App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
- 1.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) rate the driver (b) change the bus icon (c) a dark mode (d) show arrival time
- 2.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) see where the bus is (b) show arrival time (c) pick your bus stop (d) a dark mode
- 3.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) pie-chart colours (b) add money spent (c) export to a file (d) savings stickers
- 4.🗒️ A to-do app with no “add a task” feature is ___. (a) missing a must-have (b) a nice extra (c) ready to release (d) well planned
-
5.🗒️ Version 1 of a pocket-money tracker must be ready in 12 days. How many days are left for extras after the must-haves?
add money received: 4 days
add money spent: 2 days
show the balance: 4 days -
6.🗒️ Version 1 of a bus tracker must be ready in 9 days. How many days are left for extras after the must-haves?
see where the bus is: 1 days
show arrival time: 4 days
pick your bus stop: 3 days - 7.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) check the answer (b) confetti effects (c) background music (d) an avatar shop
- 8.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) log a glass of water (b) set a reminder time (c) water animations (d) see today’s total
- 9.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) see where the bus is (b) pick your bus stop (c) change the bus icon (d) show arrival time
- 10.🗒️ In MVP, the M stands for ___. (a) minimum (b) mobile (c) maximum (d) music
- 11.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) show the balance (b) add money spent (c) pie-chart colours (d) add money received
- 12.🗒️ When should nice-to-have features be built? (a) on day one (b) after the must-haves (c) before anything (d) never
-
13.🗒️ Version 1 of a water reminder must be ready in 13 days. How many days are left for extras after the must-haves?
set a reminder time: 3 days
log a glass of water: 2 days
see today’s total: 5 days -
14.🗒️ Version 1 of a quiz app must be ready in 11 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 1 days
show the score: 5 days - 15.🗒️ What is a must-have feature? (a) a nice extra (b) a colour theme (c) one the app cannot skip (d) a sound effect
-
16.🗒️ Version 1 of a bus tracker must be ready in 8 days. How many days are left for extras after the must-haves?
see where the bus is: 1 days
show arrival time: 2 days
pick your bus stop: 2 days - 17.🗒️ Why keep version 1 small? (a) to use up storage (b) to confuse users (c) to learn from users soon (d) to look bigger
- 18.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) earn stickers (b) pick a theme colour (c) share tasks to friends (d) set a due date
- 19.🗒️ The first small, working version of an app is often called an ___. (a) FAQ (b) MVP (c) URL (d) CPU
- 20.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) show a question (b) background music (c) confetti effects (d) an avatar shop
- 21.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) share your streak (b) log a glass of water (c) custom alert sounds (d) water animations
- 22.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) add a homework task (b) pick a theme colour (c) earn stickers (d) share tasks to friends
-
23.🗒️ Version 1 of a homework planner must be ready in 13 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 4 days
see tasks by day: 3 days - 24.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) add a homework task (b) see tasks by day (c) set a due date (d) share tasks to friends
-
25.🗒️ Version 1 of a bus tracker must be ready in 11 days. How many days are left for extras after the must-haves?
see where the bus is: 2 days
show arrival time: 4 days
pick your bus stop: 5 days -
26.🗒️ Version 1 of a water reminder must be ready in 11 days. How many days are left for extras after the must-haves?
set a reminder time: 1 days
log a glass of water: 2 days
see today’s total: 4 days - 27.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show the score (b) show a question (c) background music (d) check the answer
-
28.🗒️ Version 1 of a quiz app must be ready in 13 days. How many days are left for extras after the must-haves?
show a question: 4 days
check the answer: 3 days
show the score: 4 days - 29.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) pick your bus stop (b) rate the driver (c) a dark mode (d) change the bus icon
-
30.🗒️ Version 1 of a quiz app must be ready in 10 days. How many days are left for extras after the must-haves?
show a question: 2 days
check the answer: 4 days
show the score: 4 days - 31.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) set a due date (b) see tasks by day (c) add a homework task (d) pick a theme colour
- 32.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) share your streak (b) see today’s total (c) custom alert sounds (d) water animations
-
33.🗒️ Version 1 of a homework planner must be ready in 14 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 1 days
see tasks by day: 5 days -
34.🗒️ Version 1 of a homework planner must be ready in 11 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 2 days
see tasks by day: 5 days - 35.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) see where the bus is (b) show arrival time (c) rate the driver (d) pick your bus stop
-
36.🗒️ Version 1 of a quiz app must be ready in 7 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 1 days
show the score: 5 days -
37.🗒️ Version 1 of a homework planner must be ready in 11 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 2 days
see tasks by day: 4 days -
38.🗒️ Version 1 of a bus tracker must be ready in 16 days. How many days are left for extras after the must-haves?
see where the bus is: 4 days
show arrival time: 4 days
pick your bus stop: 3 days -
39.🗒️ Version 1 of a quiz app must be ready in 8 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 4 days
show the score: 3 days - 40.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) an avatar shop (b) background music (c) show the score (d) confetti effects
Answer key
- show arrival time
- a dark mode
- add money spent
- missing a must-have
- 2
- 1
- check the answer
- water animations
- change the bus icon
- minimum
- pie-chart colours
- after the must-haves
- 3
- 4
- one the app cannot skip
- 3
- to learn from users soon
- set a due date
- MVP
- show a question
- log a glass of water
- add a homework task
- 5
- share tasks to friends
- 0
- 4
- background music
- 2
- pick your bus stop
- 0
- pick a theme colour
- see today’s total
- 5
- 1
- rate the driver
- 0
- 2
- 5
- 0
- show the score