App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
- 1.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) pick your bus stop (b) change the bus icon (c) rate the driver (d) a dark mode
- 2.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) log a glass of water (b) set a reminder time (c) custom alert sounds (d) see today’s total
- 3.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show the score (b) show a question (c) check the answer (d) background music
- 4.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) an avatar shop (b) confetti effects (c) background music (d) show a question
-
5.🗒️ Version 1 of a bus tracker must be ready in 12 days. How many days are left for extras after the must-haves?
see where the bus is: 1 days
show arrival time: 1 days
pick your bus stop: 4 days - 6.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money received (b) show the balance (c) add money spent (d) savings stickers
-
7.🗒️ Version 1 of a bus tracker must be ready in 11 days. How many days are left for extras after the must-haves?
see where the bus is: 2 days
show arrival time: 2 days
pick your bus stop: 4 days - 8.🗒️ Why keep version 1 small? (a) to look bigger (b) to confuse users (c) to learn from users soon (d) to use up storage
- 9.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) earn stickers (b) add a homework task (c) set a due date (d) see tasks by day
- 10.🗒️ What is a must-have feature? (a) a sound effect (b) one the app cannot skip (c) a colour theme (d) a nice extra
- 11.🗒️ A to-do app with no “add a task” feature is ___. (a) well planned (b) a nice extra (c) ready to release (d) missing a must-have
- 12.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) a dark mode (b) change the bus icon (c) rate the driver (d) see where the bus is
- 13.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) earn stickers (b) add a homework task (c) share tasks to friends (d) pick a theme colour
- 14.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) pie-chart colours (b) add money spent (c) export to a file (d) savings stickers
- 15.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money received (b) show the balance (c) pie-chart colours (d) add money spent
- 16.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) pie-chart colours (b) savings stickers (c) export to a file (d) add money received
-
17.🗒️ Version 1 of a bus tracker must be ready in 10 days. How many days are left for extras after the must-haves?
see where the bus is: 4 days
show arrival time: 1 days
pick your bus stop: 4 days -
18.🗒️ Version 1 of a bus tracker must be ready in 14 days. How many days are left for extras after the must-haves?
see where the bus is: 2 days
show arrival time: 4 days
pick your bus stop: 3 days - 19.🗒️ When should nice-to-have features be built? (a) never (b) on day one (c) after the must-haves (d) before anything
-
20.🗒️ Version 1 of a homework planner must be ready in 7 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 3 days
see tasks by day: 2 days -
21.🗒️ Version 1 of a water reminder must be ready in 9 days. How many days are left for extras after the must-haves?
set a reminder time: 1 days
log a glass of water: 2 days
see today’s total: 4 days - 22.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) share tasks to friends (b) add a homework task (c) see tasks by day (d) set a due date
-
23.🗒️ Version 1 of a homework planner must be ready in 9 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 4 days
see tasks by day: 4 days - 24.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) background music (b) confetti effects (c) an avatar shop (d) show the score
- 25.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) see today’s total (b) share your streak (c) log a glass of water (d) set a reminder time
-
26.🗒️ Version 1 of a bus tracker must be ready in 9 days. How many days are left for extras after the must-haves?
see where the bus is: 1 days
show arrival time: 2 days
pick your bus stop: 5 days -
27.🗒️ Version 1 of a pocket-money tracker must be ready in 12 days. How many days are left for extras after the must-haves?
add money received: 2 days
add money spent: 4 days
show the balance: 2 days - 28.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) water animations (b) log a glass of water (c) custom alert sounds (d) share your streak
-
29.🗒️ Version 1 of a homework planner must be ready in 9 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 1 days
see tasks by day: 4 days -
30.🗒️ Version 1 of a bus tracker must be ready in 11 days. How many days are left for extras after the must-haves?
see where the bus is: 4 days
show arrival time: 1 days
pick your bus stop: 2 days - 31.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) confetti effects (b) show the score (c) show a question (d) check the answer
- 32.🗒️ The first small, working version of an app is often called an ___. (a) URL (b) FAQ (c) CPU (d) MVP
- 33.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) pick a theme colour (b) share tasks to friends (c) earn stickers (d) see tasks by day
-
34.🗒️ Version 1 of a water reminder must be ready in 9 days. How many days are left for extras after the must-haves?
set a reminder time: 3 days
log a glass of water: 1 days
see today’s total: 3 days -
35.🗒️ Version 1 of a homework planner must be ready in 15 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 3 days
see tasks by day: 5 days - 36.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) share your streak (b) water animations (c) set a reminder time (d) custom alert sounds
-
37.🗒️ Version 1 of a water reminder must be ready in 6 days. How many days are left for extras after the must-haves?
set a reminder time: 1 days
log a glass of water: 3 days
see today’s total: 2 days -
38.🗒️ Version 1 of a homework planner must be ready in 11 days. How many days are left for extras after the must-haves?
add a homework task: 4 days
set a due date: 4 days
see tasks by day: 3 days -
39.🗒️ Version 1 of a bus tracker must be ready in 14 days. How many days are left for extras after the must-haves?
see where the bus is: 3 days
show arrival time: 4 days
pick your bus stop: 2 days -
40.🗒️ Version 1 of a pocket-money tracker must be ready in 14 days. How many days are left for extras after the must-haves?
add money received: 2 days
add money spent: 3 days
show the balance: 4 days
Answer key
- pick your bus stop
- custom alert sounds
- background music
- show a question
- 6
- savings stickers
- 3
- to learn from users soon
- earn stickers
- one the app cannot skip
- missing a must-have
- see where the bus is
- add a homework task
- add money spent
- pie-chart colours
- add money received
- 1
- 5
- after the must-haves
- 1
- 2
- share tasks to friends
- 0
- show the score
- share your streak
- 1
- 4
- log a glass of water
- 3
- 4
- confetti effects
- MVP
- see tasks by day
- 2
- 5
- set a reminder time
- 0
- 0
- 5
- 5