App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
- 1.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) water animations (b) share your streak (c) custom alert sounds (d) set a reminder time
- 2.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) log a glass of water (b) set a reminder time (c) water animations (d) see today’s total
- 3.🗒️ Why keep version 1 small? (a) to learn from users soon (b) to confuse users (c) to look bigger (d) to use up storage
- 4.🗒️ A to-do app with no “add a task” feature is ___. (a) missing a must-have (b) well planned (c) a nice extra (d) ready to release
-
5.🗒️ Version 1 of a water reminder must be ready in 11 days. How many days are left for extras after the must-haves?
set a reminder time: 2 days
log a glass of water: 1 days
see today’s total: 2 days -
6.🗒️ Version 1 of a quiz app must be ready in 11 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 2 days
show the score: 2 days - 7.🗒️ In MVP, the M stands for ___. (a) maximum (b) minimum (c) music (d) mobile
-
8.🗒️ Version 1 of a quiz app must be ready in 8 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 3 days
show the score: 3 days - 9.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) check the answer (b) show the score (c) background music (d) show a question
- 10.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) savings stickers (b) add money received (c) pie-chart colours (d) export to a file
-
11.🗒️ Version 1 of a quiz app must be ready in 14 days. How many days are left for extras after the must-haves?
show a question: 2 days
check the answer: 3 days
show the score: 4 days - 12.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) change the bus icon (b) pick your bus stop (c) show arrival time (d) see where the bus is
- 13.🗒️ What is a must-have feature? (a) one the app cannot skip (b) a nice extra (c) a colour theme (d) a sound effect
-
14.🗒️ Version 1 of a pocket-money tracker must be ready in 9 days. How many days are left for extras after the must-haves?
add money received: 1 days
add money spent: 3 days
show the balance: 3 days - 15.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) water animations (b) custom alert sounds (c) see today’s total (d) share your streak
-
16.🗒️ Version 1 of a bus tracker must be ready in 11 days. How many days are left for extras after the must-haves?
see where the bus is: 2 days
show arrival time: 1 days
pick your bus stop: 5 days - 17.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) see tasks by day (b) set a due date (c) pick a theme colour (d) add a homework task
- 18.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) background music (b) confetti effects (c) an avatar shop (d) show the score
-
19.🗒️ Version 1 of a homework planner must be ready in 9 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 4 days
see tasks by day: 2 days - 20.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) pie-chart colours (b) export to a file (c) savings stickers (d) add money spent
- 21.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money received (b) add money spent (c) show the balance (d) pie-chart colours
- 22.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) an avatar shop (b) background music (c) check the answer (d) confetti effects
-
23.🗒️ Version 1 of a homework planner must be ready in 12 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 3 days
see tasks by day: 3 days -
24.🗒️ Version 1 of a bus tracker must be ready in 9 days. How many days are left for extras after the must-haves?
see where the bus is: 2 days
show arrival time: 2 days
pick your bus stop: 5 days - 25.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) show arrival time (b) rate the driver (c) see where the bus is (d) pick your bus stop
- 26.🗒️ The first small, working version of an app is often called an ___. (a) URL (b) FAQ (c) MVP (d) CPU
- 27.🗒️ When should nice-to-have features be built? (a) on day one (b) after the must-haves (c) never (d) before anything
- 28.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) see tasks by day (b) pick a theme colour (c) share tasks to friends (d) earn stickers
- 29.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) earn stickers (b) share tasks to friends (c) add a homework task (d) pick a theme colour
-
30.🗒️ Version 1 of a water reminder must be ready in 12 days. How many days are left for extras after the must-haves?
set a reminder time: 4 days
log a glass of water: 2 days
see today’s total: 5 days - 31.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) custom alert sounds (b) water animations (c) log a glass of water (d) share your streak
-
32.🗒️ Version 1 of a bus tracker must be ready in 13 days. How many days are left for extras after the must-haves?
see where the bus is: 3 days
show arrival time: 2 days
pick your bus stop: 2 days -
33.🗒️ Version 1 of a water reminder must be ready in 15 days. How many days are left for extras after the must-haves?
set a reminder time: 3 days
log a glass of water: 4 days
see today’s total: 4 days -
34.🗒️ Version 1 of a quiz app must be ready in 9 days. How many days are left for extras after the must-haves?
show a question: 2 days
check the answer: 2 days
show the score: 2 days -
35.🗒️ Version 1 of a pocket-money tracker must be ready in 12 days. How many days are left for extras after the must-haves?
add money received: 4 days
add money spent: 1 days
show the balance: 4 days -
36.🗒️ Version 1 of a bus tracker must be ready in 10 days. How many days are left for extras after the must-haves?
see where the bus is: 1 days
show arrival time: 2 days
pick your bus stop: 4 days - 37.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) an avatar shop (b) show the score (c) show a question (d) check the answer
- 38.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) see where the bus is (b) a dark mode (c) change the bus icon (d) rate the driver
-
39.🗒️ Version 1 of a bus tracker must be ready in 15 days. How many days are left for extras after the must-haves?
see where the bus is: 1 days
show arrival time: 4 days
pick your bus stop: 5 days - 40.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) see where the bus is (b) show arrival time (c) a dark mode (d) pick your bus stop
Answer key
- set a reminder time
- water animations
- to learn from users soon
- missing a must-have
- 6
- 6
- minimum
- 1
- background music
- add money received
- 5
- change the bus icon
- one the app cannot skip
- 2
- see today’s total
- 3
- pick a theme colour
- show the score
- 1
- add money spent
- pie-chart colours
- check the answer
- 4
- 0
- rate the driver
- MVP
- after the must-haves
- see tasks by day
- add a homework task
- 1
- log a glass of water
- 6
- 4
- 3
- 3
- 3
- an avatar shop
- see where the bus is
- 5
- a dark mode
Free app development lessons, practice and worksheets at talentjr.in/app-development-for-students