App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
-
1.🗒️ Version 1 of a homework planner must be ready in 11 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 1 days
see tasks by day: 3 days - 2.🗒️ A to-do app with no “add a task” feature is ___. (a) ready to release (b) missing a must-have (c) a nice extra (d) well planned
-
3.🗒️ Version 1 of a water reminder must be ready in 12 days. How many days are left for extras after the must-haves?
set a reminder time: 2 days
log a glass of water: 1 days
see today’s total: 3 days - 4.🗒️ In MVP, the M stands for ___. (a) music (b) mobile (c) minimum (d) maximum
-
5.🗒️ Version 1 of a quiz app must be ready in 14 days. How many days are left for extras after the must-haves?
show a question: 2 days
check the answer: 3 days
show the score: 3 days - 6.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) pick your bus stop (b) see where the bus is (c) show arrival time (d) a dark mode
-
7.🗒️ Version 1 of a bus tracker must be ready in 8 days. How many days are left for extras after the must-haves?
see where the bus is: 2 days
show arrival time: 2 days
pick your bus stop: 2 days - 8.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) see today’s total (b) log a glass of water (c) water animations (d) set a reminder time
- 9.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) custom alert sounds (b) share your streak (c) water animations (d) see today’s total
- 10.🗒️ What is a must-have feature? (a) a sound effect (b) a colour theme (c) one the app cannot skip (d) a nice extra
- 11.🗒️ Why keep version 1 small? (a) to look bigger (b) to use up storage (c) to confuse users (d) to learn from users soon
-
12.🗒️ Version 1 of a bus tracker must be ready in 13 days. How many days are left for extras after the must-haves?
see where the bus is: 3 days
show arrival time: 2 days
pick your bus stop: 2 days - 13.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) earn stickers (b) pick a theme colour (c) add a homework task (d) share tasks to friends
-
14.🗒️ Version 1 of a homework planner must be ready in 15 days. How many days are left for extras after the must-haves?
add a homework task: 4 days
set a due date: 3 days
see tasks by day: 4 days - 15.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) confetti effects (b) check the answer (c) show a question (d) show the score
- 16.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) share your streak (b) water animations (c) set a reminder time (d) custom alert sounds
-
17.🗒️ Version 1 of a quiz app must be ready in 13 days. How many days are left for extras after the must-haves?
show a question: 3 days
check the answer: 2 days
show the score: 4 days -
18.🗒️ Version 1 of a homework planner must be ready in 9 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 1 days
see tasks by day: 3 days -
19.🗒️ Version 1 of a quiz app must be ready in 10 days. How many days are left for extras after the must-haves?
show a question: 2 days
check the answer: 1 days
show the score: 3 days - 20.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) confetti effects (b) background music (c) an avatar shop (d) show a question
- 21.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) show the balance (b) add money spent (c) pie-chart colours (d) add money received
- 22.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) a dark mode (b) pick your bus stop (c) rate the driver (d) change the bus icon
- 23.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money received (b) show the balance (c) savings stickers (d) add money spent
-
24.🗒️ Version 1 of a water reminder must be ready in 16 days. How many days are left for extras after the must-haves?
set a reminder time: 4 days
log a glass of water: 3 days
see today’s total: 3 days -
25.🗒️ Version 1 of a quiz app must be ready in 12 days. How many days are left for extras after the must-haves?
show a question: 2 days
check the answer: 4 days
show the score: 4 days -
26.🗒️ Version 1 of a homework planner must be ready in 16 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 3 days
see tasks by day: 4 days - 27.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) an avatar shop (b) background music (c) check the answer (d) confetti effects
- 28.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) see today’s total (b) log a glass of water (c) set a reminder time (d) custom alert sounds
- 29.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) add a homework task (b) set a due date (c) see tasks by day (d) earn stickers
-
30.🗒️ Version 1 of a quiz app must be ready in 7 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 1 days
show the score: 2 days -
31.🗒️ Version 1 of a pocket-money tracker must be ready in 11 days. How many days are left for extras after the must-haves?
add money received: 3 days
add money spent: 3 days
show the balance: 5 days - 32.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) show the balance (b) savings stickers (c) export to a file (d) pie-chart colours
-
33.🗒️ Version 1 of a bus tracker must be ready in 8 days. How many days are left for extras after the must-haves?
see where the bus is: 4 days
show arrival time: 1 days
pick your bus stop: 3 days - 34.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) pick your bus stop (b) change the bus icon (c) see where the bus is (d) show arrival time
-
35.🗒️ Version 1 of a bus tracker must be ready in 12 days. How many days are left for extras after the must-haves?
see where the bus is: 1 days
show arrival time: 2 days
pick your bus stop: 5 days -
36.🗒️ Version 1 of a bus tracker must be ready in 8 days. How many days are left for extras after the must-haves?
see where the bus is: 1 days
show arrival time: 1 days
pick your bus stop: 2 days - 37.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) an avatar shop (b) confetti effects (c) show the score (d) background music
- 38.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) show arrival time (b) a dark mode (c) rate the driver (d) change the bus icon
- 39.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) share tasks to friends (b) set a due date (c) add a homework task (d) see tasks by day
-
40.🗒️ Version 1 of a quiz app must be ready in 14 days. How many days are left for extras after the must-haves?
show a question: 3 days
check the answer: 4 days
show the score: 2 days
Answer key
- 5
- missing a must-have
- 6
- minimum
- 6
- a dark mode
- 2
- water animations
- see today’s total
- one the app cannot skip
- to learn from users soon
- 6
- add a homework task
- 4
- confetti effects
- set a reminder time
- 4
- 2
- 4
- show a question
- pie-chart colours
- pick your bus stop
- savings stickers
- 6
- 2
- 6
- check the answer
- custom alert sounds
- earn stickers
- 3
- 0
- show the balance
- 0
- change the bus icon
- 4
- 4
- show the score
- show arrival time
- share tasks to friends
- 5