App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
-
1.🗒️ Version 1 of a pocket-money tracker must be ready in 10 days. How many days are left for extras after the must-haves?
add money received: 2 days
add money spent: 4 days
show the balance: 4 days - 2.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) change the bus icon (b) a dark mode (c) rate the driver (d) see where the bus is
- 3.🗒️ What is a must-have feature? (a) one the app cannot skip (b) a nice extra (c) a sound effect (d) a colour theme
- 4.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) rate the driver (b) pick your bus stop (c) see where the bus is (d) show arrival time
- 5.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) pick your bus stop (b) show arrival time (c) see where the bus is (d) a dark mode
- 6.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) confetti effects (b) background music (c) show a question (d) an avatar shop
- 7.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) savings stickers (b) pie-chart colours (c) export to a file (d) add money spent
-
8.🗒️ Version 1 of a quiz app must be ready in 8 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 2 days
show the score: 2 days -
9.🗒️ Version 1 of a pocket-money tracker must be ready in 15 days. How many days are left for extras after the must-haves?
add money received: 3 days
add money spent: 4 days
show the balance: 2 days -
10.🗒️ Version 1 of a pocket-money tracker must be ready in 8 days. How many days are left for extras after the must-haves?
add money received: 2 days
add money spent: 1 days
show the balance: 4 days - 11.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show a question (b) show the score (c) check the answer (d) background music
- 12.🗒️ In MVP, the M stands for ___. (a) mobile (b) maximum (c) music (d) minimum
-
13.🗒️ Version 1 of a pocket-money tracker must be ready in 9 days. How many days are left for extras after the must-haves?
add money received: 3 days
add money spent: 1 days
show the balance: 3 days - 14.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show a question (b) check the answer (c) show the score (d) confetti effects
- 15.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) show arrival time (b) a dark mode (c) rate the driver (d) change the bus icon
- 16.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) share your streak (b) water animations (c) log a glass of water (d) custom alert sounds
- 17.🗒️ The first small, working version of an app is often called an ___. (a) URL (b) CPU (c) MVP (d) FAQ
-
18.🗒️ Version 1 of a pocket-money tracker must be ready in 15 days. How many days are left for extras after the must-haves?
add money received: 4 days
add money spent: 1 days
show the balance: 4 days - 19.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) see tasks by day (b) pick a theme colour (c) earn stickers (d) share tasks to friends
- 20.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) see today’s total (b) share your streak (c) custom alert sounds (d) water animations
- 21.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) water animations (b) share your streak (c) custom alert sounds (d) set a reminder time
-
22.🗒️ Version 1 of a water reminder must be ready in 9 days. How many days are left for extras after the must-haves?
set a reminder time: 3 days
log a glass of water: 3 days
see today’s total: 3 days - 23.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) log a glass of water (b) water animations (c) see today’s total (d) set a reminder time
- 24.🗒️ A to-do app with no “add a task” feature is ___. (a) a nice extra (b) well planned (c) missing a must-have (d) ready to release
- 25.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) change the bus icon (b) rate the driver (c) pick your bus stop (d) a dark mode
-
26.🗒️ Version 1 of a bus tracker must be ready in 9 days. How many days are left for extras after the must-haves?
see where the bus is: 3 days
show arrival time: 2 days
pick your bus stop: 4 days - 27.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) share your streak (b) see today’s total (c) set a reminder time (d) log a glass of water
- 28.🗒️ When should nice-to-have features be built? (a) on day one (b) before anything (c) never (d) after the must-haves
-
29.🗒️ Version 1 of a bus tracker must be ready in 11 days. How many days are left for extras after the must-haves?
see where the bus is: 4 days
show arrival time: 2 days
pick your bus stop: 3 days -
30.🗒️ Version 1 of a homework planner must be ready in 8 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 2 days
see tasks by day: 4 days - 31.🗒️ Why keep version 1 small? (a) to look bigger (b) to confuse users (c) to use up storage (d) to learn from users soon
-
32.🗒️ Version 1 of a water reminder must be ready in 9 days. How many days are left for extras after the must-haves?
set a reminder time: 2 days
log a glass of water: 2 days
see today’s total: 2 days - 33.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) see tasks by day (b) set a due date (c) add a homework task (d) share tasks to friends
-
34.🗒️ Version 1 of a homework planner must be ready in 8 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 1 days
see tasks by day: 3 days - 35.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) savings stickers (b) pie-chart colours (c) export to a file (d) show the balance
- 36.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money spent (b) add money received (c) show the balance (d) pie-chart colours
- 37.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) show the balance (b) add money spent (c) add money received (d) savings stickers
- 38.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) background music (b) show the score (c) confetti effects (d) an avatar shop
-
39.🗒️ Version 1 of a quiz app must be ready in 9 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 1 days
show the score: 3 days - 40.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) set a due date (b) pick a theme colour (c) add a homework task (d) see tasks by day
Answer key
- 0
- see where the bus is
- one the app cannot skip
- rate the driver
- a dark mode
- show a question
- add money spent
- 3
- 6
- 1
- background music
- minimum
- 2
- confetti effects
- show arrival time
- log a glass of water
- MVP
- 6
- see tasks by day
- see today’s total
- set a reminder time
- 0
- water animations
- missing a must-have
- pick your bus stop
- 0
- share your streak
- after the must-haves
- 2
- 0
- to learn from users soon
- 3
- share tasks to friends
- 1
- show the balance
- pie-chart colours
- savings stickers
- show the score
- 4
- pick a theme colour