App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
-
1.🗒️ Version 1 of a homework planner must be ready in 15 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 1 days
see tasks by day: 5 days - 2.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) show arrival time (b) a dark mode (c) change the bus icon (d) rate the driver
- 3.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) earn stickers (b) pick a theme colour (c) set a due date (d) share tasks to friends
- 4.🗒️ In MVP, the M stands for ___. (a) minimum (b) mobile (c) music (d) maximum
-
5.🗒️ Version 1 of a homework planner must be ready in 10 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 3 days
see tasks by day: 2 days - 6.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) check the answer (b) show the score (c) show a question (d) an avatar shop
- 7.🗒️ What is a must-have feature? (a) a nice extra (b) a sound effect (c) one the app cannot skip (d) a colour theme
- 8.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) see where the bus is (b) show arrival time (c) pick your bus stop (d) change the bus icon
- 9.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) export to a file (b) add money received (c) add money spent (d) show the balance
- 10.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) show the balance (b) add money spent (c) add money received (d) savings stickers
- 11.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) add a homework task (b) set a due date (c) see tasks by day (d) share tasks to friends
- 12.🗒️ Why keep version 1 small? (a) to confuse users (b) to use up storage (c) to look bigger (d) to learn from users soon
- 13.🗒️ The first small, working version of an app is often called an ___. (a) CPU (b) URL (c) MVP (d) FAQ
- 14.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) custom alert sounds (b) log a glass of water (c) see today’s total (d) set a reminder time
- 15.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) set a reminder time (b) water animations (c) log a glass of water (d) see today’s total
- 16.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) show arrival time (b) pick your bus stop (c) rate the driver (d) see where the bus is
-
17.🗒️ Version 1 of a pocket-money tracker must be ready in 10 days. How many days are left for extras after the must-haves?
add money received: 4 days
add money spent: 4 days
show the balance: 2 days - 18.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) pick a theme colour (b) share tasks to friends (c) add a homework task (d) earn stickers
- 19.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) export to a file (b) pie-chart colours (c) savings stickers (d) show the balance
-
20.🗒️ Version 1 of a homework planner must be ready in 12 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 4 days
see tasks by day: 3 days -
21.🗒️ Version 1 of a homework planner must be ready in 10 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 2 days
see tasks by day: 5 days - 22.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) water animations (b) custom alert sounds (c) share your streak (d) see today’s total
- 23.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) pie-chart colours (b) savings stickers (c) add money spent (d) export to a file
- 24.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) custom alert sounds (b) log a glass of water (c) share your streak (d) water animations
-
25.🗒️ Version 1 of a bus tracker must be ready in 7 days. How many days are left for extras after the must-haves?
see where the bus is: 3 days
show arrival time: 2 days
pick your bus stop: 2 days -
26.🗒️ Version 1 of a pocket-money tracker must be ready in 13 days. How many days are left for extras after the must-haves?
add money received: 4 days
add money spent: 2 days
show the balance: 4 days - 27.🗒️ When should nice-to-have features be built? (a) on day one (b) before anything (c) after the must-haves (d) never
- 28.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) pick your bus stop (b) change the bus icon (c) a dark mode (d) rate the driver
-
29.🗒️ Version 1 of a quiz app must be ready in 6 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 1 days
show the score: 4 days - 30.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) earn stickers (b) add a homework task (c) set a due date (d) see tasks by day
- 31.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money spent (b) show the balance (c) add money received (d) pie-chart colours
- 32.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) an avatar shop (b) background music (c) show the score (d) confetti effects
- 33.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) savings stickers (b) add money received (c) pie-chart colours (d) export to a file
-
34.🗒️ Version 1 of a quiz app must be ready in 13 days. How many days are left for extras after the must-haves?
show a question: 3 days
check the answer: 3 days
show the score: 4 days - 35.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) change the bus icon (b) rate the driver (c) a dark mode (d) see where the bus is
-
36.🗒️ Version 1 of a bus tracker must be ready in 15 days. How many days are left for extras after the must-haves?
see where the bus is: 4 days
show arrival time: 1 days
pick your bus stop: 4 days - 37.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) earn stickers (b) share tasks to friends (c) pick a theme colour (d) see tasks by day
-
38.🗒️ Version 1 of a bus tracker must be ready in 14 days. How many days are left for extras after the must-haves?
see where the bus is: 2 days
show arrival time: 2 days
pick your bus stop: 5 days -
39.🗒️ Version 1 of a homework planner must be ready in 13 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 3 days
see tasks by day: 5 days -
40.🗒️ Version 1 of a bus tracker must be ready in 14 days. How many days are left for extras after the must-haves?
see where the bus is: 2 days
show arrival time: 3 days
pick your bus stop: 3 days
Answer key
- 6
- show arrival time
- set a due date
- minimum
- 2
- an avatar shop
- one the app cannot skip
- change the bus icon
- export to a file
- savings stickers
- share tasks to friends
- to learn from users soon
- MVP
- custom alert sounds
- water animations
- rate the driver
- 0
- add a homework task
- show the balance
- 4
- 1
- see today’s total
- add money spent
- log a glass of water
- 0
- 3
- after the must-haves
- pick your bus stop
- 0
- earn stickers
- pie-chart colours
- show the score
- add money received
- 3
- see where the bus is
- 6
- see tasks by day
- 5
- 4
- 6