App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
- 1.🗒️ In MVP, the M stands for ___. (a) maximum (b) mobile (c) minimum (d) music
- 2.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money spent (b) show the balance (c) add money received (d) pie-chart colours
- 3.🗒️ When should nice-to-have features be built? (a) before anything (b) never (c) on day one (d) after the must-haves
- 4.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) add a homework task (b) see tasks by day (c) pick a theme colour (d) set a due date
- 5.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) see tasks by day (b) earn stickers (c) share tasks to friends (d) pick a theme colour
- 6.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) add a homework task (b) see tasks by day (c) set a due date (d) share tasks to friends
- 7.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) rate the driver (b) a dark mode (c) show arrival time (d) change the bus icon
- 8.🗒️ Why keep version 1 small? (a) to look bigger (b) to confuse users (c) to use up storage (d) to learn from users soon
- 9.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show a question (b) confetti effects (c) show the score (d) check the answer
- 10.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) show the score (b) confetti effects (c) an avatar shop (d) background music
- 11.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) show the balance (b) add money spent (c) add money received (d) savings stickers
- 12.🗒️ The first small, working version of an app is often called an ___. (a) FAQ (b) MVP (c) CPU (d) URL
-
13.🗒️ Version 1 of a homework planner must be ready in 13 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 2 days
see tasks by day: 4 days - 14.🗒️ A to-do app with no “add a task” feature is ___. (a) missing a must-have (b) well planned (c) ready to release (d) a nice extra
-
15.🗒️ Version 1 of a bus tracker must be ready in 16 days. How many days are left for extras after the must-haves?
see where the bus is: 2 days
show arrival time: 4 days
pick your bus stop: 4 days - 16.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) custom alert sounds (b) share your streak (c) log a glass of water (d) water animations
- 17.🗒️ What is a must-have feature? (a) a sound effect (b) a colour theme (c) one the app cannot skip (d) a nice extra
-
18.🗒️ Version 1 of a homework planner must be ready in 11 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 2 days
see tasks by day: 4 days - 19.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) see today’s total (b) share your streak (c) custom alert sounds (d) water animations
- 20.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) background music (b) an avatar shop (c) confetti effects (d) check the answer
- 21.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) see today’s total (b) share your streak (c) set a reminder time (d) log a glass of water
-
22.🗒️ Version 1 of a quiz app must be ready in 16 days. How many days are left for extras after the must-haves?
show a question: 4 days
check the answer: 4 days
show the score: 2 days -
23.🗒️ Version 1 of a pocket-money tracker must be ready in 15 days. How many days are left for extras after the must-haves?
add money received: 1 days
add money spent: 4 days
show the balance: 5 days -
24.🗒️ Version 1 of a quiz app must be ready in 15 days. How many days are left for extras after the must-haves?
show a question: 3 days
check the answer: 4 days
show the score: 2 days - 25.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show a question (b) show the score (c) an avatar shop (d) check the answer
-
26.🗒️ Version 1 of a homework planner must be ready in 12 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 2 days
see tasks by day: 4 days - 27.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) add a homework task (b) set a due date (c) see tasks by day (d) earn stickers
- 28.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) pick your bus stop (b) rate the driver (c) show arrival time (d) see where the bus is
-
29.🗒️ Version 1 of a homework planner must be ready in 13 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 3 days
see tasks by day: 3 days -
30.🗒️ Version 1 of a pocket-money tracker must be ready in 14 days. How many days are left for extras after the must-haves?
add money received: 3 days
add money spent: 2 days
show the balance: 5 days -
31.🗒️ Version 1 of a water reminder must be ready in 7 days. How many days are left for extras after the must-haves?
set a reminder time: 1 days
log a glass of water: 2 days
see today’s total: 4 days - 32.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) change the bus icon (b) a dark mode (c) see where the bus is (d) rate the driver
- 33.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) change the bus icon (b) show arrival time (c) pick your bus stop (d) see where the bus is
-
34.🗒️ Version 1 of a homework planner must be ready in 12 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 1 days
see tasks by day: 5 days - 35.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) add a homework task (b) earn stickers (c) pick a theme colour (d) share tasks to friends
- 36.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) pie-chart colours (b) export to a file (c) add money received (d) savings stickers
-
37.🗒️ Version 1 of a water reminder must be ready in 12 days. How many days are left for extras after the must-haves?
set a reminder time: 1 days
log a glass of water: 2 days
see today’s total: 5 days -
38.🗒️ Version 1 of a bus tracker must be ready in 8 days. How many days are left for extras after the must-haves?
see where the bus is: 1 days
show arrival time: 2 days
pick your bus stop: 2 days - 39.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) share tasks to friends (b) pick a theme colour (c) set a due date (d) earn stickers
-
40.🗒️ Version 1 of a water reminder must be ready in 8 days. How many days are left for extras after the must-haves?
set a reminder time: 4 days
log a glass of water: 2 days
see today’s total: 2 days
Answer key
- minimum
- pie-chart colours
- after the must-haves
- pick a theme colour
- see tasks by day
- share tasks to friends
- show arrival time
- to learn from users soon
- confetti effects
- show the score
- savings stickers
- MVP
- 5
- missing a must-have
- 6
- log a glass of water
- one the app cannot skip
- 4
- see today’s total
- check the answer
- share your streak
- 6
- 5
- 6
- an avatar shop
- 5
- earn stickers
- rate the driver
- 6
- 4
- 0
- see where the bus is
- change the bus icon
- 4
- add a homework task
- add money received
- 4
- 3
- set a due date
- 0
Free app development lessons, practice and worksheets at talentjr.in/app-development-for-students