App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
- 1.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) share your streak (b) water animations (c) set a reminder time (d) custom alert sounds
-
2.🗒️ Version 1 of a pocket-money tracker must be ready in 11 days. How many days are left for extras after the must-haves?
add money received: 1 days
add money spent: 3 days
show the balance: 3 days - 3.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) share tasks to friends (b) earn stickers (c) see tasks by day (d) pick a theme colour
- 4.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) show arrival time (b) see where the bus is (c) change the bus icon (d) pick your bus stop
-
5.🗒️ Version 1 of a pocket-money tracker must be ready in 15 days. How many days are left for extras after the must-haves?
add money received: 2 days
add money spent: 4 days
show the balance: 4 days - 6.🗒️ In MVP, the M stands for ___. (a) mobile (b) maximum (c) music (d) minimum
- 7.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) rate the driver (b) a dark mode (c) pick your bus stop (d) change the bus icon
- 8.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) export to a file (b) add money received (c) show the balance (d) add money spent
- 9.🗒️ When should nice-to-have features be built? (a) before anything (b) on day one (c) never (d) after the must-haves
- 10.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) rate the driver (b) a dark mode (c) see where the bus is (d) change the bus icon
- 11.🗒️ The first small, working version of an app is often called an ___. (a) FAQ (b) MVP (c) URL (d) CPU
-
12.🗒️ Version 1 of a homework planner must be ready in 16 days. How many days are left for extras after the must-haves?
add a homework task: 4 days
set a due date: 4 days
see tasks by day: 5 days - 13.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) export to a file (b) add money received (c) pie-chart colours (d) savings stickers
- 14.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) show the score (b) an avatar shop (c) background music (d) confetti effects
-
15.🗒️ Version 1 of a homework planner must be ready in 14 days. How many days are left for extras after the must-haves?
add a homework task: 4 days
set a due date: 1 days
see tasks by day: 3 days - 16.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money spent (b) savings stickers (c) show the balance (d) add money received
-
17.🗒️ Version 1 of a pocket-money tracker must be ready in 12 days. How many days are left for extras after the must-haves?
add money received: 1 days
add money spent: 3 days
show the balance: 2 days -
18.🗒️ Version 1 of a bus tracker must be ready in 17 days. How many days are left for extras after the must-haves?
see where the bus is: 4 days
show arrival time: 4 days
pick your bus stop: 4 days - 19.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) share tasks to friends (b) add a homework task (c) set a due date (d) see tasks by day
- 20.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money spent (b) add money received (c) show the balance (d) pie-chart colours
- 21.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) show arrival time (b) pick your bus stop (c) rate the driver (d) see where the bus is
- 22.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) see where the bus is (b) show arrival time (c) a dark mode (d) pick your bus stop
- 23.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) set a due date (b) earn stickers (c) pick a theme colour (d) share tasks to friends
- 24.🗒️ What is a must-have feature? (a) a colour theme (b) a sound effect (c) one the app cannot skip (d) a nice extra
-
25.🗒️ Version 1 of a water reminder must be ready in 15 days. How many days are left for extras after the must-haves?
set a reminder time: 3 days
log a glass of water: 3 days
see today’s total: 5 days -
26.🗒️ Version 1 of a water reminder must be ready in 8 days. How many days are left for extras after the must-haves?
set a reminder time: 2 days
log a glass of water: 2 days
see today’s total: 4 days -
27.🗒️ Version 1 of a homework planner must be ready in 14 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 3 days
see tasks by day: 3 days -
28.🗒️ Version 1 of a homework planner must be ready in 12 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 3 days
see tasks by day: 5 days - 29.🗒️ A to-do app with no “add a task” feature is ___. (a) well planned (b) a nice extra (c) ready to release (d) missing a must-have
- 30.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show a question (b) check the answer (c) show the score (d) background music
-
31.🗒️ Version 1 of a quiz app must be ready in 15 days. How many days are left for extras after the must-haves?
show a question: 3 days
check the answer: 4 days
show the score: 2 days - 32.🗒️ Why keep version 1 small? (a) to look bigger (b) to use up storage (c) to learn from users soon (d) to confuse users
-
33.🗒️ Version 1 of a pocket-money tracker must be ready in 15 days. How many days are left for extras after the must-haves?
add money received: 4 days
add money spent: 3 days
show the balance: 3 days - 34.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) custom alert sounds (b) set a reminder time (c) log a glass of water (d) see today’s total
- 35.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) export to a file (b) show the balance (c) savings stickers (d) pie-chart colours
-
36.🗒️ Version 1 of a bus tracker must be ready in 15 days. How many days are left for extras after the must-haves?
see where the bus is: 1 days
show arrival time: 3 days
pick your bus stop: 5 days - 37.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) confetti effects (b) an avatar shop (c) background music (d) check the answer
- 38.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) share your streak (b) custom alert sounds (c) see today’s total (d) water animations
-
39.🗒️ Version 1 of a water reminder must be ready in 13 days. How many days are left for extras after the must-haves?
set a reminder time: 3 days
log a glass of water: 2 days
see today’s total: 3 days -
40.🗒️ Version 1 of a pocket-money tracker must be ready in 8 days. How many days are left for extras after the must-haves?
add money received: 1 days
add money spent: 3 days
show the balance: 3 days
Answer key
- set a reminder time
- 4
- see tasks by day
- change the bus icon
- 5
- minimum
- pick your bus stop
- export to a file
- after the must-haves
- see where the bus is
- MVP
- 3
- add money received
- show the score
- 6
- savings stickers
- 6
- 5
- share tasks to friends
- pie-chart colours
- rate the driver
- a dark mode
- set a due date
- one the app cannot skip
- 4
- 0
- 5
- 2
- missing a must-have
- background music
- 6
- to learn from users soon
- 5
- custom alert sounds
- show the balance
- 6
- check the answer
- see today’s total
- 5
- 1