App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
- 1.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) pick a theme colour (b) see tasks by day (c) set a due date (d) add a homework task
- 2.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) share your streak (b) custom alert sounds (c) water animations (d) log a glass of water
- 3.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) change the bus icon (b) show arrival time (c) pick your bus stop (d) see where the bus is
- 4.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) change the bus icon (b) a dark mode (c) pick your bus stop (d) rate the driver
- 5.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) share tasks to friends (b) pick a theme colour (c) set a due date (d) earn stickers
- 6.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) savings stickers (b) pie-chart colours (c) show the balance (d) export to a file
- 7.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) water animations (b) share your streak (c) set a reminder time (d) custom alert sounds
-
8.🗒️ Version 1 of a homework planner must be ready in 16 days. How many days are left for extras after the must-haves?
add a homework task: 4 days
set a due date: 3 days
see tasks by day: 4 days - 9.🗒️ What is a must-have feature? (a) a nice extra (b) one the app cannot skip (c) a sound effect (d) a colour theme
-
10.🗒️ Version 1 of a quiz app must be ready in 9 days. How many days are left for extras after the must-haves?
show a question: 3 days
check the answer: 2 days
show the score: 3 days - 11.🗒️ When should nice-to-have features be built? (a) before anything (b) on day one (c) never (d) after the must-haves
-
12.🗒️ Version 1 of a quiz app must be ready in 12 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 1 days
show the score: 5 days -
13.🗒️ Version 1 of a homework planner must be ready in 11 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 4 days
see tasks by day: 3 days - 14.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) see today’s total (b) set a reminder time (c) log a glass of water (d) share your streak
- 15.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) confetti effects (b) an avatar shop (c) background music (d) show a question
-
16.🗒️ Version 1 of a quiz app must be ready in 12 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 3 days
show the score: 3 days - 17.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) savings stickers (b) pie-chart colours (c) export to a file (d) add money spent
- 18.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) see today’s total (b) set a reminder time (c) custom alert sounds (d) log a glass of water
- 19.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money received (b) savings stickers (c) show the balance (d) add money spent
- 20.🗒️ Why keep version 1 small? (a) to confuse users (b) to use up storage (c) to look bigger (d) to learn from users soon
- 21.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) savings stickers (b) export to a file (c) add money received (d) pie-chart colours
-
22.🗒️ Version 1 of a homework planner must be ready in 13 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 4 days
see tasks by day: 4 days - 23.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) confetti effects (b) background music (c) an avatar shop (d) show the score
- 24.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) share tasks to friends (b) pick a theme colour (c) earn stickers (d) add a homework task
- 25.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) custom alert sounds (b) share your streak (c) see today’s total (d) water animations
- 26.🗒️ A to-do app with no “add a task” feature is ___. (a) missing a must-have (b) a nice extra (c) well planned (d) ready to release
- 27.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) set a due date (b) add a homework task (c) see tasks by day (d) earn stickers
-
28.🗒️ Version 1 of a pocket-money tracker must be ready in 8 days. How many days are left for extras after the must-haves?
add money received: 2 days
add money spent: 1 days
show the balance: 5 days -
29.🗒️ Version 1 of a bus tracker must be ready in 9 days. How many days are left for extras after the must-haves?
see where the bus is: 2 days
show arrival time: 1 days
pick your bus stop: 2 days -
30.🗒️ Version 1 of a quiz app must be ready in 9 days. How many days are left for extras after the must-haves?
show a question: 2 days
check the answer: 1 days
show the score: 2 days - 31.🗒️ The first small, working version of an app is often called an ___. (a) FAQ (b) URL (c) CPU (d) MVP
- 32.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) check the answer (b) show a question (c) show the score (d) confetti effects
- 33.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) show the balance (b) add money spent (c) add money received (d) pie-chart colours
- 34.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) change the bus icon (b) a dark mode (c) rate the driver (d) see where the bus is
-
35.🗒️ Version 1 of a homework planner must be ready in 13 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 2 days
see tasks by day: 3 days -
36.🗒️ Version 1 of a quiz app must be ready in 13 days. How many days are left for extras after the must-haves?
show a question: 3 days
check the answer: 1 days
show the score: 3 days -
37.🗒️ Version 1 of a quiz app must be ready in 10 days. How many days are left for extras after the must-haves?
show a question: 2 days
check the answer: 3 days
show the score: 2 days -
38.🗒️ Version 1 of a pocket-money tracker must be ready in 11 days. How many days are left for extras after the must-haves?
add money received: 2 days
add money spent: 4 days
show the balance: 4 days -
39.🗒️ Version 1 of a quiz app must be ready in 18 days. How many days are left for extras after the must-haves?
show a question: 4 days
check the answer: 4 days
show the score: 5 days -
40.🗒️ Version 1 of a pocket-money tracker must be ready in 13 days. How many days are left for extras after the must-haves?
add money received: 2 days
add money spent: 1 days
show the balance: 5 days
Answer key
- pick a theme colour
- log a glass of water
- change the bus icon
- pick your bus stop
- set a due date
- show the balance
- set a reminder time
- 5
- one the app cannot skip
- 1
- after the must-haves
- 5
- 3
- share your streak
- show a question
- 5
- add money spent
- custom alert sounds
- savings stickers
- to learn from users soon
- add money received
- 3
- show the score
- add a homework task
- see today’s total
- missing a must-have
- earn stickers
- 0
- 4
- 4
- MVP
- confetti effects
- pie-chart colours
- see where the bus is
- 6
- 6
- 3
- 1
- 5
- 5