers
- pick a theme colour
- add money spent
- see where the bus is
- 1
- see tasks by day
- to learn from users soon
- export to a file
- 6
- 2
- one the app cannot skip
- 4
- 6
- 2
- 0
- minimum
- 2
- 5
- water animations
- pick your bus stop
- add a homework task
- 0
- 4
- 5
- check the answer