App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
- 1.🗒️ What is a must-have feature? (a) a colour theme (b) a sound effect (c) a nice extra (d) one the app cannot skip
- 2.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) custom alert sounds (b) set a reminder time (c) water animations (d) share your streak
- 3.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) share tasks to friends (b) add a homework task (c) set a due date (d) see tasks by day
- 4.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) rate the driver (b) pick your bus stop (c) a dark mode (d) change the bus icon
- 5.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) background music (b) confetti effects (c) check the answer (d) an avatar shop
-
6.🗒️ Version 1 of a bus tracker must be ready in 7 days. How many days are left for extras after the must-haves?
see where the bus is: 3 days
show arrival time: 1 days
pick your bus stop: 3 days -
7.🗒️ Version 1 of a homework planner must be ready in 12 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 1 days
see tasks by day: 3 days - 8.🗒️ The first small, working version of an app is often called an ___. (a) CPU (b) MVP (c) FAQ (d) URL
- 9.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) add money spent (b) export to a file (c) pie-chart colours (d) savings stickers
- 10.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) see tasks by day (b) earn stickers (c) set a due date (d) add a homework task
- 11.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) earn stickers (b) share tasks to friends (c) add a homework task (d) pick a theme colour
- 12.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) a dark mode (b) rate the driver (c) see where the bus is (d) change the bus icon
- 13.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) add a homework task (b) set a due date (c) pick a theme colour (d) see tasks by day
-
14.🗒️ Version 1 of a bus tracker must be ready in 8 days. How many days are left for extras after the must-haves?
see where the bus is: 3 days
show arrival time: 2 days
pick your bus stop: 2 days - 15.🗒️ Why keep version 1 small? (a) to use up storage (b) to look bigger (c) to confuse users (d) to learn from users soon
- 16.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) see today’s total (b) custom alert sounds (c) share your streak (d) water animations
-
17.🗒️ Version 1 of a water reminder must be ready in 9 days. How many days are left for extras after the must-haves?
set a reminder time: 4 days
log a glass of water: 3 days
see today’s total: 2 days - 18.🗒️ A to-do app with no “add a task” feature is ___. (a) ready to release (b) well planned (c) missing a must-have (d) a nice extra
- 19.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show the score (b) check the answer (c) background music (d) show a question
-
20.🗒️ Version 1 of a homework planner must be ready in 12 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 4 days
see tasks by day: 2 days - 21.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) share your streak (b) see today’s total (c) set a reminder time (d) log a glass of water
-
22.🗒️ Version 1 of a bus tracker must be ready in 10 days. How many days are left for extras after the must-haves?
see where the bus is: 2 days
show arrival time: 3 days
pick your bus stop: 5 days -
23.🗒️ Version 1 of a homework planner must be ready in 9 days. How many days are left for extras after the must-haves?
add a homework task: 1 days
set a due date: 1 days
see tasks by day: 2 days - 24.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) set a reminder time (b) custom alert sounds (c) log a glass of water (d) see today’s total
- 25.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) see where the bus is (b) rate the driver (c) show arrival time (d) pick your bus stop
- 26.🗒️ In MVP, the M stands for ___. (a) mobile (b) minimum (c) music (d) maximum
-
27.🗒️ Version 1 of a bus tracker must be ready in 14 days. How many days are left for extras after the must-haves?
see where the bus is: 1 days
show arrival time: 4 days
pick your bus stop: 5 days -
28.🗒️ Version 1 of a homework planner must be ready in 10 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 3 days
see tasks by day: 4 days - 29.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) log a glass of water (b) water animations (c) custom alert sounds (d) share your streak
-
30.🗒️ Version 1 of a pocket-money tracker must be ready in 11 days. How many days are left for extras after the must-haves?
add money received: 3 days
add money spent: 4 days
show the balance: 4 days -
31.🗒️ Version 1 of a quiz app must be ready in 13 days. How many days are left for extras after the must-haves?
show a question: 4 days
check the answer: 2 days
show the score: 3 days - 32.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) change the bus icon (b) rate the driver (c) show arrival time (d) a dark mode
-
33.🗒️ Version 1 of a bus tracker must be ready in 13 days. How many days are left for extras after the must-haves?
see where the bus is: 2 days
show arrival time: 4 days
pick your bus stop: 4 days -
34.🗒️ Version 1 of a quiz app must be ready in 15 days. How many days are left for extras after the must-haves?
show a question: 4 days
check the answer: 4 days
show the score: 4 days -
35.🗒️ Version 1 of a quiz app must be ready in 11 days. How many days are left for extras after the must-haves?
show a question: 4 days
check the answer: 4 days
show the score: 2 days -
36.🗒️ Version 1 of a homework planner must be ready in 18 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 4 days
see tasks by day: 5 days - 37.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) pie-chart colours (b) show the balance (c) add money received (d) add money spent
- 38.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show the score (b) show a question (c) an avatar shop (d) check the answer
- 39.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) see where the bus is (b) pick your bus stop (c) change the bus icon (d) show arrival time
-
40.🗒️ Version 1 of a homework planner must be ready in 12 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 3 days
see tasks by day: 3 days
Answer key
- one the app cannot skip
- set a reminder time
- share tasks to friends
- pick your bus stop
- check the answer
- 0
- 5
- MVP
- add money spent
- earn stickers
- add a homework task
- see where the bus is
- pick a theme colour
- 1
- to learn from users soon
- see today’s total
- 0
- missing a must-have
- background music
- 4
- share your streak
- 0
- 5
- custom alert sounds
- rate the driver
- minimum
- 4
- 1
- log a glass of water
- 0
- 4
- show arrival time
- 3
- 3
- 1
- 6
- pie-chart colours
- an avatar shop
- change the bus icon
- 4