App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
-
1.🗒️ Version 1 of a water reminder must be ready in 12 days. How many days are left for extras after the must-haves?
set a reminder time: 4 days
log a glass of water: 1 days
see today’s total: 4 days - 2.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) pick a theme colour (b) earn stickers (c) set a due date (d) share tasks to friends
- 3.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) pick a theme colour (b) see tasks by day (c) add a homework task (d) set a due date
- 4.🗒️ In MVP, the M stands for ___. (a) maximum (b) music (c) mobile (d) minimum
-
5.🗒️ Version 1 of a water reminder must be ready in 8 days. How many days are left for extras after the must-haves?
set a reminder time: 3 days
log a glass of water: 1 days
see today’s total: 2 days -
6.🗒️ Version 1 of a water reminder must be ready in 15 days. How many days are left for extras after the must-haves?
set a reminder time: 3 days
log a glass of water: 1 days
see today’s total: 5 days - 7.🗒️ The first small, working version of an app is often called an ___. (a) URL (b) CPU (c) MVP (d) FAQ
- 8.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) background music (b) an avatar shop (c) confetti effects (d) show a question
- 9.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) an avatar shop (b) confetti effects (c) background music (d) check the answer
- 10.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) see where the bus is (b) change the bus icon (c) rate the driver (d) a dark mode
-
11.🗒️ Version 1 of a pocket-money tracker must be ready in 12 days. How many days are left for extras after the must-haves?
add money received: 3 days
add money spent: 3 days
show the balance: 3 days - 12.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) share tasks to friends (b) add a homework task (c) pick a theme colour (d) earn stickers
- 13.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) an avatar shop (b) show the score (c) confetti effects (d) background music
- 14.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) water animations (b) see today’s total (c) share your streak (d) custom alert sounds
- 15.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) see where the bus is (b) pick your bus stop (c) a dark mode (d) show arrival time
-
16.🗒️ Version 1 of a quiz app must be ready in 8 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 2 days
show the score: 3 days - 17.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) water animations (b) log a glass of water (c) see today’s total (d) set a reminder time
- 18.🗒️ When should nice-to-have features be built? (a) on day one (b) never (c) after the must-haves (d) before anything
- 19.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) change the bus icon (b) pick your bus stop (c) show arrival time (d) see where the bus is
- 20.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show a question (b) show the score (c) confetti effects (d) check the answer
-
21.🗒️ Version 1 of a bus tracker must be ready in 7 days. How many days are left for extras after the must-haves?
see where the bus is: 2 days
show arrival time: 1 days
pick your bus stop: 4 days - 22.🗒️ What is a must-have feature? (a) one the app cannot skip (b) a sound effect (c) a colour theme (d) a nice extra
-
23.🗒️ Version 1 of a homework planner must be ready in 10 days. How many days are left for extras after the must-haves?
add a homework task: 4 days
set a due date: 2 days
see tasks by day: 4 days - 24.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) custom alert sounds (b) log a glass of water (c) share your streak (d) water animations
- 25.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) show the balance (b) add money spent (c) pie-chart colours (d) add money received
- 26.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) savings stickers (b) add money received (c) export to a file (d) pie-chart colours
-
27.🗒️ Version 1 of a pocket-money tracker must be ready in 5 days. How many days are left for extras after the must-haves?
add money received: 1 days
add money spent: 2 days
show the balance: 2 days -
28.🗒️ Version 1 of a water reminder must be ready in 9 days. How many days are left for extras after the must-haves?
set a reminder time: 2 days
log a glass of water: 4 days
see today’s total: 3 days - 29.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money spent (b) add money received (c) show the balance (d) export to a file
-
30.🗒️ Version 1 of a quiz app must be ready in 13 days. How many days are left for extras after the must-haves?
show a question: 2 days
check the answer: 4 days
show the score: 2 days - 31.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) rate the driver (b) see where the bus is (c) show arrival time (d) pick your bus stop
-
32.🗒️ Version 1 of a homework planner must be ready in 12 days. How many days are left for extras after the must-haves?
add a homework task: 4 days
set a due date: 2 days
see tasks by day: 4 days -
33.🗒️ Version 1 of a homework planner must be ready in 14 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 2 days
see tasks by day: 5 days - 34.🗒️ Why keep version 1 small? (a) to look bigger (b) to learn from users soon (c) to use up storage (d) to confuse users
- 35.🗒️ A to-do app with no “add a task” feature is ___. (a) ready to release (b) missing a must-have (c) well planned (d) a nice extra
-
36.🗒️ Version 1 of a homework planner must be ready in 9 days. How many days are left for extras after the must-haves?
add a homework task: 4 days
set a due date: 1 days
see tasks by day: 4 days -
37.🗒️ Version 1 of a homework planner must be ready in 6 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 2 days
see tasks by day: 2 days -
38.🗒️ Version 1 of a bus tracker must be ready in 6 days. How many days are left for extras after the must-haves?
see where the bus is: 1 days
show arrival time: 1 days
pick your bus stop: 3 days - 39.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show the score (b) check the answer (c) show a question (d) an avatar shop
-
40.🗒️ Version 1 of a water reminder must be ready in 6 days. How many days are left for extras after the must-haves?
set a reminder time: 2 days
log a glass of water: 1 days
see today’s total: 2 days
Answer key
- 3
- set a due date
- pick a theme colour
- minimum
- 2
- 6
- MVP
- show a question
- check the answer
- see where the bus is
- 3
- add a homework task
- show the score
- see today’s total
- a dark mode
- 2
- water animations
- after the must-haves
- change the bus icon
- confetti effects
- 0
- one the app cannot skip
- 0
- log a glass of water
- pie-chart colours
- add money received
- 0
- 0
- export to a file
- 5
- rate the driver
- 2
- 4
- to learn from users soon
- missing a must-have
- 0
- 1
- 1
- an avatar shop
- 1
Free app development lessons, practice and worksheets at talentjr.in/app-development-for-students