App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
- 1.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) check the answer (b) show the score (c) show a question (d) confetti effects
- 2.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) share tasks to friends (b) earn stickers (c) pick a theme colour (d) add a homework task
- 3.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) confetti effects (b) an avatar shop (c) background music (d) show a question
-
4.🗒️ Version 1 of a quiz app must be ready in 11 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 2 days
show the score: 2 days - 5.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) confetti effects (b) check the answer (c) background music (d) an avatar shop
- 6.🗒️ What is a must-have feature? (a) a nice extra (b) a sound effect (c) a colour theme (d) one the app cannot skip
-
7.🗒️ Version 1 of a water reminder must be ready in 12 days. How many days are left for extras after the must-haves?
set a reminder time: 2 days
log a glass of water: 1 days
see today’s total: 3 days - 8.🗒️ The first small, working version of an app is often called an ___. (a) FAQ (b) URL (c) MVP (d) CPU
-
9.🗒️ Version 1 of a homework planner must be ready in 9 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 3 days
see tasks by day: 3 days - 10.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) change the bus icon (b) see where the bus is (c) show arrival time (d) pick your bus stop
- 11.🗒️ In MVP, the M stands for ___. (a) maximum (b) music (c) minimum (d) mobile
-
12.🗒️ Version 1 of a quiz app must be ready in 17 days. How many days are left for extras after the must-haves?
show a question: 4 days
check the answer: 3 days
show the score: 4 days - 13.🗒️ Why keep version 1 small? (a) to confuse users (b) to learn from users soon (c) to use up storage (d) to look bigger
- 14.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) set a reminder time (b) see today’s total (c) custom alert sounds (d) log a glass of water
-
15.🗒️ Version 1 of a quiz app must be ready in 7 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 3 days
show the score: 2 days - 16.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) water animations (b) custom alert sounds (c) share your streak (d) set a reminder time
-
17.🗒️ Version 1 of a pocket-money tracker must be ready in 11 days. How many days are left for extras after the must-haves?
add money received: 3 days
add money spent: 1 days
show the balance: 3 days - 18.🗒️ A to-do app with no “add a task” feature is ___. (a) well planned (b) ready to release (c) missing a must-have (d) a nice extra
-
19.🗒️ Version 1 of a homework planner must be ready in 13 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 2 days
see tasks by day: 5 days - 20.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money spent (b) show the balance (c) pie-chart colours (d) add money received
-
21.🗒️ Version 1 of a pocket-money tracker must be ready in 11 days. How many days are left for extras after the must-haves?
add money received: 4 days
add money spent: 4 days
show the balance: 2 days -
22.🗒️ Version 1 of a quiz app must be ready in 12 days. How many days are left for extras after the must-haves?
show a question: 2 days
check the answer: 4 days
show the score: 5 days - 23.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money received (b) export to a file (c) show the balance (d) add money spent
- 24.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) show arrival time (b) pick your bus stop (c) see where the bus is (d) a dark mode
-
25.🗒️ Version 1 of a homework planner must be ready in 8 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 2 days
see tasks by day: 5 days - 26.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) share tasks to friends (b) earn stickers (c) see tasks by day (d) pick a theme colour
- 27.🗒️ When should nice-to-have features be built? (a) never (b) before anything (c) after the must-haves (d) on day one
-
28.🗒️ Version 1 of a homework planner must be ready in 15 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 2 days
see tasks by day: 5 days - 29.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) savings stickers (b) pie-chart colours (c) add money received (d) export to a file
- 30.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) background music (b) an avatar shop (c) confetti effects (d) show the score
-
31.🗒️ Version 1 of a water reminder must be ready in 11 days. How many days are left for extras after the must-haves?
set a reminder time: 2 days
log a glass of water: 1 days
see today’s total: 4 days -
32.🗒️ Version 1 of a homework planner must be ready in 14 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 3 days
see tasks by day: 3 days - 33.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) pie-chart colours (b) export to a file (c) savings stickers (d) add money spent
- 34.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) see tasks by day (b) set a due date (c) earn stickers (d) add a homework task
- 35.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) set a due date (b) see tasks by day (c) add a homework task (d) pick a theme colour
- 36.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) a dark mode (b) rate the driver (c) change the bus icon (d) see where the bus is
- 37.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money received (b) savings stickers (c) add money spent (d) show the balance
-
38.🗒️ Version 1 of a bus tracker must be ready in 15 days. How many days are left for extras after the must-haves?
see where the bus is: 2 days
show arrival time: 4 days
pick your bus stop: 3 days - 39.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) show arrival time (b) rate the driver (c) pick your bus stop (d) see where the bus is
- 40.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) check the answer (b) show the score (c) show a question (d) an avatar shop
Answer key
- confetti effects
- add a homework task
- show a question
- 6
- check the answer
- one the app cannot skip
- 6
- MVP
- 0
- change the bus icon
- minimum
- 6
- to learn from users soon
- custom alert sounds
- 1
- set a reminder time
- 4
- missing a must-have
- 3
- pie-chart colours
- 1
- 1
- export to a file
- a dark mode
- 0
- see tasks by day
- after the must-haves
- 5
- add money received
- show the score
- 4
- 5
- add money spent
- earn stickers
- pick a theme colour
- see where the bus is
- savings stickers
- 6
- rate the driver
- an avatar shop