App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
- 1.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) show the balance (b) export to a file (c) pie-chart colours (d) savings stickers
-
2.🗒️ Version 1 of a quiz app must be ready in 9 days. How many days are left for extras after the must-haves?
show a question: 3 days
check the answer: 2 days
show the score: 4 days - 3.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) set a due date (b) see tasks by day (c) add a homework task (d) earn stickers
- 4.🗒️ Why keep version 1 small? (a) to learn from users soon (b) to use up storage (c) to confuse users (d) to look bigger
- 5.🗒️ A to-do app with no “add a task” feature is ___. (a) well planned (b) a nice extra (c) ready to release (d) missing a must-have
- 6.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) share tasks to friends (b) add a homework task (c) pick a theme colour (d) earn stickers
- 7.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) log a glass of water (b) water animations (c) custom alert sounds (d) share your streak
- 8.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) a dark mode (b) rate the driver (c) show arrival time (d) change the bus icon
-
9.🗒️ Version 1 of a homework planner must be ready in 17 days. How many days are left for extras after the must-haves?
add a homework task: 4 days
set a due date: 3 days
see tasks by day: 4 days -
10.🗒️ Version 1 of a water reminder must be ready in 8 days. How many days are left for extras after the must-haves?
set a reminder time: 2 days
log a glass of water: 2 days
see today’s total: 4 days - 11.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) earn stickers (b) pick a theme colour (c) share tasks to friends (d) set a due date
-
12.🗒️ Version 1 of a quiz app must be ready in 11 days. How many days are left for extras after the must-haves?
show a question: 2 days
check the answer: 4 days
show the score: 4 days - 13.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show the score (b) show a question (c) background music (d) check the answer
-
14.🗒️ Version 1 of a pocket-money tracker must be ready in 7 days. How many days are left for extras after the must-haves?
add money received: 2 days
add money spent: 2 days
show the balance: 3 days -
15.🗒️ Version 1 of a bus tracker must be ready in 15 days. How many days are left for extras after the must-haves?
see where the bus is: 4 days
show arrival time: 3 days
pick your bus stop: 3 days - 16.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) an avatar shop (b) check the answer (c) show the score (d) show a question
-
17.🗒️ Version 1 of a quiz app must be ready in 13 days. How many days are left for extras after the must-haves?
show a question: 2 days
check the answer: 1 days
show the score: 4 days - 18.🗒️ What is a must-have feature? (a) a sound effect (b) a colour theme (c) one the app cannot skip (d) a nice extra
-
19.🗒️ Version 1 of a homework planner must be ready in 13 days. How many days are left for extras after the must-haves?
add a homework task: 4 days
set a due date: 1 days
see tasks by day: 2 days -
20.🗒️ Version 1 of a quiz app must be ready in 11 days. How many days are left for extras after the must-haves?
show a question: 2 days
check the answer: 2 days
show the score: 3 days - 21.🗒️ In MVP, the M stands for ___. (a) music (b) mobile (c) minimum (d) maximum
-
22.🗒️ Version 1 of a water reminder must be ready in 15 days. How many days are left for extras after the must-haves?
set a reminder time: 2 days
log a glass of water: 4 days
see today’s total: 5 days - 23.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) see where the bus is (b) a dark mode (c) show arrival time (d) pick your bus stop
- 24.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) background music (b) show a question (c) confetti effects (d) an avatar shop
-
25.🗒️ Version 1 of a bus tracker must be ready in 13 days. How many days are left for extras after the must-haves?
see where the bus is: 2 days
show arrival time: 2 days
pick your bus stop: 5 days - 26.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) show the balance (b) add money spent (c) savings stickers (d) add money received
-
27.🗒️ Version 1 of a pocket-money tracker must be ready in 14 days. How many days are left for extras after the must-haves?
add money received: 4 days
add money spent: 1 days
show the balance: 5 days -
28.🗒️ Version 1 of a bus tracker must be ready in 13 days. How many days are left for extras after the must-haves?
see where the bus is: 2 days
show arrival time: 3 days
pick your bus stop: 2 days - 29.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) savings stickers (b) pie-chart colours (c) export to a file (d) add money spent
- 30.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) see where the bus is (b) pick your bus stop (c) change the bus icon (d) show arrival time
-
31.🗒️ Version 1 of a pocket-money tracker must be ready in 13 days. How many days are left for extras after the must-haves?
add money received: 3 days
add money spent: 2 days
show the balance: 5 days - 32.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) pie-chart colours (b) add money spent (c) show the balance (d) add money received
-
33.🗒️ Version 1 of a bus tracker must be ready in 14 days. How many days are left for extras after the must-haves?
see where the bus is: 3 days
show arrival time: 4 days
pick your bus stop: 3 days -
34.🗒️ Version 1 of a water reminder must be ready in 15 days. How many days are left for extras after the must-haves?
set a reminder time: 4 days
log a glass of water: 3 days
see today’s total: 3 days - 35.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) change the bus icon (b) pick your bus stop (c) rate the driver (d) a dark mode
-
36.🗒️ Version 1 of a quiz app must be ready in 11 days. How many days are left for extras after the must-haves?
show a question: 3 days
check the answer: 4 days
show the score: 2 days - 37.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) show arrival time (b) see where the bus is (c) rate the driver (d) pick your bus stop
- 38.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) see today’s total (b) set a reminder time (c) log a glass of water (d) custom alert sounds
-
39.🗒️ Version 1 of a bus tracker must be ready in 10 days. How many days are left for extras after the must-haves?
see where the bus is: 4 days
show arrival time: 1 days
pick your bus stop: 2 days - 40.🗒️ The first small, working version of an app is often called an ___. (a) CPU (b) MVP (c) URL (d) FAQ
Answer key
- show the balance
- 0
- earn stickers
- to learn from users soon
- missing a must-have
- add a homework task
- log a glass of water
- show arrival time
- 6
- 0
- set a due date
- 1
- background music
- 0
- 5
- an avatar shop
- 6
- one the app cannot skip
- 6
- 4
- minimum
- 4
- a dark mode
- show a question
- 4
- savings stickers
- 4
- 6
- add money spent
- change the bus icon
- 3
- pie-chart colours
- 4
- 5
- pick your bus stop
- 2
- rate the driver
- custom alert sounds
- 3
- MVP