App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
-
1.🗒️ Version 1 of a quiz app must be ready in 10 days. How many days are left for extras after the must-haves?
show a question: 3 days
check the answer: 1 days
show the score: 4 days - 2.🗒️ Why keep version 1 small? (a) to look bigger (b) to confuse users (c) to use up storage (d) to learn from users soon
-
3.🗒️ Version 1 of a quiz app must be ready in 7 days. How many days are left for extras after the must-haves?
show a question: 2 days
check the answer: 2 days
show the score: 2 days - 4.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) see today’s total (b) set a reminder time (c) log a glass of water (d) water animations
- 5.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money received (b) add money spent (c) pie-chart colours (d) show the balance
- 6.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) show arrival time (b) a dark mode (c) pick your bus stop (d) see where the bus is
-
7.🗒️ Version 1 of a bus tracker must be ready in 9 days. How many days are left for extras after the must-haves?
see where the bus is: 4 days
show arrival time: 1 days
pick your bus stop: 3 days - 8.🗒️ What is a must-have feature? (a) a sound effect (b) a colour theme (c) one the app cannot skip (d) a nice extra
-
9.🗒️ Version 1 of a homework planner must be ready in 11 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 1 days
see tasks by day: 4 days - 10.🗒️ In MVP, the M stands for ___. (a) mobile (b) maximum (c) music (d) minimum
- 11.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) background music (b) an avatar shop (c) show the score (d) confetti effects
- 12.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) background music (b) confetti effects (c) an avatar shop (d) show a question
- 13.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) an avatar shop (b) check the answer (c) background music (d) confetti effects
- 14.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) a dark mode (b) show arrival time (c) change the bus icon (d) rate the driver
-
15.🗒️ Version 1 of a homework planner must be ready in 16 days. How many days are left for extras after the must-haves?
add a homework task: 4 days
set a due date: 3 days
see tasks by day: 3 days - 16.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) show arrival time (b) pick your bus stop (c) see where the bus is (d) change the bus icon
-
17.🗒️ Version 1 of a water reminder must be ready in 14 days. How many days are left for extras after the must-haves?
set a reminder time: 2 days
log a glass of water: 4 days
see today’s total: 4 days -
18.🗒️ Version 1 of a quiz app must be ready in 15 days. How many days are left for extras after the must-haves?
show a question: 3 days
check the answer: 3 days
show the score: 5 days - 19.🗒️ When should nice-to-have features be built? (a) after the must-haves (b) never (c) before anything (d) on day one
-
20.🗒️ Version 1 of a quiz app must be ready in 12 days. How many days are left for extras after the must-haves?
show a question: 3 days
check the answer: 1 days
show the score: 3 days -
21.🗒️ Version 1 of a homework planner must be ready in 15 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 4 days
see tasks by day: 3 days - 22.🗒️ A to-do app with no “add a task” feature is ___. (a) well planned (b) ready to release (c) a nice extra (d) missing a must-have
- 23.🗒️ The first small, working version of an app is often called an ___. (a) FAQ (b) CPU (c) URL (d) MVP
- 24.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money received (b) add money spent (c) show the balance (d) savings stickers
-
25.🗒️ Version 1 of a pocket-money tracker must be ready in 11 days. How many days are left for extras after the must-haves?
add money received: 2 days
add money spent: 3 days
show the balance: 2 days -
26.🗒️ Version 1 of a pocket-money tracker must be ready in 10 days. How many days are left for extras after the must-haves?
add money received: 4 days
add money spent: 1 days
show the balance: 3 days - 27.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) pick a theme colour (b) set a due date (c) add a homework task (d) see tasks by day
-
28.🗒️ Version 1 of a water reminder must be ready in 13 days. How many days are left for extras after the must-haves?
set a reminder time: 4 days
log a glass of water: 1 days
see today’s total: 4 days - 29.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) earn stickers (b) add a homework task (c) share tasks to friends (d) pick a theme colour
-
30.🗒️ Version 1 of a water reminder must be ready in 8 days. How many days are left for extras after the must-haves?
set a reminder time: 1 days
log a glass of water: 2 days
see today’s total: 2 days - 31.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) change the bus icon (b) rate the driver (c) pick your bus stop (d) a dark mode
- 32.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) add a homework task (b) share tasks to friends (c) set a due date (d) see tasks by day
-
33.🗒️ Version 1 of a pocket-money tracker must be ready in 12 days. How many days are left for extras after the must-haves?
add money received: 2 days
add money spent: 1 days
show the balance: 3 days - 34.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) earn stickers (b) see tasks by day (c) set a due date (d) add a homework task
- 35.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) pie-chart colours (b) export to a file (c) add money received (d) savings stickers
-
36.🗒️ Version 1 of a water reminder must be ready in 11 days. How many days are left for extras after the must-haves?
set a reminder time: 4 days
log a glass of water: 4 days
see today’s total: 3 days - 37.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) log a glass of water (b) water animations (c) share your streak (d) custom alert sounds
- 38.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) check the answer (b) show the score (c) confetti effects (d) show a question
-
39.🗒️ Version 1 of a quiz app must be ready in 17 days. How many days are left for extras after the must-haves?
show a question: 4 days
check the answer: 2 days
show the score: 5 days -
40.🗒️ Version 1 of a bus tracker must be ready in 17 days. How many days are left for extras after the must-haves?
see where the bus is: 3 days
show arrival time: 3 days
pick your bus stop: 5 days
Answer key
- 2
- to learn from users soon
- 1
- water animations
- pie-chart colours
- a dark mode
- 1
- one the app cannot skip
- 4
- minimum
- show the score
- show a question
- check the answer
- show arrival time
- 6
- change the bus icon
- 4
- 4
- after the must-haves
- 5
- 5
- missing a must-have
- MVP
- savings stickers
- 4
- 2
- pick a theme colour
- 4
- add a homework task
- 3
- pick your bus stop
- share tasks to friends
- 6
- earn stickers
- add money received
- 0
- log a glass of water
- confetti effects
- 6
- 6
Free app development lessons, practice and worksheets at talentjr.in/app-development-for-students