App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
-
1.🗒️ Version 1 of a water reminder must be ready in 13 days. How many days are left for extras after the must-haves?
set a reminder time: 4 days
log a glass of water: 1 days
see today’s total: 3 days - 2.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) custom alert sounds (b) see today’s total (c) set a reminder time (d) log a glass of water
-
3.🗒️ Version 1 of a homework planner must be ready in 11 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 1 days
see tasks by day: 3 days - 4.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) pick your bus stop (b) show arrival time (c) rate the driver (d) see where the bus is
- 5.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) share tasks to friends (b) pick a theme colour (c) earn stickers (d) see tasks by day
-
6.🗒️ Version 1 of a water reminder must be ready in 8 days. How many days are left for extras after the must-haves?
set a reminder time: 2 days
log a glass of water: 1 days
see today’s total: 3 days -
7.🗒️ Version 1 of a bus tracker must be ready in 13 days. How many days are left for extras after the must-haves?
see where the bus is: 4 days
show arrival time: 4 days
pick your bus stop: 3 days - 8.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) set a reminder time (b) custom alert sounds (c) water animations (d) share your streak
- 9.🗒️ When should nice-to-have features be built? (a) never (b) after the must-haves (c) before anything (d) on day one
- 10.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) log a glass of water (b) set a reminder time (c) see today’s total (d) water animations
- 11.🗒️ The first small, working version of an app is often called an ___. (a) MVP (b) CPU (c) FAQ (d) URL
-
12.🗒️ Version 1 of a homework planner must be ready in 12 days. How many days are left for extras after the must-haves?
add a homework task: 4 days
set a due date: 2 days
see tasks by day: 5 days -
13.🗒️ Version 1 of a bus tracker must be ready in 13 days. How many days are left for extras after the must-haves?
see where the bus is: 3 days
show arrival time: 3 days
pick your bus stop: 2 days - 14.🗒️ Why keep version 1 small? (a) to use up storage (b) to look bigger (c) to confuse users (d) to learn from users soon
-
15.🗒️ Version 1 of a water reminder must be ready in 12 days. How many days are left for extras after the must-haves?
set a reminder time: 2 days
log a glass of water: 3 days
see today’s total: 3 days - 16.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) confetti effects (b) background music (c) an avatar shop (d) check the answer
- 17.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) show arrival time (b) change the bus icon (c) see where the bus is (d) pick your bus stop
- 18.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) share tasks to friends (b) set a due date (c) see tasks by day (d) add a homework task
- 19.🗒️ In MVP, the M stands for ___. (a) music (b) minimum (c) mobile (d) maximum
- 20.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) a dark mode (b) pick your bus stop (c) change the bus icon (d) rate the driver
-
21.🗒️ Version 1 of a bus tracker must be ready in 13 days. How many days are left for extras after the must-haves?
see where the bus is: 1 days
show arrival time: 3 days
pick your bus stop: 4 days - 22.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) custom alert sounds (b) water animations (c) share your streak (d) log a glass of water
- 23.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) pie-chart colours (b) export to a file (c) add money spent (d) savings stickers
- 24.🗒️ A to-do app with no “add a task” feature is ___. (a) well planned (b) a nice extra (c) ready to release (d) missing a must-have
- 25.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) background music (b) an avatar shop (c) show the score (d) confetti effects
- 26.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) share your streak (b) see today’s total (c) custom alert sounds (d) water animations
-
27.🗒️ Version 1 of a pocket-money tracker must be ready in 13 days. How many days are left for extras after the must-haves?
add money received: 3 days
add money spent: 4 days
show the balance: 2 days - 28.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) show the balance (b) pie-chart colours (c) add money spent (d) add money received
- 29.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) share tasks to friends (b) pick a theme colour (c) set a due date (d) earn stickers
- 30.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) see where the bus is (b) rate the driver (c) a dark mode (d) change the bus icon
-
31.🗒️ Version 1 of a bus tracker must be ready in 14 days. How many days are left for extras after the must-haves?
see where the bus is: 1 days
show arrival time: 3 days
pick your bus stop: 5 days - 32.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) pick a theme colour (b) see tasks by day (c) set a due date (d) add a homework task
- 33.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) an avatar shop (b) show a question (c) show the score (d) check the answer
-
34.🗒️ Version 1 of a water reminder must be ready in 8 days. How many days are left for extras after the must-haves?
set a reminder time: 2 days
log a glass of water: 1 days
see today’s total: 5 days -
35.🗒️ Version 1 of a water reminder must be ready in 10 days. How many days are left for extras after the must-haves?
set a reminder time: 1 days
log a glass of water: 1 days
see today’s total: 4 days - 36.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) confetti effects (b) check the answer (c) show the score (d) show a question
- 37.🗒️ What is a must-have feature? (a) a sound effect (b) a nice extra (c) one the app cannot skip (d) a colour theme
-
38.🗒️ Version 1 of a bus tracker must be ready in 13 days. How many days are left for extras after the must-haves?
see where the bus is: 1 days
show arrival time: 2 days
pick your bus stop: 4 days - 39.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) a dark mode (b) rate the driver (c) show arrival time (d) change the bus icon
- 40.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) add a homework task (b) share tasks to friends (c) earn stickers (d) pick a theme colour
Answer key
- 5
- custom alert sounds
- 6
- rate the driver
- see tasks by day
- 2
- 2
- set a reminder time
- after the must-haves
- water animations
- MVP
- 1
- 5
- to learn from users soon
- 4
- check the answer
- change the bus icon
- share tasks to friends
- minimum
- pick your bus stop
- 5
- log a glass of water
- add money spent
- missing a must-have
- show the score
- see today’s total
- 4
- pie-chart colours
- set a due date
- see where the bus is
- 5
- pick a theme colour
- an avatar shop
- 0
- 4
- confetti effects
- one the app cannot skip
- 6
- show arrival time
- add a homework task