App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
- 1.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) see tasks by day (b) pick a theme colour (c) add a homework task (d) set a due date
- 2.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) earn stickers (b) share tasks to friends (c) pick a theme colour (d) add a homework task
- 3.🗒️ A to-do app with no “add a task” feature is ___. (a) missing a must-have (b) well planned (c) ready to release (d) a nice extra
- 4.🗒️ The first small, working version of an app is often called an ___. (a) CPU (b) FAQ (c) URL (d) MVP
- 5.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) see tasks by day (b) share tasks to friends (c) set a due date (d) add a homework task
- 6.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) show a question (b) background music (c) an avatar shop (d) confetti effects
- 7.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) share your streak (b) water animations (c) set a reminder time (d) custom alert sounds
-
8.🗒️ Version 1 of a bus tracker must be ready in 13 days. How many days are left for extras after the must-haves?
see where the bus is: 4 days
show arrival time: 2 days
pick your bus stop: 2 days - 9.🗒️ What is a must-have feature? (a) a nice extra (b) a colour theme (c) a sound effect (d) one the app cannot skip
- 10.🗒️ In MVP, the M stands for ___. (a) maximum (b) music (c) minimum (d) mobile
- 11.🗒️ Why keep version 1 small? (a) to look bigger (b) to use up storage (c) to learn from users soon (d) to confuse users
- 12.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) pie-chart colours (b) show the balance (c) export to a file (d) savings stickers
- 13.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) share your streak (b) custom alert sounds (c) water animations (d) see today’s total
- 14.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) see today’s total (b) log a glass of water (c) share your streak (d) set a reminder time
- 15.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) change the bus icon (b) rate the driver (c) a dark mode (d) pick your bus stop
-
16.🗒️ Version 1 of a homework planner must be ready in 7 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 2 days
see tasks by day: 2 days - 17.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) see where the bus is (b) show arrival time (c) a dark mode (d) pick your bus stop
-
18.🗒️ Version 1 of a homework planner must be ready in 16 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 4 days
see tasks by day: 5 days - 19.🗒️ When should nice-to-have features be built? (a) never (b) after the must-haves (c) on day one (d) before anything
- 20.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) add money received (b) pie-chart colours (c) export to a file (d) savings stickers
-
21.🗒️ Version 1 of a water reminder must be ready in 8 days. How many days are left for extras after the must-haves?
set a reminder time: 3 days
log a glass of water: 1 days
see today’s total: 2 days -
22.🗒️ Version 1 of a bus tracker must be ready in 9 days. How many days are left for extras after the must-haves?
see where the bus is: 3 days
show arrival time: 4 days
pick your bus stop: 2 days - 23.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) pick a theme colour (b) share tasks to friends (c) earn stickers (d) set a due date
- 24.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) export to a file (b) add money spent (c) savings stickers (d) pie-chart colours
-
25.🗒️ Version 1 of a pocket-money tracker must be ready in 15 days. How many days are left for extras after the must-haves?
add money received: 3 days
add money spent: 1 days
show the balance: 5 days - 26.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) show the balance (b) add money spent (c) add money received (d) export to a file
-
27.🗒️ Version 1 of a water reminder must be ready in 6 days. How many days are left for extras after the must-haves?
set a reminder time: 3 days
log a glass of water: 1 days
see today’s total: 2 days -
28.🗒️ Version 1 of a quiz app must be ready in 15 days. How many days are left for extras after the must-haves?
show a question: 4 days
check the answer: 4 days
show the score: 4 days -
29.🗒️ Version 1 of a quiz app must be ready in 7 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 4 days
show the score: 2 days -
30.🗒️ Version 1 of a pocket-money tracker must be ready in 11 days. How many days are left for extras after the must-haves?
add money received: 3 days
add money spent: 1 days
show the balance: 5 days - 31.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show a question (b) check the answer (c) confetti effects (d) show the score
- 32.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show the score (b) an avatar shop (c) show a question (d) check the answer
-
33.🗒️ Version 1 of a pocket-money tracker must be ready in 6 days. How many days are left for extras after the must-haves?
add money received: 1 days
add money spent: 1 days
show the balance: 3 days - 34.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) rate the driver (b) a dark mode (c) change the bus icon (d) see where the bus is
- 35.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) confetti effects (b) an avatar shop (c) check the answer (d) background music
-
36.🗒️ Version 1 of a water reminder must be ready in 8 days. How many days are left for extras after the must-haves?
set a reminder time: 2 days
log a glass of water: 2 days
see today’s total: 2 days -
37.🗒️ Version 1 of a water reminder must be ready in 11 days. How many days are left for extras after the must-haves?
set a reminder time: 1 days
log a glass of water: 3 days
see today’s total: 3 days -
38.🗒️ Version 1 of a bus tracker must be ready in 11 days. How many days are left for extras after the must-haves?
see where the bus is: 2 days
show arrival time: 1 days
pick your bus stop: 3 days - 39.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) check the answer (b) show a question (c) show the score (d) background music
- 40.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) see today’s total (b) set a reminder time (c) log a glass of water (d) custom alert sounds
Answer key
- pick a theme colour
- add a homework task
- missing a must-have
- MVP
- share tasks to friends
- show a question
- set a reminder time
- 5
- one the app cannot skip
- minimum
- to learn from users soon
- show the balance
- see today’s total
- share your streak
- pick your bus stop
- 1
- a dark mode
- 6
- after the must-haves
- add money received
- 2
- 0
- set a due date
- add money spent
- 6
- export to a file
- 0
- 3
- 0
- 2
- confetti effects
- an avatar shop
- 1
- see where the bus is
- check the answer
- 2
- 4
- 5
- background music
- custom alert sounds
Free app development lessons, practice and worksheets at talentjr.in/app-development-for-students