App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
- 1.🗒️ What is a must-have feature? (a) a nice extra (b) a colour theme (c) one the app cannot skip (d) a sound effect
-
2.🗒️ Version 1 of a homework planner must be ready in 12 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 4 days
see tasks by day: 5 days -
3.🗒️ Version 1 of a quiz app must be ready in 12 days. How many days are left for extras after the must-haves?
show a question: 4 days
check the answer: 2 days
show the score: 5 days -
4.🗒️ Version 1 of a pocket-money tracker must be ready in 12 days. How many days are left for extras after the must-haves?
add money received: 2 days
add money spent: 3 days
show the balance: 2 days -
5.🗒️ Version 1 of a bus tracker must be ready in 10 days. How many days are left for extras after the must-haves?
see where the bus is: 2 days
show arrival time: 3 days
pick your bus stop: 2 days - 6.🗒️ In MVP, the M stands for ___. (a) minimum (b) music (c) mobile (d) maximum
- 7.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) custom alert sounds (b) water animations (c) share your streak (d) set a reminder time
- 8.🗒️ When should nice-to-have features be built? (a) on day one (b) after the must-haves (c) before anything (d) never
- 9.🗒️ Why keep version 1 small? (a) to confuse users (b) to look bigger (c) to use up storage (d) to learn from users soon
-
10.🗒️ Version 1 of a bus tracker must be ready in 17 days. How many days are left for extras after the must-haves?
see where the bus is: 4 days
show arrival time: 4 days
pick your bus stop: 4 days - 11.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) see tasks by day (b) set a due date (c) add a homework task (d) share tasks to friends
-
12.🗒️ Version 1 of a bus tracker must be ready in 10 days. How many days are left for extras after the must-haves?
see where the bus is: 2 days
show arrival time: 4 days
pick your bus stop: 2 days - 13.🗒️ The first small, working version of an app is often called an ___. (a) URL (b) CPU (c) MVP (d) FAQ
- 14.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) confetti effects (b) background music (c) an avatar shop (d) check the answer
- 15.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) see today’s total (b) log a glass of water (c) set a reminder time (d) water animations
-
16.🗒️ Version 1 of a pocket-money tracker must be ready in 12 days. How many days are left for extras after the must-haves?
add money received: 2 days
add money spent: 2 days
show the balance: 4 days -
17.🗒️ Version 1 of a bus tracker must be ready in 9 days. How many days are left for extras after the must-haves?
see where the bus is: 2 days
show arrival time: 2 days
pick your bus stop: 2 days -
18.🗒️ Version 1 of a bus tracker must be ready in 15 days. How many days are left for extras after the must-haves?
see where the bus is: 4 days
show arrival time: 3 days
pick your bus stop: 3 days -
19.🗒️ Version 1 of a quiz app must be ready in 12 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 4 days
show the score: 2 days - 20.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) an avatar shop (b) show the score (c) background music (d) confetti effects
- 21.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) pie-chart colours (b) export to a file (c) savings stickers (d) add money spent
- 22.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) earn stickers (b) pick a theme colour (c) see tasks by day (d) share tasks to friends
- 23.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) change the bus icon (b) rate the driver (c) pick your bus stop (d) a dark mode
-
24.🗒️ Version 1 of a pocket-money tracker must be ready in 16 days. How many days are left for extras after the must-haves?
add money received: 3 days
add money spent: 4 days
show the balance: 4 days -
25.🗒️ Version 1 of a bus tracker must be ready in 14 days. How many days are left for extras after the must-haves?
see where the bus is: 3 days
show arrival time: 3 days
pick your bus stop: 5 days - 26.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) export to a file (b) pie-chart colours (c) savings stickers (d) add money received
- 27.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) show arrival time (b) a dark mode (c) rate the driver (d) change the bus icon
- 28.🗒️ A to-do app with no “add a task” feature is ___. (a) ready to release (b) missing a must-have (c) well planned (d) a nice extra
- 29.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) savings stickers (b) export to a file (c) show the balance (d) pie-chart colours
- 30.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money spent (b) add money received (c) show the balance (d) pie-chart colours
- 31.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) background music (b) show a question (c) check the answer (d) show the score
- 32.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) log a glass of water (b) see today’s total (c) share your streak (d) set a reminder time
- 33.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) confetti effects (b) show the score (c) check the answer (d) show a question
- 34.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) show a question (b) an avatar shop (c) confetti effects (d) background music
- 35.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) an avatar shop (b) check the answer (c) show a question (d) show the score
- 36.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) savings stickers (b) show the balance (c) add money received (d) add money spent
- 37.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) add a homework task (b) set a due date (c) see tasks by day (d) earn stickers
- 38.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) pick a theme colour (b) add a homework task (c) set a due date (d) see tasks by day
-
39.🗒️ Version 1 of a pocket-money tracker must be ready in 11 days. How many days are left for extras after the must-haves?
add money received: 1 days
add money spent: 1 days
show the balance: 4 days - 40.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) share your streak (b) water animations (c) log a glass of water (d) custom alert sounds
Answer key
- one the app cannot skip
- 0
- 1
- 5
- 3
- minimum
- set a reminder time
- after the must-haves
- to learn from users soon
- 5
- share tasks to friends
- 2
- MVP
- check the answer
- water animations
- 4
- 3
- 5
- 5
- show the score
- add money spent
- see tasks by day
- pick your bus stop
- 5
- 3
- add money received
- show arrival time
- missing a must-have
- show the balance
- pie-chart colours
- background music
- share your streak
- confetti effects
- show a question
- an avatar shop
- savings stickers
- earn stickers
- pick a theme colour
- 5
- log a glass of water
Free app development lessons, practice and worksheets at talentjr.in/app-development-for-students