App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
- 1.🗒️ When should nice-to-have features be built? (a) never (b) before anything (c) after the must-haves (d) on day one
- 2.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) export to a file (b) pie-chart colours (c) savings stickers (d) add money spent
- 3.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) confetti effects (b) show a question (c) an avatar shop (d) background music
- 4.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) set a due date (b) add a homework task (c) see tasks by day (d) pick a theme colour
- 5.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) rate the driver (b) a dark mode (c) pick your bus stop (d) change the bus icon
-
6.🗒️ Version 1 of a quiz app must be ready in 13 days. How many days are left for extras after the must-haves?
show a question: 2 days
check the answer: 3 days
show the score: 4 days - 7.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) a dark mode (b) change the bus icon (c) see where the bus is (d) rate the driver
- 8.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) pie-chart colours (b) savings stickers (c) export to a file (d) add money received
-
9.🗒️ Version 1 of a bus tracker must be ready in 7 days. How many days are left for extras after the must-haves?
see where the bus is: 2 days
show arrival time: 1 days
pick your bus stop: 3 days -
10.🗒️ Version 1 of a pocket-money tracker must be ready in 7 days. How many days are left for extras after the must-haves?
add money received: 2 days
add money spent: 1 days
show the balance: 3 days - 11.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) pie-chart colours (b) export to a file (c) savings stickers (d) show the balance
- 12.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) custom alert sounds (b) share your streak (c) water animations (d) see today’s total
- 13.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) pick a theme colour (b) add a homework task (c) earn stickers (d) share tasks to friends
-
14.🗒️ Version 1 of a quiz app must be ready in 10 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 2 days
show the score: 5 days - 15.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) show arrival time (b) change the bus icon (c) pick your bus stop (d) see where the bus is
-
16.🗒️ Version 1 of a water reminder must be ready in 11 days. How many days are left for extras after the must-haves?
set a reminder time: 1 days
log a glass of water: 3 days
see today’s total: 2 days - 17.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) see where the bus is (b) a dark mode (c) show arrival time (d) pick your bus stop
- 18.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) background music (b) show the score (c) show a question (d) check the answer
-
19.🗒️ Version 1 of a water reminder must be ready in 9 days. How many days are left for extras after the must-haves?
set a reminder time: 3 days
log a glass of water: 3 days
see today’s total: 3 days - 20.🗒️ Why keep version 1 small? (a) to use up storage (b) to learn from users soon (c) to confuse users (d) to look bigger
- 21.🗒️ A to-do app with no “add a task” feature is ___. (a) well planned (b) a nice extra (c) missing a must-have (d) ready to release
- 22.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) check the answer (b) show the score (c) show a question (d) confetti effects
- 23.🗒️ The first small, working version of an app is often called an ___. (a) URL (b) MVP (c) FAQ (d) CPU
- 24.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) set a due date (b) share tasks to friends (c) add a homework task (d) see tasks by day
-
25.🗒️ Version 1 of a homework planner must be ready in 8 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 2 days
see tasks by day: 3 days -
26.🗒️ Version 1 of a water reminder must be ready in 12 days. How many days are left for extras after the must-haves?
set a reminder time: 1 days
log a glass of water: 1 days
see today’s total: 5 days - 27.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) pie-chart colours (b) add money received (c) add money spent (d) show the balance
- 28.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) water animations (b) share your streak (c) custom alert sounds (d) log a glass of water
-
29.🗒️ Version 1 of a water reminder must be ready in 12 days. How many days are left for extras after the must-haves?
set a reminder time: 1 days
log a glass of water: 2 days
see today’s total: 5 days -
30.🗒️ Version 1 of a pocket-money tracker must be ready in 14 days. How many days are left for extras after the must-haves?
add money received: 2 days
add money spent: 4 days
show the balance: 5 days - 31.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money spent (b) add money received (c) show the balance (d) savings stickers
-
32.🗒️ Version 1 of a homework planner must be ready in 15 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 4 days
see tasks by day: 3 days - 33.🗒️ What is a must-have feature? (a) a colour theme (b) a nice extra (c) a sound effect (d) one the app cannot skip
- 34.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) background music (b) check the answer (c) an avatar shop (d) confetti effects
-
35.🗒️ Version 1 of a bus tracker must be ready in 6 days. How many days are left for extras after the must-haves?
see where the bus is: 1 days
show arrival time: 1 days
pick your bus stop: 4 days -
36.🗒️ Version 1 of a homework planner must be ready in 5 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 1 days
see tasks by day: 2 days -
37.🗒️ Version 1 of a quiz app must be ready in 11 days. How many days are left for extras after the must-haves?
show a question: 2 days
check the answer: 1 days
show the score: 4 days -
38.🗒️ Version 1 of a pocket-money tracker must be ready in 12 days. How many days are left for extras after the must-haves?
add money received: 3 days
add money spent: 3 days
show the balance: 3 days -
39.🗒️ Version 1 of a homework planner must be ready in 4 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 1 days
see tasks by day: 2 days - 40.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) log a glass of water (b) water animations (c) see today’s total (d) set a reminder time
Answer key
- after the must-haves
- add money spent
- show a question
- pick a theme colour
- pick your bus stop
- 4
- see where the bus is
- add money received
- 1
- 1
- show the balance
- see today’s total
- add a homework task
- 2
- change the bus icon
- 5
- a dark mode
- background music
- 0
- to learn from users soon
- missing a must-have
- confetti effects
- MVP
- share tasks to friends
- 2
- 5
- pie-chart colours
- log a glass of water
- 4
- 3
- savings stickers
- 5
- one the app cannot skip
- check the answer
- 0
- 0
- 4
- 3
- 0
- water animations