App Dev Worksheet: Planning Features

App development lesson 6: Planning features: must-haves first · Set 63 · 40 questions
TalentJR

Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.

NameDateTime takenScore ___ / 40
  1. 1.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) water animations (b) log a glass of water (c) set a reminder time (d) see today’s total
  2. 2.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) rate the driver (b) see where the bus is (c) a dark mode (d) change the bus icon
  3. 3.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show the score (b) confetti effects (c) check the answer (d) show a question
  4. 4.🗒️ Version 1 of a pocket-money tracker must be ready in 12 days. How many days are left for extras after the must-haves?
    add money received: 4 days
    add money spent: 1 days
    show the balance: 2 days
  5. 5.🗒️ Version 1 of a quiz app must be ready in 13 days. How many days are left for extras after the must-haves?
    show a question: 2 days
    check the answer: 2 days
    show the score: 5 days
  6. 6.🗒️ Version 1 of a pocket-money tracker must be ready in 10 days. How many days are left for extras after the must-haves?
    add money received: 3 days
    add money spent: 1 days
    show the balance: 2 days
  7. 7.🗒️ Version 1 of a bus tracker must be ready in 14 days. How many days are left for extras after the must-haves?
    see where the bus is: 3 days
    show arrival time: 3 days
    pick your bus stop: 4 days
  8. 8.🗒️ When should nice-to-have features be built? (a) on day one (b) before anything (c) never (d) after the must-haves
  9. 9.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) pick a theme colour (b) share tasks to friends (c) earn stickers (d) add a homework task
  10. 10.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) a dark mode (b) see where the bus is (c) show arrival time (d) pick your bus stop
  11. 11.🗒️ Why keep version 1 small? (a) to look bigger (b) to confuse users (c) to learn from users soon (d) to use up storage
  12. 12.🗒️ What is a must-have feature? (a) a nice extra (b) one the app cannot skip (c) a colour theme (d) a sound effect
  13. 13.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) export to a file (b) pie-chart colours (c) add money received (d) savings stickers
  14. 14.🗒️ Version 1 of a bus tracker must be ready in 15 days. How many days are left for extras after the must-haves?
    see where the bus is: 4 days
    show arrival time: 3 days
    pick your bus stop: 4 days
  15. 15.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) rate the driver (b) show arrival time (c) see where the bus is (d) pick your bus stop
  16. 16.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) custom alert sounds (b) log a glass of water (c) water animations (d) share your streak
  17. 17.🗒️ Version 1 of a quiz app must be ready in 12 days. How many days are left for extras after the must-haves?
    show a question: 1 days
    check the answer: 2 days
    show the score: 5 days
  18. 18.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) pie-chart colours (b) show the balance (c) savings stickers (d) export to a file
  19. 19.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) custom alert sounds (b) water animations (c) share your streak (d) set a reminder time
  20. 20.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money spent (b) export to a file (c) add money received (d) show the balance
  21. 21.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) an avatar shop (b) confetti effects (c) show a question (d) background music
  22. 22.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) share your streak (b) custom alert sounds (c) water animations (d) see today’s total
  23. 23.🗒️ A to-do app with no “add a task” feature is ___. (a) a nice extra (b) ready to release (c) missing a must-have (d) well planned
  24. 24.🗒️ In MVP, the M stands for ___. (a) minimum (b) mobile (c) maximum (d) music
  25. 25.🗒️ Version 1 of a homework planner must be ready in 7 days. How many days are left for extras after the must-haves?
    add a homework task: 1 days
    set a due date: 1 days
    see tasks by day: 4 days
  26. 26.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) add a homework task (b) set a due date (c) earn stickers (d) see tasks by day
  27. 27.🗒️ Version 1 of a quiz app must be ready in 8 days. How many days are left for extras after the must-haves?
    show a question: 1 days
    check the answer: 1 days
    show the score: 3 days
  28. 28.🗒️ The first small, working version of an app is often called an ___. (a) URL (b) MVP (c) CPU (d) FAQ
  29. 29.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money received (b) show the balance (c) add money spent (d) pie-chart colours
  30. 30.🗒️ Version 1 of a pocket-money tracker must be ready in 15 days. How many days are left for extras after the must-haves?
    add money received: 4 days
    add money spent: 4 days
    show the balance: 4 days
  31. 31.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show a question (b) check the answer (c) background music (d) show the score
  32. 32.🗒️ Version 1 of a pocket-money tracker must be ready in 7 days. How many days are left for extras after the must-haves?
    add money received: 1 days
    add money spent: 2 days
    show the balance: 3 days
  33. 33.🗒️ Version 1 of a water reminder must be ready in 9 days. How many days are left for extras after the must-haves?
    set a reminder time: 2 days
    log a glass of water: 1 days
    see today’s total: 4 days
  34. 34.🗒️ Version 1 of a homework planner must be ready in 6 days. How many days are left for extras after the must-haves?
    add a homework task: 1 days
    set a due date: 2 days
    see tasks by day: 2 days
  35. 35.🗒️ Version 1 of a water reminder must be ready in 16 days. How many days are left for extras after the must-haves?
    set a reminder time: 4 days
    log a glass of water: 2 days
    see today’s total: 5 days
  36. 36.🗒️ Version 1 of a quiz app must be ready in 9 days. How many days are left for extras after the must-haves?
    show a question: 4 days
    check the answer: 1 days
    show the score: 2 days
  37. 37.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) share tasks to friends (b) pick a theme colour (c) set a due date (d) earn stickers
  38. 38.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) an avatar shop (b) background music (c) confetti effects (d) check the answer
  39. 39.🗒️ Version 1 of a bus tracker must be ready in 8 days. How many days are left for extras after the must-haves?
    see where the bus is: 1 days
    show arrival time: 1 days
    pick your bus stop: 3 days
  40. 40.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) see today’s total (b) custom alert sounds (c) set a reminder time (d) log a glass of water

Answer key

  1. water animations
  2. see where the bus is
  3. confetti effects
  4. 5
  5. 4
  6. 4
  7. 4
  8. after the must-haves
  9. add a homework task
  10. a dark mode
  11. to learn from users soon
  12. one the app cannot skip
  13. add money received
  14. 4
  15. rate the driver
  16. log a glass of water
  17. 4
  18. show the balance
  19. set a reminder time
  20. export to a file
  21. show a question
  22. see today’s total
  23. missing a must-have
  24. minimum
  25. 1
  26. earn stickers
  27. 3
  28. MVP
  29. pie-chart colours
  30. 3
  31. background music
  32. 1
  33. 2
  34. 1
  35. 5
  36. 2
  37. set a due date
  38. check the answer
  39. 3
  40. custom alert sounds