App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
- 1.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) check the answer (b) show the score (c) background music (d) show a question
- 2.🗒️ A to-do app with no “add a task” feature is ___. (a) missing a must-have (b) well planned (c) a nice extra (d) ready to release
- 3.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) set a due date (b) add a homework task (c) see tasks by day (d) share tasks to friends
-
4.🗒️ Version 1 of a bus tracker must be ready in 12 days. How many days are left for extras after the must-haves?
see where the bus is: 2 days
show arrival time: 3 days
pick your bus stop: 4 days - 5.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) set a due date (b) share tasks to friends (c) pick a theme colour (d) earn stickers
- 6.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) see today’s total (b) custom alert sounds (c) water animations (d) share your streak
- 7.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) see where the bus is (b) pick your bus stop (c) change the bus icon (d) show arrival time
- 8.🗒️ When should nice-to-have features be built? (a) after the must-haves (b) on day one (c) never (d) before anything
- 9.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money spent (b) show the balance (c) pie-chart colours (d) add money received
-
10.🗒️ Version 1 of a homework planner must be ready in 10 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 2 days
see tasks by day: 3 days - 11.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) show arrival time (b) change the bus icon (c) rate the driver (d) a dark mode
-
12.🗒️ Version 1 of a homework planner must be ready in 12 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 4 days
see tasks by day: 2 days - 13.🗒️ In MVP, the M stands for ___. (a) music (b) maximum (c) minimum (d) mobile
- 14.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) share tasks to friends (b) earn stickers (c) add a homework task (d) pick a theme colour
- 15.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show the score (b) show a question (c) an avatar shop (d) check the answer
- 16.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) savings stickers (b) pie-chart colours (c) export to a file (d) show the balance
-
17.🗒️ Version 1 of a quiz app must be ready in 12 days. How many days are left for extras after the must-haves?
show a question: 4 days
check the answer: 2 days
show the score: 5 days - 18.🗒️ The first small, working version of an app is often called an ___. (a) CPU (b) URL (c) FAQ (d) MVP
-
19.🗒️ Version 1 of a water reminder must be ready in 5 days. How many days are left for extras after the must-haves?
set a reminder time: 1 days
log a glass of water: 2 days
see today’s total: 2 days - 20.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) pie-chart colours (b) savings stickers (c) export to a file (d) add money received
- 21.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) see where the bus is (b) show arrival time (c) a dark mode (d) pick your bus stop
- 22.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) see today’s total (b) water animations (c) set a reminder time (d) log a glass of water
- 23.🗒️ What is a must-have feature? (a) a colour theme (b) one the app cannot skip (c) a sound effect (d) a nice extra
- 24.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) rate the driver (b) a dark mode (c) pick your bus stop (d) change the bus icon
- 25.🗒️ Why keep version 1 small? (a) to use up storage (b) to look bigger (c) to confuse users (d) to learn from users soon
- 26.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) confetti effects (b) an avatar shop (c) show a question (d) background music
-
27.🗒️ Version 1 of a bus tracker must be ready in 7 days. How many days are left for extras after the must-haves?
see where the bus is: 1 days
show arrival time: 1 days
pick your bus stop: 3 days -
28.🗒️ Version 1 of a water reminder must be ready in 12 days. How many days are left for extras after the must-haves?
set a reminder time: 2 days
log a glass of water: 4 days
see today’s total: 3 days -
29.🗒️ Version 1 of a quiz app must be ready in 10 days. How many days are left for extras after the must-haves?
show a question: 2 days
check the answer: 3 days
show the score: 5 days -
30.🗒️ Version 1 of a quiz app must be ready in 15 days. How many days are left for extras after the must-haves?
show a question: 3 days
check the answer: 4 days
show the score: 2 days -
31.🗒️ Version 1 of a bus tracker must be ready in 12 days. How many days are left for extras after the must-haves?
see where the bus is: 4 days
show arrival time: 2 days
pick your bus stop: 2 days - 32.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) check the answer (b) an avatar shop (c) confetti effects (d) background music
-
33.🗒️ Version 1 of a homework planner must be ready in 15 days. How many days are left for extras after the must-haves?
add a homework task: 4 days
set a due date: 3 days
see tasks by day: 2 days -
34.🗒️ Version 1 of a bus tracker must be ready in 15 days. How many days are left for extras after the must-haves?
see where the bus is: 3 days
show arrival time: 4 days
pick your bus stop: 5 days - 35.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) share your streak (b) log a glass of water (c) custom alert sounds (d) water animations
- 36.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) set a reminder time (b) log a glass of water (c) custom alert sounds (d) see today’s total
-
37.🗒️ Version 1 of a homework planner must be ready in 18 days. How many days are left for extras after the must-haves?
add a homework task: 4 days
set a due date: 4 days
see tasks by day: 5 days - 38.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) add a homework task (b) set a due date (c) see tasks by day (d) earn stickers
-
39.🗒️ Version 1 of a bus tracker must be ready in 10 days. How many days are left for extras after the must-haves?
see where the bus is: 4 days
show arrival time: 4 days
pick your bus stop: 2 days -
40.🗒️ Version 1 of a water reminder must be ready in 15 days. How many days are left for extras after the must-haves?
set a reminder time: 2 days
log a glass of water: 2 days
see today’s total: 5 days
Answer key
- background music
- missing a must-have
- share tasks to friends
- 3
- set a due date
- see today’s total
- change the bus icon
- after the must-haves
- pie-chart colours
- 4
- show arrival time
- 3
- minimum
- add a homework task
- an avatar shop
- show the balance
- 1
- MVP
- 0
- add money received
- a dark mode
- water animations
- one the app cannot skip
- pick your bus stop
- to learn from users soon
- show a question
- 2
- 3
- 0
- 6
- 4
- check the answer
- 6
- 3
- log a glass of water
- custom alert sounds
- 5
- earn stickers
- 0
- 6
Free app development lessons, practice and worksheets at talentjr.in/app-development-for-students