App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
-
1.🗒️ Version 1 of a water reminder must be ready in 9 days. How many days are left for extras after the must-haves?
set a reminder time: 3 days
log a glass of water: 1 days
see today’s total: 2 days - 2.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) custom alert sounds (b) set a reminder time (c) water animations (d) share your streak
- 3.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) an avatar shop (b) show a question (c) show the score (d) check the answer
- 4.🗒️ A to-do app with no “add a task” feature is ___. (a) missing a must-have (b) well planned (c) a nice extra (d) ready to release
-
5.🗒️ Version 1 of a quiz app must be ready in 11 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 2 days
show the score: 3 days - 6.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) check the answer (b) show the score (c) background music (d) show a question
- 7.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show the score (b) confetti effects (c) show a question (d) check the answer
- 8.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money received (b) pie-chart colours (c) add money spent (d) show the balance
- 9.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) share tasks to friends (b) see tasks by day (c) earn stickers (d) pick a theme colour
-
10.🗒️ Version 1 of a homework planner must be ready in 11 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 2 days
see tasks by day: 2 days -
11.🗒️ Version 1 of a water reminder must be ready in 5 days. How many days are left for extras after the must-haves?
set a reminder time: 2 days
log a glass of water: 1 days
see today’s total: 2 days - 12.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) see where the bus is (b) change the bus icon (c) a dark mode (d) rate the driver
- 13.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) see where the bus is (b) pick your bus stop (c) show arrival time (d) rate the driver
- 14.🗒️ Why keep version 1 small? (a) to use up storage (b) to learn from users soon (c) to look bigger (d) to confuse users
- 15.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) background music (b) an avatar shop (c) confetti effects (d) show a question
-
16.🗒️ Version 1 of a pocket-money tracker must be ready in 11 days. How many days are left for extras after the must-haves?
add money received: 4 days
add money spent: 1 days
show the balance: 4 days - 17.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) water animations (b) share your streak (c) custom alert sounds (d) see today’s total
- 18.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) set a due date (b) earn stickers (c) pick a theme colour (d) share tasks to friends
- 19.🗒️ What is a must-have feature? (a) a nice extra (b) a colour theme (c) a sound effect (d) one the app cannot skip
- 20.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) share your streak (b) set a reminder time (c) see today’s total (d) log a glass of water
- 21.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) add money received (b) export to a file (c) pie-chart colours (d) savings stickers
- 22.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) log a glass of water (b) water animations (c) see today’s total (d) set a reminder time
- 23.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) see today’s total (b) custom alert sounds (c) log a glass of water (d) set a reminder time
- 24.🗒️ In MVP, the M stands for ___. (a) music (b) maximum (c) mobile (d) minimum
- 25.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) export to a file (b) savings stickers (c) pie-chart colours (d) add money spent
- 26.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) pick your bus stop (b) a dark mode (c) change the bus icon (d) rate the driver
- 27.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) export to a file (b) pie-chart colours (c) savings stickers (d) show the balance
-
28.🗒️ Version 1 of a pocket-money tracker must be ready in 13 days. How many days are left for extras after the must-haves?
add money received: 1 days
add money spent: 4 days
show the balance: 5 days - 29.🗒️ When should nice-to-have features be built? (a) never (b) on day one (c) after the must-haves (d) before anything
- 30.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) add a homework task (b) see tasks by day (c) set a due date (d) pick a theme colour
-
31.🗒️ Version 1 of a homework planner must be ready in 15 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 3 days
see tasks by day: 5 days -
32.🗒️ Version 1 of a pocket-money tracker must be ready in 6 days. How many days are left for extras after the must-haves?
add money received: 1 days
add money spent: 1 days
show the balance: 2 days - 33.🗒️ The first small, working version of an app is often called an ___. (a) CPU (b) FAQ (c) URL (d) MVP
-
34.🗒️ Version 1 of a homework planner must be ready in 7 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 2 days
see tasks by day: 3 days - 35.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) water animations (b) share your streak (c) log a glass of water (d) custom alert sounds
- 36.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) confetti effects (b) background music (c) check the answer (d) an avatar shop
- 37.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) share tasks to friends (b) earn stickers (c) add a homework task (d) pick a theme colour
- 38.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) see tasks by day (b) add a homework task (c) set a due date (d) earn stickers
-
39.🗒️ Version 1 of a quiz app must be ready in 15 days. How many days are left for extras after the must-haves?
show a question: 4 days
check the answer: 2 days
show the score: 5 days - 40.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) show arrival time (b) change the bus icon (c) a dark mode (d) rate the driver
Answer key
- 3
- set a reminder time
- an avatar shop
- missing a must-have
- 5
- background music
- confetti effects
- pie-chart colours
- see tasks by day
- 6
- 0
- see where the bus is
- rate the driver
- to learn from users soon
- show a question
- 2
- see today’s total
- set a due date
- one the app cannot skip
- share your streak
- add money received
- water animations
- custom alert sounds
- minimum
- add money spent
- pick your bus stop
- show the balance
- 3
- after the must-haves
- pick a theme colour
- 6
- 2
- MVP
- 1
- log a glass of water
- check the answer
- add a homework task
- earn stickers
- 4
- show arrival time