App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
- 1.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) see tasks by day (b) set a due date (c) pick a theme colour (d) add a homework task
- 2.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) earn stickers (b) share tasks to friends (c) pick a theme colour (d) add a homework task
-
3.🗒️ Version 1 of a water reminder must be ready in 10 days. How many days are left for extras after the must-haves?
set a reminder time: 1 days
log a glass of water: 1 days
see today’s total: 5 days - 4.🗒️ In MVP, the M stands for ___. (a) mobile (b) maximum (c) minimum (d) music
- 5.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) confetti effects (b) show a question (c) check the answer (d) show the score
- 6.🗒️ What is a must-have feature? (a) a nice extra (b) a colour theme (c) one the app cannot skip (d) a sound effect
-
7.🗒️ Version 1 of a water reminder must be ready in 13 days. How many days are left for extras after the must-haves?
set a reminder time: 2 days
log a glass of water: 2 days
see today’s total: 4 days - 8.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) set a reminder time (b) log a glass of water (c) see today’s total (d) custom alert sounds
- 9.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) rate the driver (b) see where the bus is (c) pick your bus stop (d) show arrival time
-
10.🗒️ Version 1 of a quiz app must be ready in 13 days. How many days are left for extras after the must-haves?
show a question: 2 days
check the answer: 3 days
show the score: 5 days - 11.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) set a reminder time (b) log a glass of water (c) see today’s total (d) water animations
- 12.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) show a question (b) background music (c) an avatar shop (d) confetti effects
-
13.🗒️ Version 1 of a water reminder must be ready in 12 days. How many days are left for extras after the must-haves?
set a reminder time: 1 days
log a glass of water: 4 days
see today’s total: 3 days -
14.🗒️ Version 1 of a homework planner must be ready in 17 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 3 days
see tasks by day: 5 days -
15.🗒️ Version 1 of a water reminder must be ready in 12 days. How many days are left for extras after the must-haves?
set a reminder time: 3 days
log a glass of water: 3 days
see today’s total: 4 days -
16.🗒️ Version 1 of a homework planner must be ready in 15 days. How many days are left for extras after the must-haves?
add a homework task: 4 days
set a due date: 3 days
see tasks by day: 5 days - 17.🗒️ Why keep version 1 small? (a) to look bigger (b) to confuse users (c) to learn from users soon (d) to use up storage
-
18.🗒️ Version 1 of a bus tracker must be ready in 18 days. How many days are left for extras after the must-haves?
see where the bus is: 4 days
show arrival time: 3 days
pick your bus stop: 5 days -
19.🗒️ Version 1 of a pocket-money tracker must be ready in 12 days. How many days are left for extras after the must-haves?
add money received: 3 days
add money spent: 4 days
show the balance: 2 days -
20.🗒️ Version 1 of a bus tracker must be ready in 13 days. How many days are left for extras after the must-haves?
see where the bus is: 4 days
show arrival time: 4 days
pick your bus stop: 4 days - 21.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) show the balance (b) add money spent (c) export to a file (d) add money received
- 22.🗒️ When should nice-to-have features be built? (a) never (b) on day one (c) after the must-haves (d) before anything
- 23.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) share your streak (b) see today’s total (c) log a glass of water (d) set a reminder time
- 24.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) share your streak (b) log a glass of water (c) water animations (d) custom alert sounds
-
25.🗒️ Version 1 of a homework planner must be ready in 11 days. How many days are left for extras after the must-haves?
add a homework task: 4 days
set a due date: 3 days
see tasks by day: 3 days - 26.🗒️ The first small, working version of an app is often called an ___. (a) CPU (b) MVP (c) URL (d) FAQ
- 27.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) change the bus icon (b) show arrival time (c) pick your bus stop (d) see where the bus is
-
28.🗒️ Version 1 of a water reminder must be ready in 6 days. How many days are left for extras after the must-haves?
set a reminder time: 3 days
log a glass of water: 1 days
see today’s total: 2 days -
29.🗒️ Version 1 of a pocket-money tracker must be ready in 14 days. How many days are left for extras after the must-haves?
add money received: 2 days
add money spent: 2 days
show the balance: 5 days - 30.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) earn stickers (b) share tasks to friends (c) see tasks by day (d) pick a theme colour
- 31.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) pie-chart colours (b) add money spent (c) export to a file (d) savings stickers
- 32.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) background music (b) show the score (c) show a question (d) check the answer
- 33.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) pick a theme colour (b) share tasks to friends (c) set a due date (d) earn stickers
-
34.🗒️ Version 1 of a quiz app must be ready in 8 days. How many days are left for extras after the must-haves?
show a question: 3 days
check the answer: 1 days
show the score: 4 days - 35.🗒️ A to-do app with no “add a task” feature is ___. (a) ready to release (b) a nice extra (c) well planned (d) missing a must-have
-
36.🗒️ Version 1 of a bus tracker must be ready in 10 days. How many days are left for extras after the must-haves?
see where the bus is: 1 days
show arrival time: 1 days
pick your bus stop: 4 days - 37.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) export to a file (b) pie-chart colours (c) show the balance (d) savings stickers
- 38.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) pie-chart colours (b) add money received (c) add money spent (d) show the balance
- 39.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) share your streak (b) custom alert sounds (c) see today’s total (d) water animations
-
40.🗒️ Version 1 of a quiz app must be ready in 5 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 2 days
show the score: 2 days
Answer key
- pick a theme colour
- add a homework task
- 3
- minimum
- confetti effects
- one the app cannot skip
- 5
- custom alert sounds
- rate the driver
- 3
- water animations
- show a question
- 4
- 6
- 2
- 3
- to learn from users soon
- 6
- 3
- 1
- export to a file
- after the must-haves
- share your streak
- log a glass of water
- 1
- MVP
- change the bus icon
- 0
- 5
- see tasks by day
- add money spent
- background music
- set a due date
- 0
- missing a must-have
- 4
- show the balance
- pie-chart colours
- see today’s total
- 0
Free app development lessons, practice and worksheets at talentjr.in/app-development-for-students