App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
- 1.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) background music (b) confetti effects (c) an avatar shop (d) show a question
- 2.🗒️ In MVP, the M stands for ___. (a) music (b) maximum (c) mobile (d) minimum
-
3.🗒️ Version 1 of a quiz app must be ready in 12 days. How many days are left for extras after the must-haves?
show a question: 2 days
check the answer: 3 days
show the score: 5 days - 4.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) pick a theme colour (b) earn stickers (c) share tasks to friends (d) add a homework task
- 5.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) confetti effects (b) show the score (c) show a question (d) check the answer
- 6.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) share your streak (b) custom alert sounds (c) water animations (d) see today’s total
- 7.🗒️ What is a must-have feature? (a) a nice extra (b) a sound effect (c) a colour theme (d) one the app cannot skip
- 8.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) an avatar shop (b) confetti effects (c) check the answer (d) background music
- 9.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) share your streak (b) set a reminder time (c) see today’s total (d) log a glass of water
- 10.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) change the bus icon (b) see where the bus is (c) a dark mode (d) rate the driver
- 11.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) pick a theme colour (b) share tasks to friends (c) earn stickers (d) see tasks by day
- 12.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) see tasks by day (b) add a homework task (c) set a due date (d) share tasks to friends
- 13.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) pie-chart colours (b) export to a file (c) savings stickers (d) add money received
-
14.🗒️ Version 1 of a bus tracker must be ready in 11 days. How many days are left for extras after the must-haves?
see where the bus is: 3 days
show arrival time: 2 days
pick your bus stop: 5 days - 15.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) show the balance (b) add money received (c) pie-chart colours (d) add money spent
- 16.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) set a due date (b) pick a theme colour (c) add a homework task (d) see tasks by day
-
17.🗒️ Version 1 of a bus tracker must be ready in 15 days. How many days are left for extras after the must-haves?
see where the bus is: 3 days
show arrival time: 3 days
pick your bus stop: 4 days - 18.🗒️ Why keep version 1 small? (a) to look bigger (b) to use up storage (c) to confuse users (d) to learn from users soon
- 19.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) a dark mode (b) pick your bus stop (c) rate the driver (d) change the bus icon
- 20.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) log a glass of water (b) set a reminder time (c) water animations (d) see today’s total
- 21.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) set a due date (b) see tasks by day (c) add a homework task (d) earn stickers
- 22.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) see where the bus is (b) show arrival time (c) a dark mode (d) pick your bus stop
-
23.🗒️ Version 1 of a quiz app must be ready in 9 days. How many days are left for extras after the must-haves?
show a question: 3 days
check the answer: 2 days
show the score: 3 days -
24.🗒️ Version 1 of a bus tracker must be ready in 16 days. How many days are left for extras after the must-haves?
see where the bus is: 3 days
show arrival time: 3 days
pick your bus stop: 5 days -
25.🗒️ Version 1 of a quiz app must be ready in 11 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 1 days
show the score: 4 days -
26.🗒️ Version 1 of a pocket-money tracker must be ready in 12 days. How many days are left for extras after the must-haves?
add money received: 1 days
add money spent: 1 days
show the balance: 4 days - 27.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) export to a file (b) savings stickers (c) pie-chart colours (d) show the balance
- 28.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show a question (b) show the score (c) check the answer (d) an avatar shop
- 29.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money spent (b) export to a file (c) show the balance (d) add money received
- 30.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) confetti effects (b) an avatar shop (c) background music (d) show the score
- 31.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) water animations (b) custom alert sounds (c) set a reminder time (d) share your streak
- 32.🗒️ A to-do app with no “add a task” feature is ___. (a) well planned (b) a nice extra (c) missing a must-have (d) ready to release
- 33.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) savings stickers (b) add money received (c) show the balance (d) add money spent
- 34.🗒️ The first small, working version of an app is often called an ___. (a) CPU (b) URL (c) FAQ (d) MVP
-
35.🗒️ Version 1 of a bus tracker must be ready in 10 days. How many days are left for extras after the must-haves?
see where the bus is: 2 days
show arrival time: 1 days
pick your bus stop: 2 days -
36.🗒️ Version 1 of a quiz app must be ready in 16 days. How many days are left for extras after the must-haves?
show a question: 2 days
check the answer: 4 days
show the score: 4 days - 37.🗒️ When should nice-to-have features be built? (a) on day one (b) never (c) after the must-haves (d) before anything
-
38.🗒️ Version 1 of a bus tracker must be ready in 8 days. How many days are left for extras after the must-haves?
see where the bus is: 1 days
show arrival time: 2 days
pick your bus stop: 2 days - 39.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) custom alert sounds (b) log a glass of water (c) share your streak (d) water animations
-
40.🗒️ Version 1 of a quiz app must be ready in 12 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 2 days
show the score: 4 days
Answer key
- show a question
- minimum
- 2
- add a homework task
- confetti effects
- see today’s total
- one the app cannot skip
- check the answer
- share your streak
- see where the bus is
- see tasks by day
- share tasks to friends
- add money received
- 1
- pie-chart colours
- pick a theme colour
- 5
- to learn from users soon
- pick your bus stop
- water animations
- earn stickers
- a dark mode
- 1
- 5
- 5
- 6
- show the balance
- an avatar shop
- export to a file
- show the score
- set a reminder time
- missing a must-have
- savings stickers
- MVP
- 5
- 6
- after the must-haves
- 3
- log a glass of water
- 5