App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
-
1.🗒️ Version 1 of a water reminder must be ready in 15 days. How many days are left for extras after the must-haves?
set a reminder time: 2 days
log a glass of water: 2 days
see today’s total: 5 days - 2.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) export to a file (b) pie-chart colours (c) show the balance (d) savings stickers
- 3.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show a question (b) check the answer (c) show the score (d) confetti effects
- 4.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) log a glass of water (b) custom alert sounds (c) share your streak (d) water animations
- 5.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) see where the bus is (b) show arrival time (c) pick your bus stop (d) a dark mode
- 6.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) earn stickers (b) see tasks by day (c) add a homework task (d) set a due date
-
7.🗒️ Version 1 of a bus tracker must be ready in 13 days. How many days are left for extras after the must-haves?
see where the bus is: 1 days
show arrival time: 4 days
pick your bus stop: 4 days - 8.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) add money spent (b) export to a file (c) savings stickers (d) pie-chart colours
-
9.🗒️ Version 1 of a homework planner must be ready in 13 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 1 days
see tasks by day: 4 days - 10.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) share tasks to friends (b) set a due date (c) pick a theme colour (d) earn stickers
- 11.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) pick a theme colour (b) earn stickers (c) see tasks by day (d) share tasks to friends
-
12.🗒️ Version 1 of a water reminder must be ready in 12 days. How many days are left for extras after the must-haves?
set a reminder time: 1 days
log a glass of water: 4 days
see today’s total: 5 days - 13.🗒️ What is a must-have feature? (a) a colour theme (b) a sound effect (c) a nice extra (d) one the app cannot skip
- 14.🗒️ In MVP, the M stands for ___. (a) maximum (b) music (c) minimum (d) mobile
- 15.🗒️ Why keep version 1 small? (a) to look bigger (b) to learn from users soon (c) to confuse users (d) to use up storage
- 16.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) water animations (b) log a glass of water (c) set a reminder time (d) see today’s total
- 17.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) a dark mode (b) rate the driver (c) change the bus icon (d) show arrival time
-
18.🗒️ Version 1 of a pocket-money tracker must be ready in 13 days. How many days are left for extras after the must-haves?
add money received: 3 days
add money spent: 1 days
show the balance: 3 days - 19.🗒️ When should nice-to-have features be built? (a) before anything (b) never (c) after the must-haves (d) on day one
- 20.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) pick a theme colour (b) add a homework task (c) share tasks to friends (d) earn stickers
- 21.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show a question (b) an avatar shop (c) show the score (d) check the answer
- 22.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) show the balance (b) add money spent (c) add money received (d) pie-chart colours
- 23.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) see tasks by day (b) add a homework task (c) set a due date (d) share tasks to friends
- 24.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) log a glass of water (b) set a reminder time (c) custom alert sounds (d) see today’s total
- 25.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) share your streak (b) set a reminder time (c) see today’s total (d) log a glass of water
- 26.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) background music (b) confetti effects (c) check the answer (d) an avatar shop
-
27.🗒️ Version 1 of a bus tracker must be ready in 8 days. How many days are left for extras after the must-haves?
see where the bus is: 2 days
show arrival time: 1 days
pick your bus stop: 5 days -
28.🗒️ Version 1 of a bus tracker must be ready in 9 days. How many days are left for extras after the must-haves?
see where the bus is: 2 days
show arrival time: 3 days
pick your bus stop: 4 days - 29.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) set a due date (b) pick a theme colour (c) add a homework task (d) see tasks by day
- 30.🗒️ The first small, working version of an app is often called an ___. (a) FAQ (b) URL (c) CPU (d) MVP
-
31.🗒️ Version 1 of a homework planner must be ready in 10 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 2 days
see tasks by day: 2 days - 32.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) confetti effects (b) background music (c) show a question (d) an avatar shop
- 33.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show a question (b) check the answer (c) background music (d) show the score
-
34.🗒️ Version 1 of a bus tracker must be ready in 14 days. How many days are left for extras after the must-haves?
see where the bus is: 3 days
show arrival time: 3 days
pick your bus stop: 3 days - 35.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) water animations (b) set a reminder time (c) share your streak (d) custom alert sounds
- 36.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money spent (b) add money received (c) show the balance (d) export to a file
-
37.🗒️ Version 1 of a pocket-money tracker must be ready in 15 days. How many days are left for extras after the must-haves?
add money received: 3 days
add money spent: 4 days
show the balance: 5 days - 38.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) a dark mode (b) see where the bus is (c) change the bus icon (d) rate the driver
- 39.🗒️ A to-do app with no “add a task” feature is ___. (a) a nice extra (b) well planned (c) missing a must-have (d) ready to release
- 40.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) see where the bus is (b) pick your bus stop (c) rate the driver (d) show arrival time
Answer key
- 6
- show the balance
- confetti effects
- log a glass of water
- a dark mode
- earn stickers
- 4
- add money spent
- 5
- set a due date
- see tasks by day
- 2
- one the app cannot skip
- minimum
- to learn from users soon
- water animations
- show arrival time
- 6
- after the must-haves
- add a homework task
- an avatar shop
- pie-chart colours
- share tasks to friends
- custom alert sounds
- share your streak
- check the answer
- 0
- 0
- pick a theme colour
- MVP
- 5
- show a question
- background music
- 5
- set a reminder time
- export to a file
- 3
- see where the bus is
- missing a must-have
- rate the driver