App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
- 1.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) share tasks to friends (b) pick a theme colour (c) earn stickers (d) see tasks by day
-
2.🗒️ Version 1 of a quiz app must be ready in 13 days. How many days are left for extras after the must-haves?
show a question: 3 days
check the answer: 1 days
show the score: 3 days - 3.🗒️ The first small, working version of an app is often called an ___. (a) FAQ (b) MVP (c) CPU (d) URL
- 4.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) log a glass of water (b) set a reminder time (c) share your streak (d) see today’s total
- 5.🗒️ What is a must-have feature? (a) a colour theme (b) a nice extra (c) a sound effect (d) one the app cannot skip
- 6.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) pie-chart colours (b) export to a file (c) add money received (d) savings stickers
- 7.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) see today’s total (b) log a glass of water (c) set a reminder time (d) water animations
-
8.🗒️ Version 1 of a quiz app must be ready in 9 days. How many days are left for extras after the must-haves?
show a question: 2 days
check the answer: 2 days
show the score: 2 days - 9.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) show arrival time (b) see where the bus is (c) a dark mode (d) pick your bus stop
- 10.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) confetti effects (b) an avatar shop (c) show a question (d) background music
-
11.🗒️ Version 1 of a bus tracker must be ready in 13 days. How many days are left for extras after the must-haves?
see where the bus is: 1 days
show arrival time: 2 days
pick your bus stop: 4 days -
12.🗒️ Version 1 of a quiz app must be ready in 9 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 2 days
show the score: 5 days - 13.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) confetti effects (b) background music (c) an avatar shop (d) show the score
- 14.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) share your streak (b) custom alert sounds (c) see today’s total (d) water animations
-
15.🗒️ Version 1 of a quiz app must be ready in 15 days. How many days are left for extras after the must-haves?
show a question: 3 days
check the answer: 4 days
show the score: 3 days - 16.🗒️ When should nice-to-have features be built? (a) before anything (b) on day one (c) after the must-haves (d) never
-
17.🗒️ Version 1 of a bus tracker must be ready in 13 days. How many days are left for extras after the must-haves?
see where the bus is: 4 days
show arrival time: 2 days
pick your bus stop: 3 days - 18.🗒️ A to-do app with no “add a task” feature is ___. (a) a nice extra (b) ready to release (c) well planned (d) missing a must-have
- 19.🗒️ In MVP, the M stands for ___. (a) maximum (b) mobile (c) music (d) minimum
- 20.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) share your streak (b) set a reminder time (c) custom alert sounds (d) water animations
-
21.🗒️ Version 1 of a pocket-money tracker must be ready in 15 days. How many days are left for extras after the must-haves?
add money received: 4 days
add money spent: 4 days
show the balance: 2 days - 22.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show the score (b) check the answer (c) an avatar shop (d) show a question
- 23.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) set a due date (b) add a homework task (c) see tasks by day (d) earn stickers
-
24.🗒️ Version 1 of a quiz app must be ready in 9 days. How many days are left for extras after the must-haves?
show a question: 3 days
check the answer: 2 days
show the score: 3 days - 25.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) pie-chart colours (b) savings stickers (c) show the balance (d) export to a file
- 26.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) change the bus icon (b) rate the driver (c) see where the bus is (d) a dark mode
-
27.🗒️ Version 1 of a water reminder must be ready in 14 days. How many days are left for extras after the must-haves?
set a reminder time: 2 days
log a glass of water: 4 days
see today’s total: 4 days - 28.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) share tasks to friends (b) pick a theme colour (c) earn stickers (d) set a due date
-
29.🗒️ Version 1 of a pocket-money tracker must be ready in 10 days. How many days are left for extras after the must-haves?
add money received: 1 days
add money spent: 3 days
show the balance: 5 days - 30.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) pie-chart colours (b) add money spent (c) export to a file (d) savings stickers
- 31.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) see where the bus is (b) change the bus icon (c) pick your bus stop (d) show arrival time
-
32.🗒️ Version 1 of a homework planner must be ready in 10 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 2 days
see tasks by day: 4 days - 33.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show the score (b) confetti effects (c) check the answer (d) show a question
-
34.🗒️ Version 1 of a water reminder must be ready in 14 days. How many days are left for extras after the must-haves?
set a reminder time: 3 days
log a glass of water: 1 days
see today’s total: 5 days - 35.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) pick your bus stop (b) rate the driver (c) show arrival time (d) see where the bus is
- 36.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money received (b) show the balance (c) pie-chart colours (d) add money spent
- 37.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) see tasks by day (b) share tasks to friends (c) set a due date (d) add a homework task
- 38.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) rate the driver (b) show arrival time (c) a dark mode (d) change the bus icon
-
39.🗒️ Version 1 of a bus tracker must be ready in 10 days. How many days are left for extras after the must-haves?
see where the bus is: 1 days
show arrival time: 4 days
pick your bus stop: 2 days - 40.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) pick a theme colour (b) see tasks by day (c) set a due date (d) add a homework task
Answer key
- see tasks by day
- 6
- MVP
- share your streak
- one the app cannot skip
- add money received
- water animations
- 3
- a dark mode
- show a question
- 6
- 1
- show the score
- see today’s total
- 5
- after the must-haves
- 4
- missing a must-have
- minimum
- set a reminder time
- 5
- an avatar shop
- earn stickers
- 1
- show the balance
- see where the bus is
- 4
- set a due date
- 1
- add money spent
- change the bus icon
- 2
- confetti effects
- 5
- rate the driver
- pie-chart colours
- share tasks to friends
- show arrival time
- 3
- pick a theme colour