App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
-
1.🗒️ Version 1 of a bus tracker must be ready in 11 days. How many days are left for extras after the must-haves?
see where the bus is: 4 days
show arrival time: 1 days
pick your bus stop: 5 days - 2.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) change the bus icon (b) rate the driver (c) pick your bus stop (d) a dark mode
- 3.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) background music (b) check the answer (c) show a question (d) show the score
- 4.🗒️ When should nice-to-have features be built? (a) on day one (b) never (c) before anything (d) after the must-haves
- 5.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) export to a file (b) show the balance (c) add money spent (d) add money received
- 6.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) an avatar shop (b) show a question (c) background music (d) confetti effects
-
7.🗒️ Version 1 of a pocket-money tracker must be ready in 6 days. How many days are left for extras after the must-haves?
add money received: 3 days
add money spent: 1 days
show the balance: 2 days - 8.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) confetti effects (b) an avatar shop (c) background music (d) check the answer
- 9.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) show the score (b) confetti effects (c) background music (d) an avatar shop
- 10.🗒️ The first small, working version of an app is often called an ___. (a) FAQ (b) MVP (c) CPU (d) URL
- 11.🗒️ Why keep version 1 small? (a) to use up storage (b) to look bigger (c) to confuse users (d) to learn from users soon
-
12.🗒️ Version 1 of a bus tracker must be ready in 10 days. How many days are left for extras after the must-haves?
see where the bus is: 1 days
show arrival time: 3 days
pick your bus stop: 4 days -
13.🗒️ Version 1 of a quiz app must be ready in 6 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 1 days
show the score: 2 days - 14.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) earn stickers (b) add a homework task (c) pick a theme colour (d) share tasks to friends
-
15.🗒️ Version 1 of a quiz app must be ready in 13 days. How many days are left for extras after the must-haves?
show a question: 3 days
check the answer: 4 days
show the score: 5 days -
16.🗒️ Version 1 of a water reminder must be ready in 17 days. How many days are left for extras after the must-haves?
set a reminder time: 4 days
log a glass of water: 2 days
see today’s total: 5 days -
17.🗒️ Version 1 of a water reminder must be ready in 12 days. How many days are left for extras after the must-haves?
set a reminder time: 3 days
log a glass of water: 2 days
see today’s total: 3 days - 18.🗒️ What is a must-have feature? (a) a colour theme (b) one the app cannot skip (c) a nice extra (d) a sound effect
-
19.🗒️ Version 1 of a quiz app must be ready in 11 days. How many days are left for extras after the must-haves?
show a question: 4 days
check the answer: 2 days
show the score: 2 days -
20.🗒️ Version 1 of a bus tracker must be ready in 9 days. How many days are left for extras after the must-haves?
see where the bus is: 3 days
show arrival time: 1 days
pick your bus stop: 5 days - 21.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) share your streak (b) water animations (c) set a reminder time (d) custom alert sounds
-
22.🗒️ Version 1 of a bus tracker must be ready in 9 days. How many days are left for extras after the must-haves?
see where the bus is: 1 days
show arrival time: 3 days
pick your bus stop: 5 days - 23.🗒️ In MVP, the M stands for ___. (a) music (b) mobile (c) minimum (d) maximum
- 24.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) show arrival time (b) rate the driver (c) see where the bus is (d) pick your bus stop
- 25.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show the score (b) check the answer (c) show a question (d) an avatar shop
-
26.🗒️ Version 1 of a water reminder must be ready in 10 days. How many days are left for extras after the must-haves?
set a reminder time: 3 days
log a glass of water: 4 days
see today’s total: 2 days -
27.🗒️ Version 1 of a water reminder must be ready in 8 days. How many days are left for extras after the must-haves?
set a reminder time: 2 days
log a glass of water: 2 days
see today’s total: 4 days -
28.🗒️ Version 1 of a water reminder must be ready in 8 days. How many days are left for extras after the must-haves?
set a reminder time: 1 days
log a glass of water: 2 days
see today’s total: 5 days - 29.🗒️ A to-do app with no “add a task” feature is ___. (a) missing a must-have (b) ready to release (c) a nice extra (d) well planned
- 30.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) show arrival time (b) see where the bus is (c) pick your bus stop (d) a dark mode
- 31.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) earn stickers (b) see tasks by day (c) share tasks to friends (d) pick a theme colour
-
32.🗒️ Version 1 of a homework planner must be ready in 16 days. How many days are left for extras after the must-haves?
add a homework task: 4 days
set a due date: 3 days
see tasks by day: 3 days - 33.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) a dark mode (b) change the bus icon (c) rate the driver (d) see where the bus is
-
34.🗒️ Version 1 of a water reminder must be ready in 10 days. How many days are left for extras after the must-haves?
set a reminder time: 2 days
log a glass of water: 2 days
see today’s total: 3 days -
35.🗒️ Version 1 of a bus tracker must be ready in 10 days. How many days are left for extras after the must-haves?
see where the bus is: 3 days
show arrival time: 2 days
pick your bus stop: 4 days - 36.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) set a reminder time (b) log a glass of water (c) custom alert sounds (d) see today’s total
- 37.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) earn stickers (b) pick a theme colour (c) share tasks to friends (d) set a due date
-
38.🗒️ Version 1 of a quiz app must be ready in 12 days. How many days are left for extras after the must-haves?
show a question: 2 days
check the answer: 2 days
show the score: 4 days -
39.🗒️ Version 1 of a water reminder must be ready in 17 days. How many days are left for extras after the must-haves?
set a reminder time: 4 days
log a glass of water: 4 days
see today’s total: 5 days -
40.🗒️ Version 1 of a bus tracker must be ready in 5 days. How many days are left for extras after the must-haves?
see where the bus is: 1 days
show arrival time: 1 days
pick your bus stop: 3 days
Answer key
- 1
- pick your bus stop
- background music
- after the must-haves
- export to a file
- show a question
- 0
- check the answer
- show the score
- MVP
- to learn from users soon
- 2
- 2
- add a homework task
- 1
- 6
- 4
- one the app cannot skip
- 3
- 0
- set a reminder time
- 0
- minimum
- rate the driver
- an avatar shop
- 1
- 0
- 0
- missing a must-have
- a dark mode
- see tasks by day
- 6
- see where the bus is
- 3
- 1
- custom alert sounds
- set a due date
- 4
- 4
- 0