App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
-
1.🗒️ Version 1 of a homework planner must be ready in 18 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 4 days
see tasks by day: 5 days -
2.🗒️ Version 1 of a homework planner must be ready in 11 days. How many days are left for extras after the must-haves?
add a homework task: 4 days
set a due date: 2 days
see tasks by day: 5 days - 3.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) savings stickers (b) add money spent (c) show the balance (d) add money received
-
4.🗒️ Version 1 of a bus tracker must be ready in 15 days. How many days are left for extras after the must-haves?
see where the bus is: 4 days
show arrival time: 3 days
pick your bus stop: 2 days -
5.🗒️ Version 1 of a quiz app must be ready in 12 days. How many days are left for extras after the must-haves?
show a question: 4 days
check the answer: 2 days
show the score: 5 days -
6.🗒️ Version 1 of a homework planner must be ready in 14 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 3 days
see tasks by day: 4 days - 7.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) water animations (b) custom alert sounds (c) see today’s total (d) share your streak
- 8.🗒️ What is a must-have feature? (a) a sound effect (b) one the app cannot skip (c) a nice extra (d) a colour theme
- 9.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) rate the driver (b) a dark mode (c) see where the bus is (d) change the bus icon
- 10.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) change the bus icon (b) show arrival time (c) see where the bus is (d) pick your bus stop
-
11.🗒️ Version 1 of a quiz app must be ready in 12 days. How many days are left for extras after the must-haves?
show a question: 3 days
check the answer: 1 days
show the score: 2 days - 12.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) rate the driver (b) see where the bus is (c) show arrival time (d) pick your bus stop
- 13.🗒️ The first small, working version of an app is often called an ___. (a) MVP (b) CPU (c) FAQ (d) URL
- 14.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) see tasks by day (b) add a homework task (c) set a due date (d) pick a theme colour
- 15.🗒️ A to-do app with no “add a task” feature is ___. (a) ready to release (b) a nice extra (c) missing a must-have (d) well planned
-
16.🗒️ Version 1 of a pocket-money tracker must be ready in 14 days. How many days are left for extras after the must-haves?
add money received: 4 days
add money spent: 4 days
show the balance: 4 days -
17.🗒️ Version 1 of a homework planner must be ready in 15 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 4 days
see tasks by day: 4 days -
18.🗒️ Version 1 of a homework planner must be ready in 6 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 1 days
see tasks by day: 2 days - 19.🗒️ Why keep version 1 small? (a) to confuse users (b) to use up storage (c) to look bigger (d) to learn from users soon
-
20.🗒️ Version 1 of a quiz app must be ready in 10 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 1 days
show the score: 2 days -
21.🗒️ Version 1 of a homework planner must be ready in 14 days. How many days are left for extras after the must-haves?
add a homework task: 4 days
set a due date: 3 days
see tasks by day: 5 days -
22.🗒️ Version 1 of a bus tracker must be ready in 15 days. How many days are left for extras after the must-haves?
see where the bus is: 4 days
show arrival time: 4 days
pick your bus stop: 2 days - 23.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) set a reminder time (b) see today’s total (c) custom alert sounds (d) log a glass of water
-
24.🗒️ Version 1 of a pocket-money tracker must be ready in 5 days. How many days are left for extras after the must-haves?
add money received: 2 days
add money spent: 1 days
show the balance: 2 days - 25.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) background music (b) an avatar shop (c) confetti effects (d) show the score
- 26.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) earn stickers (b) pick a theme colour (c) share tasks to friends (d) set a due date
-
27.🗒️ Version 1 of a quiz app must be ready in 12 days. How many days are left for extras after the must-haves?
show a question: 3 days
check the answer: 3 days
show the score: 2 days - 28.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show a question (b) show the score (c) confetti effects (d) check the answer
- 29.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) set a reminder time (b) see today’s total (c) water animations (d) log a glass of water
- 30.🗒️ In MVP, the M stands for ___. (a) maximum (b) music (c) minimum (d) mobile
-
31.🗒️ Version 1 of a water reminder must be ready in 7 days. How many days are left for extras after the must-haves?
set a reminder time: 1 days
log a glass of water: 1 days
see today’s total: 2 days - 32.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) background music (b) show the score (c) show a question (d) check the answer
- 33.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) export to a file (b) pie-chart colours (c) savings stickers (d) show the balance
-
34.🗒️ Version 1 of a bus tracker must be ready in 15 days. How many days are left for extras after the must-haves?
see where the bus is: 3 days
show arrival time: 1 days
pick your bus stop: 5 days - 35.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) share tasks to friends (b) pick a theme colour (c) earn stickers (d) see tasks by day
- 36.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) water animations (b) custom alert sounds (c) share your streak (d) set a reminder time
- 37.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) a dark mode (b) change the bus icon (c) rate the driver (d) pick your bus stop
-
38.🗒️ Version 1 of a bus tracker must be ready in 8 days. How many days are left for extras after the must-haves?
see where the bus is: 2 days
show arrival time: 3 days
pick your bus stop: 2 days -
39.🗒️ Version 1 of a pocket-money tracker must be ready in 9 days. How many days are left for extras after the must-haves?
add money received: 1 days
add money spent: 1 days
show the balance: 2 days - 40.🗒️ When should nice-to-have features be built? (a) before anything (b) never (c) on day one (d) after the must-haves
Answer key
- 6
- 0
- savings stickers
- 6
- 1
- 6
- see today’s total
- one the app cannot skip
- see where the bus is
- change the bus icon
- 6
- rate the driver
- MVP
- pick a theme colour
- missing a must-have
- 2
- 4
- 1
- to learn from users soon
- 6
- 2
- 5
- custom alert sounds
- 0
- show the score
- set a due date
- 4
- confetti effects
- water animations
- minimum
- 3
- background music
- show the balance
- 6
- see tasks by day
- set a reminder time
- pick your bus stop
- 1
- 5
- after the must-haves
Free app development lessons, practice and worksheets at talentjr.in/app-development-for-students