App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
- 1.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) check the answer (b) show a question (c) show the score (d) background music
- 2.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) share tasks to friends (b) earn stickers (c) pick a theme colour (d) set a due date
- 3.🗒️ What is a must-have feature? (a) a colour theme (b) a sound effect (c) a nice extra (d) one the app cannot skip
- 4.🗒️ Why keep version 1 small? (a) to look bigger (b) to use up storage (c) to confuse users (d) to learn from users soon
- 5.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) water animations (b) share your streak (c) custom alert sounds (d) set a reminder time
-
6.🗒️ Version 1 of a pocket-money tracker must be ready in 14 days. How many days are left for extras after the must-haves?
add money received: 2 days
add money spent: 4 days
show the balance: 2 days - 7.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) add a homework task (b) set a due date (c) see tasks by day (d) pick a theme colour
- 8.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) an avatar shop (b) background music (c) confetti effects (d) check the answer
- 9.🗒️ The first small, working version of an app is often called an ___. (a) MVP (b) FAQ (c) URL (d) CPU
- 10.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) background music (b) show a question (c) an avatar shop (d) confetti effects
- 11.🗒️ When should nice-to-have features be built? (a) after the must-haves (b) on day one (c) before anything (d) never
- 12.🗒️ In MVP, the M stands for ___. (a) mobile (b) maximum (c) music (d) minimum
- 13.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) pick a theme colour (b) share tasks to friends (c) earn stickers (d) add a homework task
- 14.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) water animations (b) set a reminder time (c) see today’s total (d) log a glass of water
-
15.🗒️ Version 1 of a homework planner must be ready in 9 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 1 days
see tasks by day: 4 days - 16.🗒️ A to-do app with no “add a task” feature is ___. (a) ready to release (b) well planned (c) a nice extra (d) missing a must-have
-
17.🗒️ Version 1 of a quiz app must be ready in 15 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 3 days
show the score: 5 days -
18.🗒️ Version 1 of a water reminder must be ready in 11 days. How many days are left for extras after the must-haves?
set a reminder time: 4 days
log a glass of water: 1 days
see today’s total: 3 days -
19.🗒️ Version 1 of a pocket-money tracker must be ready in 7 days. How many days are left for extras after the must-haves?
add money received: 2 days
add money spent: 3 days
show the balance: 2 days -
20.🗒️ Version 1 of a water reminder must be ready in 9 days. How many days are left for extras after the must-haves?
set a reminder time: 2 days
log a glass of water: 3 days
see today’s total: 3 days - 21.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) an avatar shop (b) show the score (c) show a question (d) check the answer
- 22.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) see where the bus is (b) change the bus icon (c) a dark mode (d) rate the driver
- 23.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) export to a file (b) add money spent (c) pie-chart colours (d) savings stickers
- 24.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) change the bus icon (b) rate the driver (c) a dark mode (d) show arrival time
-
25.🗒️ Version 1 of a water reminder must be ready in 11 days. How many days are left for extras after the must-haves?
set a reminder time: 4 days
log a glass of water: 4 days
see today’s total: 3 days -
26.🗒️ Version 1 of a homework planner must be ready in 11 days. How many days are left for extras after the must-haves?
add a homework task: 4 days
set a due date: 2 days
see tasks by day: 5 days -
27.🗒️ Version 1 of a quiz app must be ready in 8 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 1 days
show the score: 2 days - 28.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) custom alert sounds (b) water animations (c) share your streak (d) see today’s total
- 29.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money spent (b) add money received (c) savings stickers (d) show the balance
-
30.🗒️ Version 1 of a homework planner must be ready in 10 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 4 days
see tasks by day: 4 days - 31.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) show the balance (b) pie-chart colours (c) add money received (d) add money spent
-
32.🗒️ Version 1 of a homework planner must be ready in 6 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 2 days
see tasks by day: 2 days -
33.🗒️ Version 1 of a water reminder must be ready in 14 days. How many days are left for extras after the must-haves?
set a reminder time: 3 days
log a glass of water: 3 days
see today’s total: 5 days - 34.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) savings stickers (b) export to a file (c) add money received (d) pie-chart colours
- 35.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) an avatar shop (b) background music (c) confetti effects (d) show the score
- 36.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) change the bus icon (b) show arrival time (c) see where the bus is (d) pick your bus stop
- 37.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) see where the bus is (b) show arrival time (c) pick your bus stop (d) rate the driver
-
38.🗒️ Version 1 of a water reminder must be ready in 4 days. How many days are left for extras after the must-haves?
set a reminder time: 1 days
log a glass of water: 1 days
see today’s total: 2 days -
39.🗒️ Version 1 of a quiz app must be ready in 13 days. How many days are left for extras after the must-haves?
show a question: 3 days
check the answer: 2 days
show the score: 3 days -
40.🗒️ Version 1 of a bus tracker must be ready in 17 days. How many days are left for extras after the must-haves?
see where the bus is: 4 days
show arrival time: 4 days
pick your bus stop: 5 days
Answer key
- background music
- set a due date
- one the app cannot skip
- to learn from users soon
- set a reminder time
- 6
- pick a theme colour
- check the answer
- MVP
- show a question
- after the must-haves
- minimum
- add a homework task
- water animations
- 1
- missing a must-have
- 6
- 3
- 0
- 1
- an avatar shop
- see where the bus is
- add money spent
- show arrival time
- 0
- 0
- 4
- see today’s total
- savings stickers
- 0
- pie-chart colours
- 1
- 3
- add money received
- show the score
- change the bus icon
- rate the driver
- 0
- 5
- 4