App Dev Worksheet: Planning Features

App development lesson 6: Planning features: must-haves first · Set 313 · 40 questions
TalentJR

Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.

NameDateTime takenScore ___ / 40
  1. 1.🗒️ Version 1 of a quiz app must be ready in 10 days. How many days are left for extras after the must-haves?
    show a question: 1 days
    check the answer: 1 days
    show the score: 4 days
  2. 2.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) see where the bus is (b) show arrival time (c) pick your bus stop (d) change the bus icon
  3. 3.🗒️ Version 1 of a quiz app must be ready in 12 days. How many days are left for extras after the must-haves?
    show a question: 2 days
    check the answer: 1 days
    show the score: 5 days
  4. 4.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) pick your bus stop (b) a dark mode (c) rate the driver (d) change the bus icon
  5. 5.🗒️ Version 1 of a water reminder must be ready in 14 days. How many days are left for extras after the must-haves?
    set a reminder time: 3 days
    log a glass of water: 1 days
    see today’s total: 5 days
  6. 6.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) log a glass of water (b) set a reminder time (c) see today’s total (d) water animations
  7. 7.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) savings stickers (b) pie-chart colours (c) add money received (d) export to a file
  8. 8.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) share tasks to friends (b) set a due date (c) see tasks by day (d) add a homework task
  9. 9.🗒️ In MVP, the M stands for ___. (a) mobile (b) minimum (c) maximum (d) music
  10. 10.🗒️ What is a must-have feature? (a) a nice extra (b) a colour theme (c) one the app cannot skip (d) a sound effect
  11. 11.🗒️ Version 1 of a quiz app must be ready in 8 days. How many days are left for extras after the must-haves?
    show a question: 3 days
    check the answer: 2 days
    show the score: 3 days
  12. 12.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) share your streak (b) custom alert sounds (c) set a reminder time (d) water animations
  13. 13.🗒️ A to-do app with no “add a task” feature is ___. (a) ready to release (b) a nice extra (c) missing a must-have (d) well planned
  14. 14.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) show the balance (b) savings stickers (c) add money spent (d) add money received
  15. 15.🗒️ When should nice-to-have features be built? (a) never (b) after the must-haves (c) before anything (d) on day one
  16. 16.🗒️ Version 1 of a quiz app must be ready in 10 days. How many days are left for extras after the must-haves?
    show a question: 1 days
    check the answer: 2 days
    show the score: 2 days
  17. 17.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show a question (b) show the score (c) an avatar shop (d) check the answer
  18. 18.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) an avatar shop (b) show the score (c) confetti effects (d) background music
  19. 19.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) see tasks by day (b) earn stickers (c) share tasks to friends (d) pick a theme colour
  20. 20.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) background music (b) show a question (c) an avatar shop (d) confetti effects
  21. 21.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) pick a theme colour (b) add a homework task (c) earn stickers (d) share tasks to friends
  22. 22.🗒️ Version 1 of a quiz app must be ready in 12 days. How many days are left for extras after the must-haves?
    show a question: 1 days
    check the answer: 3 days
    show the score: 2 days
  23. 23.🗒️ The first small, working version of an app is often called an ___. (a) FAQ (b) CPU (c) URL (d) MVP
  24. 24.🗒️ Version 1 of a bus tracker must be ready in 11 days. How many days are left for extras after the must-haves?
    see where the bus is: 4 days
    show arrival time: 2 days
    pick your bus stop: 3 days
  25. 25.🗒️ Version 1 of a bus tracker must be ready in 7 days. How many days are left for extras after the must-haves?
    see where the bus is: 2 days
    show arrival time: 2 days
    pick your bus stop: 2 days
  26. 26.🗒️ Version 1 of a homework planner must be ready in 12 days. How many days are left for extras after the must-haves?
    add a homework task: 1 days
    set a due date: 2 days
    see tasks by day: 3 days
  27. 27.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) show arrival time (b) rate the driver (c) a dark mode (d) change the bus icon
  28. 28.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) pie-chart colours (b) export to a file (c) savings stickers (d) add money spent
  29. 29.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) pick your bus stop (b) show arrival time (c) a dark mode (d) see where the bus is
  30. 30.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) set a due date (b) see tasks by day (c) earn stickers (d) add a homework task
  31. 31.🗒️ Version 1 of a water reminder must be ready in 12 days. How many days are left for extras after the must-haves?
    set a reminder time: 1 days
    log a glass of water: 3 days
    see today’s total: 4 days
  32. 32.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) rate the driver (b) change the bus icon (c) a dark mode (d) see where the bus is
  33. 33.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) savings stickers (b) pie-chart colours (c) show the balance (d) export to a file
  34. 34.🗒️ Version 1 of a bus tracker must be ready in 11 days. How many days are left for extras after the must-haves?
    see where the bus is: 2 days
    show arrival time: 1 days
    pick your bus stop: 2 days
  35. 35.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) see today’s total (b) custom alert sounds (c) share your streak (d) water animations
  36. 36.🗒️ Version 1 of a quiz app must be ready in 13 days. How many days are left for extras after the must-haves?
    show a question: 4 days
    check the answer: 3 days
    show the score: 5 days
  37. 37.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show the score (b) background music (c) check the answer (d) show a question
  38. 38.🗒️ Version 1 of a quiz app must be ready in 9 days. How many days are left for extras after the must-haves?
    show a question: 2 days
    check the answer: 4 days
    show the score: 2 days
  39. 39.🗒️ Why keep version 1 small? (a) to learn from users soon (b) to look bigger (c) to confuse users (d) to use up storage
  40. 40.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show the score (b) check the answer (c) confetti effects (d) show a question

Answer key

  1. 4
  2. change the bus icon
  3. 4
  4. pick your bus stop
  5. 5
  6. water animations
  7. add money received
  8. share tasks to friends
  9. minimum
  10. one the app cannot skip
  11. 0
  12. set a reminder time
  13. missing a must-have
  14. savings stickers
  15. after the must-haves
  16. 5
  17. an avatar shop
  18. show the score
  19. see tasks by day
  20. show a question
  21. add a homework task
  22. 6
  23. MVP
  24. 2
  25. 1
  26. 6
  27. show arrival time
  28. add money spent
  29. a dark mode
  30. earn stickers
  31. 4
  32. see where the bus is
  33. show the balance
  34. 6
  35. see today’s total
  36. 1
  37. background music
  38. 1
  39. to learn from users soon
  40. confetti effects