App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
-
1.🗒️ Version 1 of a bus tracker must be ready in 7 days. How many days are left for extras after the must-haves?
see where the bus is: 1 days
show arrival time: 4 days
pick your bus stop: 2 days - 2.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) add money spent (b) pie-chart colours (c) savings stickers (d) export to a file
- 3.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) see where the bus is (b) show arrival time (c) a dark mode (d) pick your bus stop
- 4.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) background music (b) an avatar shop (c) confetti effects (d) show the score
- 5.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) confetti effects (b) show a question (c) background music (d) an avatar shop
- 6.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) change the bus icon (b) a dark mode (c) rate the driver (d) pick your bus stop
- 7.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) rate the driver (b) a dark mode (c) change the bus icon (d) see where the bus is
- 8.🗒️ The first small, working version of an app is often called an ___. (a) URL (b) FAQ (c) CPU (d) MVP
- 9.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) pie-chart colours (b) show the balance (c) add money spent (d) add money received
- 10.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) see tasks by day (b) share tasks to friends (c) set a due date (d) add a homework task
-
11.🗒️ Version 1 of a pocket-money tracker must be ready in 14 days. How many days are left for extras after the must-haves?
add money received: 1 days
add money spent: 2 days
show the balance: 5 days - 12.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) water animations (b) set a reminder time (c) share your streak (d) custom alert sounds
- 13.🗒️ In MVP, the M stands for ___. (a) maximum (b) minimum (c) music (d) mobile
- 14.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money spent (b) add money received (c) savings stickers (d) show the balance
-
15.🗒️ Version 1 of a bus tracker must be ready in 11 days. How many days are left for extras after the must-haves?
see where the bus is: 3 days
show arrival time: 2 days
pick your bus stop: 4 days - 16.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) check the answer (b) show the score (c) show a question (d) confetti effects
- 17.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) see today’s total (b) set a reminder time (c) log a glass of water (d) water animations
- 18.🗒️ When should nice-to-have features be built? (a) on day one (b) after the must-haves (c) never (d) before anything
- 19.🗒️ Why keep version 1 small? (a) to confuse users (b) to use up storage (c) to look bigger (d) to learn from users soon
- 20.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) check the answer (b) background music (c) an avatar shop (d) confetti effects
-
21.🗒️ Version 1 of a quiz app must be ready in 7 days. How many days are left for extras after the must-haves?
show a question: 3 days
check the answer: 2 days
show the score: 2 days - 22.🗒️ A to-do app with no “add a task” feature is ___. (a) ready to release (b) a nice extra (c) well planned (d) missing a must-have
-
23.🗒️ Version 1 of a bus tracker must be ready in 12 days. How many days are left for extras after the must-haves?
see where the bus is: 4 days
show arrival time: 3 days
pick your bus stop: 3 days - 24.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) add a homework task (b) set a due date (c) see tasks by day (d) earn stickers
- 25.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) earn stickers (b) share tasks to friends (c) pick a theme colour (d) see tasks by day
- 26.🗒️ What is a must-have feature? (a) a nice extra (b) a sound effect (c) one the app cannot skip (d) a colour theme
- 27.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) see today’s total (b) custom alert sounds (c) share your streak (d) water animations
-
28.🗒️ Version 1 of a pocket-money tracker must be ready in 12 days. How many days are left for extras after the must-haves?
add money received: 3 days
add money spent: 1 days
show the balance: 5 days - 29.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) share tasks to friends (b) pick a theme colour (c) earn stickers (d) add a homework task
- 30.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) export to a file (b) pie-chart colours (c) savings stickers (d) show the balance
-
31.🗒️ Version 1 of a homework planner must be ready in 8 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 1 days
see tasks by day: 3 days -
32.🗒️ Version 1 of a quiz app must be ready in 11 days. How many days are left for extras after the must-haves?
show a question: 3 days
check the answer: 4 days
show the score: 2 days -
33.🗒️ Version 1 of a bus tracker must be ready in 14 days. How many days are left for extras after the must-haves?
see where the bus is: 4 days
show arrival time: 1 days
pick your bus stop: 3 days -
34.🗒️ Version 1 of a homework planner must be ready in 8 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 2 days
see tasks by day: 2 days -
35.🗒️ Version 1 of a homework planner must be ready in 13 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 2 days
see tasks by day: 4 days -
36.🗒️ Version 1 of a homework planner must be ready in 12 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 3 days
see tasks by day: 3 days -
37.🗒️ Version 1 of a homework planner must be ready in 14 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 3 days
see tasks by day: 3 days -
38.🗒️ Version 1 of a bus tracker must be ready in 15 days. How many days are left for extras after the must-haves?
see where the bus is: 4 days
show arrival time: 4 days
pick your bus stop: 4 days -
39.🗒️ Version 1 of a quiz app must be ready in 14 days. How many days are left for extras after the must-haves?
show a question: 4 days
check the answer: 1 days
show the score: 5 days - 40.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money spent (b) show the balance (c) export to a file (d) add money received
Answer key
- 0
- add money spent
- a dark mode
- show the score
- show a question
- pick your bus stop
- see where the bus is
- MVP
- pie-chart colours
- share tasks to friends
- 6
- set a reminder time
- minimum
- savings stickers
- 2
- confetti effects
- water animations
- after the must-haves
- to learn from users soon
- check the answer
- 0
- missing a must-have
- 2
- earn stickers
- see tasks by day
- one the app cannot skip
- see today’s total
- 3
- add a homework task
- show the balance
- 1
- 2
- 6
- 2
- 6
- 4
- 5
- 3
- 4
- export to a file