App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
- 1.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) share tasks to friends (b) pick a theme colour (c) see tasks by day (d) earn stickers
- 2.🗒️ When should nice-to-have features be built? (a) on day one (b) never (c) before anything (d) after the must-haves
- 3.🗒️ Why keep version 1 small? (a) to confuse users (b) to use up storage (c) to look bigger (d) to learn from users soon
-
4.🗒️ Version 1 of a water reminder must be ready in 10 days. How many days are left for extras after the must-haves?
set a reminder time: 3 days
log a glass of water: 3 days
see today’s total: 2 days - 5.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) add a homework task (b) see tasks by day (c) set a due date (d) share tasks to friends
- 6.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) share tasks to friends (b) earn stickers (c) pick a theme colour (d) add a homework task
- 7.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) add a homework task (b) pick a theme colour (c) set a due date (d) see tasks by day
- 8.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) savings stickers (b) add money spent (c) export to a file (d) pie-chart colours
-
9.🗒️ Version 1 of a quiz app must be ready in 14 days. How many days are left for extras after the must-haves?
show a question: 3 days
check the answer: 1 days
show the score: 5 days - 10.🗒️ What is a must-have feature? (a) a sound effect (b) one the app cannot skip (c) a nice extra (d) a colour theme
- 11.🗒️ A to-do app with no “add a task” feature is ___. (a) a nice extra (b) well planned (c) missing a must-have (d) ready to release
- 12.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) confetti effects (b) an avatar shop (c) background music (d) show a question
- 13.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money received (b) show the balance (c) savings stickers (d) add money spent
-
14.🗒️ Version 1 of a bus tracker must be ready in 4 days. How many days are left for extras after the must-haves?
see where the bus is: 1 days
show arrival time: 1 days
pick your bus stop: 2 days - 15.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) water animations (b) custom alert sounds (c) set a reminder time (d) share your streak
- 16.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) change the bus icon (b) rate the driver (c) a dark mode (d) show arrival time
-
17.🗒️ Version 1 of a pocket-money tracker must be ready in 10 days. How many days are left for extras after the must-haves?
add money received: 3 days
add money spent: 4 days
show the balance: 2 days - 18.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) pick your bus stop (b) show arrival time (c) see where the bus is (d) a dark mode
- 19.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) water animations (b) share your streak (c) log a glass of water (d) custom alert sounds
-
20.🗒️ Version 1 of a pocket-money tracker must be ready in 10 days. How many days are left for extras after the must-haves?
add money received: 4 days
add money spent: 3 days
show the balance: 2 days - 21.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) water animations (b) see today’s total (c) custom alert sounds (d) share your streak
-
22.🗒️ Version 1 of a pocket-money tracker must be ready in 14 days. How many days are left for extras after the must-haves?
add money received: 1 days
add money spent: 4 days
show the balance: 5 days - 23.🗒️ The first small, working version of an app is often called an ___. (a) URL (b) FAQ (c) CPU (d) MVP
- 24.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) pie-chart colours (b) export to a file (c) add money received (d) savings stickers
- 25.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) background music (b) an avatar shop (c) show the score (d) confetti effects
- 26.🗒️ In MVP, the M stands for ___. (a) maximum (b) mobile (c) music (d) minimum
- 27.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) change the bus icon (b) pick your bus stop (c) see where the bus is (d) show arrival time
- 28.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) see tasks by day (b) earn stickers (c) set a due date (d) add a homework task
- 29.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) show the balance (b) add money received (c) add money spent (d) pie-chart colours
- 30.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) show the balance (b) pie-chart colours (c) export to a file (d) savings stickers
- 31.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) see today’s total (b) share your streak (c) set a reminder time (d) log a glass of water
- 32.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) change the bus icon (b) a dark mode (c) rate the driver (d) pick your bus stop
-
33.🗒️ Version 1 of a pocket-money tracker must be ready in 7 days. How many days are left for extras after the must-haves?
add money received: 4 days
add money spent: 1 days
show the balance: 2 days -
34.🗒️ Version 1 of a pocket-money tracker must be ready in 11 days. How many days are left for extras after the must-haves?
add money received: 1 days
add money spent: 2 days
show the balance: 2 days -
35.🗒️ Version 1 of a homework planner must be ready in 6 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 1 days
see tasks by day: 2 days -
36.🗒️ Version 1 of a pocket-money tracker must be ready in 14 days. How many days are left for extras after the must-haves?
add money received: 2 days
add money spent: 2 days
show the balance: 5 days -
37.🗒️ Version 1 of a quiz app must be ready in 9 days. How many days are left for extras after the must-haves?
show a question: 4 days
check the answer: 1 days
show the score: 3 days - 38.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) share tasks to friends (b) set a due date (c) pick a theme colour (d) earn stickers
-
39.🗒️ Version 1 of a pocket-money tracker must be ready in 14 days. How many days are left for extras after the must-haves?
add money received: 3 days
add money spent: 4 days
show the balance: 2 days - 40.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show the score (b) confetti effects (c) check the answer (d) show a question
Answer key
- see tasks by day
- after the must-haves
- to learn from users soon
- 2
- share tasks to friends
- add a homework task
- pick a theme colour
- add money spent
- 5
- one the app cannot skip
- missing a must-have
- show a question
- savings stickers
- 0
- set a reminder time
- show arrival time
- 1
- a dark mode
- log a glass of water
- 1
- see today’s total
- 4
- MVP
- add money received
- show the score
- minimum
- change the bus icon
- earn stickers
- pie-chart colours
- show the balance
- share your streak
- pick your bus stop
- 0
- 6
- 1
- 5
- 1
- set a due date
- 5
- confetti effects
Free app development lessons, practice and worksheets at talentjr.in/app-development-for-students