App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
- 1.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) water animations (b) log a glass of water (c) set a reminder time (d) see today’s total
- 2.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) rate the driver (b) see where the bus is (c) a dark mode (d) change the bus icon
- 3.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show the score (b) confetti effects (c) check the answer (d) show a question
-
4.🗒️ Version 1 of a pocket-money tracker must be ready in 12 days. How many days are left for extras after the must-haves?
add money received: 4 days
add money spent: 1 days
show the balance: 2 days -
5.🗒️ Version 1 of a quiz app must be ready in 13 days. How many days are left for extras after the must-haves?
show a question: 2 days
check the answer: 2 days
show the score: 5 days -
6.🗒️ Version 1 of a pocket-money tracker must be ready in 10 days. How many days are left for extras after the must-haves?
add money received: 3 days
add money spent: 1 days
show the balance: 2 days -
7.🗒️ Version 1 of a bus tracker must be ready in 14 days. How many days are left for extras after the must-haves?
see where the bus is: 3 days
show arrival time: 3 days
pick your bus stop: 4 days - 8.🗒️ When should nice-to-have features be built? (a) on day one (b) before anything (c) never (d) after the must-haves
- 9.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) pick a theme colour (b) share tasks to friends (c) earn stickers (d) add a homework task
- 10.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) a dark mode (b) see where the bus is (c) show arrival time (d) pick your bus stop
- 11.🗒️ Why keep version 1 small? (a) to look bigger (b) to confuse users (c) to learn from users soon (d) to use up storage
- 12.🗒️ What is a must-have feature? (a) a nice extra (b) one the app cannot skip (c) a colour theme (d) a sound effect
- 13.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) export to a file (b) pie-chart colours (c) add money received (d) savings stickers
-
14.🗒️ Version 1 of a bus tracker must be ready in 15 days. How many days are left for extras after the must-haves?
see where the bus is: 4 days
show arrival time: 3 days
pick your bus stop: 4 days - 15.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) rate the driver (b) show arrival time (c) see where the bus is (d) pick your bus stop
- 16.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) custom alert sounds (b) log a glass of water (c) water animations (d) share your streak
-
17.🗒️ Version 1 of a quiz app must be ready in 12 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 2 days
show the score: 5 days - 18.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) pie-chart colours (b) show the balance (c) savings stickers (d) export to a file
- 19.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) custom alert sounds (b) water animations (c) share your streak (d) set a reminder time
- 20.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money spent (b) export to a file (c) add money received (d) show the balance
- 21.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) an avatar shop (b) confetti effects (c) show a question (d) background music
- 22.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) share your streak (b) custom alert sounds (c) water animations (d) see today’s total
- 23.🗒️ A to-do app with no “add a task” feature is ___. (a) a nice extra (b) ready to release (c) missing a must-have (d) well planned
- 24.🗒️ In MVP, the M stands for ___. (a) minimum (b) mobile (c) maximum (d) music
-
25.🗒️ Version 1 of a homework planner must be ready in 7 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 1 days
see tasks by day: 4 days - 26.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) add a homework task (b) set a due date (c) earn stickers (d) see tasks by day
-
27.🗒️ Version 1 of a quiz app must be ready in 8 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 1 days
show the score: 3 days - 28.🗒️ The first small, working version of an app is often called an ___. (a) URL (b) MVP (c) CPU (d) FAQ
- 29.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money received (b) show the balance (c) add money spent (d) pie-chart colours
-
30.🗒️ Version 1 of a pocket-money tracker must be ready in 15 days. How many days are left for extras after the must-haves?
add money received: 4 days
add money spent: 4 days
show the balance: 4 days - 31.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show a question (b) check the answer (c) background music (d) show the score
-
32.🗒️ Version 1 of a pocket-money tracker must be ready in 7 days. How many days are left for extras after the must-haves?
add money received: 1 days
add money spent: 2 days
show the balance: 3 days -
33.🗒️ Version 1 of a water reminder must be ready in 9 days. How many days are left for extras after the must-haves?
set a reminder time: 2 days
log a glass of water: 1 days
see today’s total: 4 days -
34.🗒️ Version 1 of a homework planner must be ready in 6 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 2 days
see tasks by day: 2 days -
35.🗒️ Version 1 of a water reminder must be ready in 16 days. How many days are left for extras after the must-haves?
set a reminder time: 4 days
log a glass of water: 2 days
see today’s total: 5 days -
36.🗒️ Version 1 of a quiz app must be ready in 9 days. How many days are left for extras after the must-haves?
show a question: 4 days
check the answer: 1 days
show the score: 2 days - 37.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) share tasks to friends (b) pick a theme colour (c) set a due date (d) earn stickers
- 38.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) an avatar shop (b) background music (c) confetti effects (d) check the answer
-
39.🗒️ Version 1 of a bus tracker must be ready in 8 days. How many days are left for extras after the must-haves?
see where the bus is: 1 days
show arrival time: 1 days
pick your bus stop: 3 days - 40.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) see today’s total (b) custom alert sounds (c) set a reminder time (d) log a glass of water
Answer key
- water animations
- see where the bus is
- confetti effects
- 5
- 4
- 4
- 4
- after the must-haves
- add a homework task
- a dark mode
- to learn from users soon
- one the app cannot skip
- add money received
- 4
- rate the driver
- log a glass of water
- 4
- show the balance
- set a reminder time
- export to a file
- show a question
- see today’s total
- missing a must-have
- minimum
- 1
- earn stickers
- 3
- MVP
- pie-chart colours
- 3
- background music
- 1
- 2
- 1
- 5
- 2
- set a due date
- check the answer
- 3
- custom alert sounds
Free app development lessons, practice and worksheets at talentjr.in/app-development-for-students