App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
-
1.🗒️ Version 1 of a quiz app must be ready in 9 days. How many days are left for extras after the must-haves?
show a question: 2 days
check the answer: 3 days
show the score: 4 days -
2.🗒️ Version 1 of a quiz app must be ready in 15 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 4 days
show the score: 5 days - 3.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) show arrival time (b) pick your bus stop (c) rate the driver (d) see where the bus is
-
4.🗒️ Version 1 of a pocket-money tracker must be ready in 9 days. How many days are left for extras after the must-haves?
add money received: 2 days
add money spent: 2 days
show the balance: 4 days -
5.🗒️ Version 1 of a pocket-money tracker must be ready in 8 days. How many days are left for extras after the must-haves?
add money received: 2 days
add money spent: 3 days
show the balance: 2 days - 6.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) export to a file (b) show the balance (c) savings stickers (d) pie-chart colours
- 7.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) see today’s total (b) share your streak (c) log a glass of water (d) set a reminder time
- 8.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) see tasks by day (b) earn stickers (c) pick a theme colour (d) share tasks to friends
- 9.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) an avatar shop (b) background music (c) confetti effects (d) show the score
-
10.🗒️ Version 1 of a quiz app must be ready in 8 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 3 days
show the score: 3 days - 11.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) export to a file (b) add money received (c) show the balance (d) add money spent
- 12.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) add a homework task (b) see tasks by day (c) set a due date (d) share tasks to friends
- 13.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) check the answer (b) show a question (c) an avatar shop (d) show the score
- 14.🗒️ When should nice-to-have features be built? (a) after the must-haves (b) before anything (c) never (d) on day one
- 15.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) change the bus icon (b) rate the driver (c) a dark mode (d) show arrival time
- 16.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) water animations (b) log a glass of water (c) share your streak (d) custom alert sounds
- 17.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) add a homework task (b) see tasks by day (c) set a due date (d) pick a theme colour
- 18.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) share your streak (b) custom alert sounds (c) water animations (d) see today’s total
- 19.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) set a due date (b) add a homework task (c) earn stickers (d) see tasks by day
- 20.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) set a reminder time (b) water animations (c) log a glass of water (d) see today’s total
- 21.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money received (b) show the balance (c) add money spent (d) savings stickers
- 22.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) change the bus icon (b) a dark mode (c) rate the driver (d) pick your bus stop
-
23.🗒️ Version 1 of a water reminder must be ready in 14 days. How many days are left for extras after the must-haves?
set a reminder time: 3 days
log a glass of water: 2 days
see today’s total: 5 days - 24.🗒️ A to-do app with no “add a task” feature is ___. (a) a nice extra (b) well planned (c) ready to release (d) missing a must-have
- 25.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) log a glass of water (b) set a reminder time (c) see today’s total (d) custom alert sounds
-
26.🗒️ Version 1 of a homework planner must be ready in 12 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 3 days
see tasks by day: 2 days - 27.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) savings stickers (b) export to a file (c) pie-chart colours (d) add money spent
- 28.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) share your streak (b) set a reminder time (c) custom alert sounds (d) water animations
- 29.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) pick a theme colour (b) set a due date (c) share tasks to friends (d) earn stickers
-
30.🗒️ Version 1 of a quiz app must be ready in 8 days. How many days are left for extras after the must-haves?
show a question: 2 days
check the answer: 1 days
show the score: 4 days -
31.🗒️ Version 1 of a homework planner must be ready in 13 days. How many days are left for extras after the must-haves?
add a homework task: 4 days
set a due date: 1 days
see tasks by day: 2 days - 32.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) confetti effects (b) an avatar shop (c) check the answer (d) background music
- 33.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money received (b) pie-chart colours (c) add money spent (d) show the balance
- 34.🗒️ The first small, working version of an app is often called an ___. (a) MVP (b) FAQ (c) CPU (d) URL
- 35.🗒️ In MVP, the M stands for ___. (a) music (b) minimum (c) maximum (d) mobile
-
36.🗒️ Version 1 of a pocket-money tracker must be ready in 10 days. How many days are left for extras after the must-haves?
add money received: 2 days
add money spent: 4 days
show the balance: 2 days - 37.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) background music (b) show the score (c) check the answer (d) show a question
- 38.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) pick a theme colour (b) earn stickers (c) share tasks to friends (d) add a homework task
- 39.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) show a question (b) confetti effects (c) an avatar shop (d) background music
- 40.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) pie-chart colours (b) export to a file (c) add money received (d) savings stickers
Answer key
- 0
- 5
- rate the driver
- 1
- 1
- show the balance
- share your streak
- see tasks by day
- show the score
- 1
- export to a file
- share tasks to friends
- an avatar shop
- after the must-haves
- show arrival time
- log a glass of water
- pick a theme colour
- see today’s total
- earn stickers
- water animations
- savings stickers
- pick your bus stop
- 4
- missing a must-have
- custom alert sounds
- 5
- add money spent
- set a reminder time
- set a due date
- 1
- 6
- check the answer
- pie-chart colours
- MVP
- minimum
- 2
- background music
- add a homework task
- show a question
- add money received
Free app development lessons, practice and worksheets at talentjr.in/app-development-for-students