App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
-
1.🗒️ Version 1 of a homework planner must be ready in 14 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 3 days
see tasks by day: 5 days - 2.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) set a due date (b) see tasks by day (c) add a homework task (d) pick a theme colour
- 3.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) earn stickers (b) share tasks to friends (c) add a homework task (d) pick a theme colour
- 4.🗒️ What is a must-have feature? (a) a colour theme (b) a nice extra (c) one the app cannot skip (d) a sound effect
-
5.🗒️ Version 1 of a homework planner must be ready in 9 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 2 days
see tasks by day: 2 days -
6.🗒️ Version 1 of a quiz app must be ready in 16 days. How many days are left for extras after the must-haves?
show a question: 3 days
check the answer: 3 days
show the score: 4 days - 7.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) share tasks to friends (b) pick a theme colour (c) earn stickers (d) see tasks by day
-
8.🗒️ Version 1 of a bus tracker must be ready in 10 days. How many days are left for extras after the must-haves?
see where the bus is: 1 days
show arrival time: 4 days
pick your bus stop: 5 days - 9.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) add a homework task (b) set a due date (c) share tasks to friends (d) see tasks by day
-
10.🗒️ Version 1 of a quiz app must be ready in 9 days. How many days are left for extras after the must-haves?
show a question: 2 days
check the answer: 1 days
show the score: 3 days - 11.🗒️ In MVP, the M stands for ___. (a) music (b) minimum (c) maximum (d) mobile
- 12.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) rate the driver (b) see where the bus is (c) a dark mode (d) change the bus icon
- 13.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) change the bus icon (b) see where the bus is (c) pick your bus stop (d) show arrival time
-
14.🗒️ Version 1 of a pocket-money tracker must be ready in 10 days. How many days are left for extras after the must-haves?
add money received: 4 days
add money spent: 3 days
show the balance: 2 days - 15.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money received (b) pie-chart colours (c) show the balance (d) add money spent
- 16.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) show the balance (b) add money received (c) export to a file (d) add money spent
- 17.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show the score (b) show a question (c) check the answer (d) background music
- 18.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) background music (b) show the score (c) an avatar shop (d) confetti effects
- 19.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) confetti effects (b) an avatar shop (c) check the answer (d) background music
- 20.🗒️ When should nice-to-have features be built? (a) after the must-haves (b) before anything (c) never (d) on day one
- 21.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) log a glass of water (b) see today’s total (c) custom alert sounds (d) set a reminder time
- 22.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) water animations (b) custom alert sounds (c) share your streak (d) set a reminder time
- 23.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) see where the bus is (b) a dark mode (c) show arrival time (d) pick your bus stop
-
24.🗒️ Version 1 of a homework planner must be ready in 10 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 2 days
see tasks by day: 4 days - 25.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) water animations (b) custom alert sounds (c) share your streak (d) see today’s total
-
26.🗒️ Version 1 of a bus tracker must be ready in 5 days. How many days are left for extras after the must-haves?
see where the bus is: 1 days
show arrival time: 1 days
pick your bus stop: 2 days - 27.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) an avatar shop (b) show a question (c) show the score (d) check the answer
-
28.🗒️ Version 1 of a homework planner must be ready in 11 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 4 days
see tasks by day: 2 days -
29.🗒️ Version 1 of a homework planner must be ready in 12 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 1 days
see tasks by day: 5 days -
30.🗒️ Version 1 of a bus tracker must be ready in 10 days. How many days are left for extras after the must-haves?
see where the bus is: 2 days
show arrival time: 1 days
pick your bus stop: 5 days - 31.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money received (b) savings stickers (c) add money spent (d) show the balance
-
32.🗒️ Version 1 of a homework planner must be ready in 9 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 2 days
see tasks by day: 2 days -
33.🗒️ Version 1 of a bus tracker must be ready in 9 days. How many days are left for extras after the must-haves?
see where the bus is: 1 days
show arrival time: 1 days
pick your bus stop: 2 days - 34.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) rate the driver (b) pick your bus stop (c) change the bus icon (d) a dark mode
-
35.🗒️ Version 1 of a quiz app must be ready in 12 days. How many days are left for extras after the must-haves?
show a question: 4 days
check the answer: 2 days
show the score: 2 days - 36.🗒️ The first small, working version of an app is often called an ___. (a) MVP (b) URL (c) FAQ (d) CPU
- 37.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) share your streak (b) see today’s total (c) set a reminder time (d) log a glass of water
- 38.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) set a due date (b) pick a theme colour (c) earn stickers (d) share tasks to friends
- 39.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) export to a file (b) pie-chart colours (c) savings stickers (d) add money spent
-
40.🗒️ Version 1 of a pocket-money tracker must be ready in 15 days. How many days are left for extras after the must-haves?
add money received: 3 days
add money spent: 4 days
show the balance: 4 days
Answer key
- 4
- pick a theme colour
- add a homework task
- one the app cannot skip
- 4
- 6
- see tasks by day
- 0
- share tasks to friends
- 3
- minimum
- see where the bus is
- change the bus icon
- 1
- pie-chart colours
- export to a file
- background music
- show the score
- check the answer
- after the must-haves
- custom alert sounds
- set a reminder time
- a dark mode
- 1
- see today’s total
- 1
- an avatar shop
- 3
- 4
- 2
- savings stickers
- 2
- 5
- pick your bus stop
- 4
- MVP
- share your streak
- set a due date
- add money spent
- 4
Free app development lessons, practice and worksheets at talentjr.in/app-development-for-students