App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
- 1.🗒️ The first small, working version of an app is often called an ___. (a) CPU (b) URL (c) MVP (d) FAQ
- 2.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) change the bus icon (b) rate the driver (c) a dark mode (d) see where the bus is
- 3.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) add a homework task (b) see tasks by day (c) earn stickers (d) set a due date
- 4.🗒️ When should nice-to-have features be built? (a) after the must-haves (b) never (c) before anything (d) on day one
-
5.🗒️ Version 1 of a water reminder must be ready in 12 days. How many days are left for extras after the must-haves?
set a reminder time: 3 days
log a glass of water: 1 days
see today’s total: 2 days - 6.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) pie-chart colours (b) savings stickers (c) show the balance (d) export to a file
- 7.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) pie-chart colours (b) add money spent (c) export to a file (d) savings stickers
-
8.🗒️ Version 1 of a water reminder must be ready in 11 days. How many days are left for extras after the must-haves?
set a reminder time: 2 days
log a glass of water: 2 days
see today’s total: 2 days - 9.🗒️ What is a must-have feature? (a) a sound effect (b) a colour theme (c) a nice extra (d) one the app cannot skip
- 10.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) show arrival time (b) rate the driver (c) pick your bus stop (d) see where the bus is
-
11.🗒️ Version 1 of a homework planner must be ready in 11 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 4 days
see tasks by day: 4 days - 12.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) share your streak (b) custom alert sounds (c) water animations (d) see today’s total
- 13.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) pie-chart colours (b) export to a file (c) add money received (d) savings stickers
-
14.🗒️ Version 1 of a quiz app must be ready in 15 days. How many days are left for extras after the must-haves?
show a question: 3 days
check the answer: 4 days
show the score: 5 days - 15.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) confetti effects (b) background music (c) show a question (d) an avatar shop
- 16.🗒️ A to-do app with no “add a task” feature is ___. (a) a nice extra (b) missing a must-have (c) ready to release (d) well planned
-
17.🗒️ Version 1 of a homework planner must be ready in 12 days. How many days are left for extras after the must-haves?
add a homework task: 4 days
set a due date: 4 days
see tasks by day: 2 days - 18.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) earn stickers (b) pick a theme colour (c) share tasks to friends (d) set a due date
- 19.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) see today’s total (b) log a glass of water (c) share your streak (d) set a reminder time
- 20.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) set a due date (b) see tasks by day (c) add a homework task (d) pick a theme colour
- 21.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) confetti effects (b) show the score (c) check the answer (d) show a question
- 22.🗒️ Why keep version 1 small? (a) to look bigger (b) to use up storage (c) to confuse users (d) to learn from users soon
- 23.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) show arrival time (b) rate the driver (c) a dark mode (d) change the bus icon
-
24.🗒️ Version 1 of a homework planner must be ready in 15 days. How many days are left for extras after the must-haves?
add a homework task: 4 days
set a due date: 4 days
see tasks by day: 3 days - 25.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) earn stickers (b) pick a theme colour (c) see tasks by day (d) share tasks to friends
- 26.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) custom alert sounds (b) see today’s total (c) log a glass of water (d) set a reminder time
-
27.🗒️ Version 1 of a bus tracker must be ready in 11 days. How many days are left for extras after the must-haves?
see where the bus is: 2 days
show arrival time: 1 days
pick your bus stop: 4 days - 28.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money received (b) add money spent (c) pie-chart colours (d) show the balance
- 29.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) export to a file (b) add money received (c) show the balance (d) add money spent
- 30.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money received (b) savings stickers (c) add money spent (d) show the balance
- 31.🗒️ In MVP, the M stands for ___. (a) mobile (b) minimum (c) music (d) maximum
-
32.🗒️ Version 1 of a quiz app must be ready in 15 days. How many days are left for extras after the must-haves?
show a question: 3 days
check the answer: 4 days
show the score: 2 days - 33.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) confetti effects (b) an avatar shop (c) background music (d) check the answer
-
34.🗒️ Version 1 of a homework planner must be ready in 6 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 1 days
see tasks by day: 3 days -
35.🗒️ Version 1 of a quiz app must be ready in 9 days. How many days are left for extras after the must-haves?
show a question: 2 days
check the answer: 1 days
show the score: 5 days - 36.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) see tasks by day (b) set a due date (c) add a homework task (d) share tasks to friends
-
37.🗒️ Version 1 of a quiz app must be ready in 10 days. How many days are left for extras after the must-haves?
show a question: 4 days
check the answer: 1 days
show the score: 3 days -
38.🗒️ Version 1 of a pocket-money tracker must be ready in 6 days. How many days are left for extras after the must-haves?
add money received: 1 days
add money spent: 1 days
show the balance: 3 days -
39.🗒️ Version 1 of a water reminder must be ready in 13 days. How many days are left for extras after the must-haves?
set a reminder time: 4 days
log a glass of water: 2 days
see today’s total: 3 days - 40.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) check the answer (b) show the score (c) background music (d) show a question
Answer key
- MVP
- see where the bus is
- earn stickers
- after the must-haves
- 6
- show the balance
- add money spent
- 5
- one the app cannot skip
- rate the driver
- 2
- see today’s total
- add money received
- 3
- show a question
- missing a must-have
- 2
- set a due date
- share your streak
- pick a theme colour
- confetti effects
- to learn from users soon
- show arrival time
- 4
- see tasks by day
- custom alert sounds
- 4
- pie-chart colours
- export to a file
- savings stickers
- minimum
- 6
- check the answer
- 0
- 1
- share tasks to friends
- 2
- 1
- 4
- background music