App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
- 1.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) savings stickers (b) show the balance (c) export to a file (d) pie-chart colours
-
2.🗒️ Version 1 of a homework planner must be ready in 17 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 4 days
see tasks by day: 4 days - 3.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) set a reminder time (b) water animations (c) log a glass of water (d) see today’s total
-
4.🗒️ Version 1 of a pocket-money tracker must be ready in 7 days. How many days are left for extras after the must-haves?
add money received: 1 days
add money spent: 1 days
show the balance: 3 days - 5.🗒️ The first small, working version of an app is often called an ___. (a) FAQ (b) URL (c) CPU (d) MVP
- 6.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) show arrival time (b) pick your bus stop (c) see where the bus is (d) a dark mode
- 7.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) a dark mode (b) change the bus icon (c) rate the driver (d) show arrival time
- 8.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) show arrival time (b) change the bus icon (c) pick your bus stop (d) see where the bus is
-
9.🗒️ Version 1 of a water reminder must be ready in 7 days. How many days are left for extras after the must-haves?
set a reminder time: 4 days
log a glass of water: 1 days
see today’s total: 2 days - 10.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) share tasks to friends (b) earn stickers (c) pick a theme colour (d) see tasks by day
- 11.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money spent (b) add money received (c) show the balance (d) pie-chart colours
- 12.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) water animations (b) set a reminder time (c) custom alert sounds (d) share your streak
-
13.🗒️ Version 1 of a quiz app must be ready in 10 days. How many days are left for extras after the must-haves?
show a question: 3 days
check the answer: 3 days
show the score: 4 days - 14.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) earn stickers (b) add a homework task (c) share tasks to friends (d) pick a theme colour
- 15.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show the score (b) show a question (c) check the answer (d) background music
- 16.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) confetti effects (b) show a question (c) background music (d) an avatar shop
- 17.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) check the answer (b) show the score (c) confetti effects (d) show a question
- 18.🗒️ What is a must-have feature? (a) one the app cannot skip (b) a nice extra (c) a sound effect (d) a colour theme
- 19.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) export to a file (b) pie-chart colours (c) add money received (d) savings stickers
- 20.🗒️ In MVP, the M stands for ___. (a) maximum (b) mobile (c) music (d) minimum
-
21.🗒️ Version 1 of a quiz app must be ready in 12 days. How many days are left for extras after the must-haves?
show a question: 2 days
check the answer: 2 days
show the score: 5 days -
22.🗒️ Version 1 of a homework planner must be ready in 12 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 1 days
see tasks by day: 2 days - 23.🗒️ Why keep version 1 small? (a) to look bigger (b) to use up storage (c) to confuse users (d) to learn from users soon
- 24.🗒️ When should nice-to-have features be built? (a) on day one (b) before anything (c) after the must-haves (d) never
- 25.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) water animations (b) custom alert sounds (c) see today’s total (d) share your streak
- 26.🗒️ A to-do app with no “add a task” feature is ___. (a) a nice extra (b) missing a must-have (c) well planned (d) ready to release
-
27.🗒️ Version 1 of a bus tracker must be ready in 11 days. How many days are left for extras after the must-haves?
see where the bus is: 4 days
show arrival time: 2 days
pick your bus stop: 2 days - 28.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) an avatar shop (b) background music (c) confetti effects (d) show the score
- 29.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) show arrival time (b) rate the driver (c) pick your bus stop (d) see where the bus is
-
30.🗒️ Version 1 of a homework planner must be ready in 7 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 2 days
see tasks by day: 2 days - 31.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) rate the driver (b) see where the bus is (c) change the bus icon (d) a dark mode
- 32.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) add money spent (b) pie-chart colours (c) savings stickers (d) export to a file
-
33.🗒️ Version 1 of a pocket-money tracker must be ready in 8 days. How many days are left for extras after the must-haves?
add money received: 2 days
add money spent: 1 days
show the balance: 3 days - 34.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) background music (b) confetti effects (c) an avatar shop (d) check the answer
-
35.🗒️ Version 1 of a quiz app must be ready in 12 days. How many days are left for extras after the must-haves?
show a question: 4 days
check the answer: 3 days
show the score: 4 days -
36.🗒️ Version 1 of a homework planner must be ready in 11 days. How many days are left for extras after the must-haves?
add a homework task: 4 days
set a due date: 3 days
see tasks by day: 2 days -
37.🗒️ Version 1 of a water reminder must be ready in 17 days. How many days are left for extras after the must-haves?
set a reminder time: 4 days
log a glass of water: 3 days
see today’s total: 5 days -
38.🗒️ Version 1 of a quiz app must be ready in 7 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 1 days
show the score: 3 days - 39.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money received (b) add money spent (c) savings stickers (d) show the balance
-
40.🗒️ Version 1 of a quiz app must be ready in 14 days. How many days are left for extras after the must-haves?
show a question: 3 days
check the answer: 3 days
show the score: 2 days
Answer key
- show the balance
- 6
- water animations
- 2
- MVP
- a dark mode
- show arrival time
- change the bus icon
- 0
- see tasks by day
- pie-chart colours
- set a reminder time
- 0
- add a homework task
- background music
- show a question
- confetti effects
- one the app cannot skip
- add money received
- minimum
- 3
- 6
- to learn from users soon
- after the must-haves
- see today’s total
- missing a must-have
- 3
- show the score
- rate the driver
- 1
- see where the bus is
- add money spent
- 2
- check the answer
- 1
- 2
- 5
- 2
- savings stickers
- 6