App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
-
1.🗒️ Version 1 of a pocket-money tracker must be ready in 6 days. How many days are left for extras after the must-haves?
add money received: 2 days
add money spent: 1 days
show the balance: 2 days -
2.🗒️ Version 1 of a water reminder must be ready in 11 days. How many days are left for extras after the must-haves?
set a reminder time: 3 days
log a glass of water: 1 days
see today’s total: 3 days - 3.🗒️ A to-do app with no “add a task” feature is ___. (a) missing a must-have (b) ready to release (c) well planned (d) a nice extra
- 4.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) check the answer (b) background music (c) an avatar shop (d) confetti effects
- 5.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) show the balance (b) savings stickers (c) add money received (d) add money spent
-
6.🗒️ Version 1 of a homework planner must be ready in 12 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 4 days
see tasks by day: 3 days -
7.🗒️ Version 1 of a quiz app must be ready in 10 days. How many days are left for extras after the must-haves?
show a question: 4 days
check the answer: 3 days
show the score: 3 days - 8.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) pie-chart colours (b) savings stickers (c) export to a file (d) show the balance
-
9.🗒️ Version 1 of a pocket-money tracker must be ready in 11 days. How many days are left for extras after the must-haves?
add money received: 4 days
add money spent: 4 days
show the balance: 3 days -
10.🗒️ Version 1 of a homework planner must be ready in 14 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 4 days
see tasks by day: 3 days -
11.🗒️ Version 1 of a bus tracker must be ready in 11 days. How many days are left for extras after the must-haves?
see where the bus is: 1 days
show arrival time: 2 days
pick your bus stop: 5 days -
12.🗒️ Version 1 of a water reminder must be ready in 10 days. How many days are left for extras after the must-haves?
set a reminder time: 3 days
log a glass of water: 4 days
see today’s total: 2 days - 13.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) show arrival time (b) rate the driver (c) change the bus icon (d) a dark mode
- 14.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) rate the driver (b) show arrival time (c) pick your bus stop (d) see where the bus is
- 15.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) pick your bus stop (b) show arrival time (c) change the bus icon (d) see where the bus is
- 16.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) custom alert sounds (b) water animations (c) share your streak (d) set a reminder time
- 17.🗒️ Why keep version 1 small? (a) to use up storage (b) to confuse users (c) to learn from users soon (d) to look bigger
-
18.🗒️ Version 1 of a quiz app must be ready in 8 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 3 days
show the score: 4 days - 19.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) confetti effects (b) background music (c) show a question (d) an avatar shop
- 20.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) add a homework task (b) share tasks to friends (c) set a due date (d) see tasks by day
- 21.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show the score (b) check the answer (c) confetti effects (d) show a question
- 22.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) see tasks by day (b) add a homework task (c) set a due date (d) pick a theme colour
- 23.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) export to a file (b) savings stickers (c) pie-chart colours (d) add money received
- 24.🗒️ The first small, working version of an app is often called an ___. (a) MVP (b) URL (c) CPU (d) FAQ
- 25.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) share your streak (b) see today’s total (c) water animations (d) custom alert sounds
- 26.🗒️ What is a must-have feature? (a) a colour theme (b) a sound effect (c) a nice extra (d) one the app cannot skip
- 27.🗒️ In MVP, the M stands for ___. (a) maximum (b) music (c) minimum (d) mobile
- 28.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) see where the bus is (b) pick your bus stop (c) a dark mode (d) show arrival time
-
29.🗒️ Version 1 of a water reminder must be ready in 10 days. How many days are left for extras after the must-haves?
set a reminder time: 4 days
log a glass of water: 1 days
see today’s total: 5 days -
30.🗒️ Version 1 of a homework planner must be ready in 12 days. How many days are left for extras after the must-haves?
add a homework task: 4 days
set a due date: 1 days
see tasks by day: 3 days -
31.🗒️ Version 1 of a homework planner must be ready in 11 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 1 days
see tasks by day: 3 days - 32.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show the score (b) check the answer (c) show a question (d) background music
-
33.🗒️ Version 1 of a pocket-money tracker must be ready in 8 days. How many days are left for extras after the must-haves?
add money received: 2 days
add money spent: 4 days
show the balance: 2 days - 34.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) change the bus icon (b) a dark mode (c) rate the driver (d) see where the bus is
-
35.🗒️ Version 1 of a homework planner must be ready in 19 days. How many days are left for extras after the must-haves?
add a homework task: 4 days
set a due date: 4 days
see tasks by day: 5 days - 36.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) change the bus icon (b) rate the driver (c) a dark mode (d) pick your bus stop
- 37.🗒️ When should nice-to-have features be built? (a) before anything (b) on day one (c) after the must-haves (d) never
-
38.🗒️ Version 1 of a bus tracker must be ready in 13 days. How many days are left for extras after the must-haves?
see where the bus is: 2 days
show arrival time: 4 days
pick your bus stop: 2 days -
39.🗒️ Version 1 of a homework planner must be ready in 8 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 1 days
see tasks by day: 2 days -
40.🗒️ Version 1 of a quiz app must be ready in 12 days. How many days are left for extras after the must-haves?
show a question: 4 days
check the answer: 1 days
show the score: 4 days
Answer key
- 1
- 4
- missing a must-have
- check the answer
- savings stickers
- 3
- 0
- show the balance
- 0
- 6
- 3
- 1
- show arrival time
- rate the driver
- change the bus icon
- set a reminder time
- to learn from users soon
- 0
- show a question
- share tasks to friends
- confetti effects
- pick a theme colour
- add money received
- MVP
- see today’s total
- one the app cannot skip
- minimum
- a dark mode
- 0
- 4
- 4
- background music
- 0
- see where the bus is
- 6
- pick your bus stop
- after the must-haves
- 5
- 4
- 3