App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
- 1.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) earn stickers (b) share tasks to friends (c) set a due date (d) pick a theme colour
- 2.🗒️ What is a must-have feature? (a) one the app cannot skip (b) a sound effect (c) a nice extra (d) a colour theme
- 3.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money spent (b) pie-chart colours (c) show the balance (d) add money received
- 4.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) share your streak (b) custom alert sounds (c) water animations (d) see today’s total
- 5.🗒️ The first small, working version of an app is often called an ___. (a) MVP (b) FAQ (c) CPU (d) URL
- 6.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show the score (b) an avatar shop (c) check the answer (d) show a question
- 7.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show a question (b) check the answer (c) show the score (d) background music
-
8.🗒️ Version 1 of a bus tracker must be ready in 14 days. How many days are left for extras after the must-haves?
see where the bus is: 4 days
show arrival time: 1 days
pick your bus stop: 4 days - 9.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) savings stickers (b) pie-chart colours (c) add money received (d) export to a file
- 10.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money received (b) show the balance (c) add money spent (d) savings stickers
- 11.🗒️ Why keep version 1 small? (a) to use up storage (b) to look bigger (c) to learn from users soon (d) to confuse users
-
12.🗒️ Version 1 of a homework planner must be ready in 18 days. How many days are left for extras after the must-haves?
add a homework task: 4 days
set a due date: 4 days
see tasks by day: 5 days - 13.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) share tasks to friends (b) add a homework task (c) earn stickers (d) pick a theme colour
- 14.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) rate the driver (b) change the bus icon (c) a dark mode (d) pick your bus stop
- 15.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) show the balance (b) pie-chart colours (c) savings stickers (d) export to a file
- 16.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) a dark mode (b) show arrival time (c) see where the bus is (d) pick your bus stop
-
17.🗒️ Version 1 of a bus tracker must be ready in 16 days. How many days are left for extras after the must-haves?
see where the bus is: 3 days
show arrival time: 4 days
pick your bus stop: 3 days - 18.🗒️ In MVP, the M stands for ___. (a) maximum (b) music (c) mobile (d) minimum
-
19.🗒️ Version 1 of a pocket-money tracker must be ready in 11 days. How many days are left for extras after the must-haves?
add money received: 1 days
add money spent: 3 days
show the balance: 5 days - 20.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) see today’s total (b) log a glass of water (c) set a reminder time (d) water animations
- 21.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) confetti effects (b) an avatar shop (c) show a question (d) background music
- 22.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) water animations (b) set a reminder time (c) custom alert sounds (d) share your streak
- 23.🗒️ A to-do app with no “add a task” feature is ___. (a) a nice extra (b) missing a must-have (c) ready to release (d) well planned
- 24.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) check the answer (b) confetti effects (c) show a question (d) show the score
-
25.🗒️ Version 1 of a quiz app must be ready in 12 days. How many days are left for extras after the must-haves?
show a question: 2 days
check the answer: 4 days
show the score: 5 days - 26.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) add a homework task (b) set a due date (c) see tasks by day (d) earn stickers
-
27.🗒️ Version 1 of a homework planner must be ready in 10 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 2 days
see tasks by day: 2 days -
28.🗒️ Version 1 of a pocket-money tracker must be ready in 8 days. How many days are left for extras after the must-haves?
add money received: 3 days
add money spent: 2 days
show the balance: 2 days -
29.🗒️ Version 1 of a bus tracker must be ready in 9 days. How many days are left for extras after the must-haves?
see where the bus is: 1 days
show arrival time: 1 days
pick your bus stop: 2 days -
30.🗒️ Version 1 of a homework planner must be ready in 15 days. How many days are left for extras after the must-haves?
add a homework task: 4 days
set a due date: 2 days
see tasks by day: 5 days - 31.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) see tasks by day (b) add a homework task (c) set a due date (d) share tasks to friends
- 32.🗒️ When should nice-to-have features be built? (a) on day one (b) after the must-haves (c) before anything (d) never
- 33.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) share your streak (b) water animations (c) log a glass of water (d) custom alert sounds
-
34.🗒️ Version 1 of a quiz app must be ready in 13 days. How many days are left for extras after the must-haves?
show a question: 2 days
check the answer: 4 days
show the score: 2 days -
35.🗒️ Version 1 of a bus tracker must be ready in 12 days. How many days are left for extras after the must-haves?
see where the bus is: 3 days
show arrival time: 3 days
pick your bus stop: 4 days -
36.🗒️ Version 1 of a homework planner must be ready in 5 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 1 days
see tasks by day: 2 days - 37.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) change the bus icon (b) pick your bus stop (c) see where the bus is (d) show arrival time
-
38.🗒️ Version 1 of a homework planner must be ready in 7 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 2 days
see tasks by day: 2 days -
39.🗒️ Version 1 of a homework planner must be ready in 10 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 1 days
see tasks by day: 2 days - 40.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) show arrival time (b) rate the driver (c) pick your bus stop (d) see where the bus is
Answer key
- set a due date
- one the app cannot skip
- pie-chart colours
- see today’s total
- MVP
- an avatar shop
- background music
- 5
- add money received
- savings stickers
- to learn from users soon
- 5
- add a homework task
- pick your bus stop
- show the balance
- a dark mode
- 6
- minimum
- 2
- water animations
- show a question
- set a reminder time
- missing a must-have
- confetti effects
- 1
- earn stickers
- 4
- 1
- 5
- 4
- share tasks to friends
- after the must-haves
- log a glass of water
- 5
- 2
- 1
- change the bus icon
- 1
- 6
- rate the driver
Free app development lessons, practice and worksheets at talentjr.in/app-development-for-students