App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
- 1.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) water animations (b) set a reminder time (c) share your streak (d) custom alert sounds
- 2.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) add money spent (b) pie-chart colours (c) export to a file (d) savings stickers
-
3.🗒️ Version 1 of a homework planner must be ready in 11 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 1 days
see tasks by day: 5 days - 4.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) pick your bus stop (b) a dark mode (c) rate the driver (d) change the bus icon
- 5.🗒️ In MVP, the M stands for ___. (a) music (b) mobile (c) minimum (d) maximum
- 6.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) add a homework task (b) share tasks to friends (c) pick a theme colour (d) earn stickers
- 7.🗒️ The first small, working version of an app is often called an ___. (a) FAQ (b) CPU (c) URL (d) MVP
- 8.🗒️ What is a must-have feature? (a) one the app cannot skip (b) a nice extra (c) a sound effect (d) a colour theme
-
9.🗒️ Version 1 of a homework planner must be ready in 11 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 3 days
see tasks by day: 2 days - 10.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) rate the driver (b) show arrival time (c) a dark mode (d) change the bus icon
-
11.🗒️ Version 1 of a quiz app must be ready in 11 days. How many days are left for extras after the must-haves?
show a question: 4 days
check the answer: 2 days
show the score: 5 days - 12.🗒️ A to-do app with no “add a task” feature is ___. (a) missing a must-have (b) a nice extra (c) well planned (d) ready to release
-
13.🗒️ Version 1 of a quiz app must be ready in 13 days. How many days are left for extras after the must-haves?
show a question: 2 days
check the answer: 3 days
show the score: 4 days -
14.🗒️ Version 1 of a water reminder must be ready in 15 days. How many days are left for extras after the must-haves?
set a reminder time: 1 days
log a glass of water: 4 days
see today’s total: 4 days - 15.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) pick a theme colour (b) share tasks to friends (c) see tasks by day (d) earn stickers
- 16.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) custom alert sounds (b) water animations (c) see today’s total (d) share your streak
-
17.🗒️ Version 1 of a homework planner must be ready in 12 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 1 days
see tasks by day: 5 days - 18.🗒️ Why keep version 1 small? (a) to confuse users (b) to use up storage (c) to learn from users soon (d) to look bigger
- 19.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) set a due date (b) see tasks by day (c) pick a theme colour (d) add a homework task
- 20.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show the score (b) confetti effects (c) show a question (d) check the answer
- 21.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) savings stickers (b) add money received (c) pie-chart colours (d) export to a file
- 22.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) background music (b) an avatar shop (c) confetti effects (d) show a question
- 23.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) pick your bus stop (b) show arrival time (c) see where the bus is (d) a dark mode
-
24.🗒️ Version 1 of a pocket-money tracker must be ready in 11 days. How many days are left for extras after the must-haves?
add money received: 3 days
add money spent: 3 days
show the balance: 2 days - 25.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) an avatar shop (b) background music (c) show the score (d) confetti effects
-
26.🗒️ Version 1 of a quiz app must be ready in 13 days. How many days are left for extras after the must-haves?
show a question: 4 days
check the answer: 2 days
show the score: 3 days - 27.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) set a reminder time (b) see today’s total (c) log a glass of water (d) water animations
-
28.🗒️ Version 1 of a quiz app must be ready in 9 days. How many days are left for extras after the must-haves?
show a question: 2 days
check the answer: 1 days
show the score: 5 days - 29.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) background music (b) show the score (c) show a question (d) check the answer
-
30.🗒️ Version 1 of a pocket-money tracker must be ready in 12 days. How many days are left for extras after the must-haves?
add money received: 2 days
add money spent: 4 days
show the balance: 5 days -
31.🗒️ Version 1 of a pocket-money tracker must be ready in 14 days. How many days are left for extras after the must-haves?
add money received: 4 days
add money spent: 3 days
show the balance: 3 days - 32.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) share your streak (b) water animations (c) custom alert sounds (d) log a glass of water
-
33.🗒️ Version 1 of a water reminder must be ready in 15 days. How many days are left for extras after the must-haves?
set a reminder time: 1 days
log a glass of water: 4 days
see today’s total: 5 days - 34.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) earn stickers (b) share tasks to friends (c) set a due date (d) pick a theme colour
-
35.🗒️ Version 1 of a quiz app must be ready in 11 days. How many days are left for extras after the must-haves?
show a question: 3 days
check the answer: 4 days
show the score: 4 days -
36.🗒️ Version 1 of a bus tracker must be ready in 12 days. How many days are left for extras after the must-haves?
see where the bus is: 3 days
show arrival time: 2 days
pick your bus stop: 3 days -
37.🗒️ Version 1 of a homework planner must be ready in 14 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 1 days
see tasks by day: 5 days - 38.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) rate the driver (b) a dark mode (c) see where the bus is (d) change the bus icon
- 39.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show the score (b) check the answer (c) an avatar shop (d) show a question
-
40.🗒️ Version 1 of a quiz app must be ready in 11 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 3 days
show the score: 3 days
Answer key
- set a reminder time
- add money spent
- 2
- pick your bus stop
- minimum
- add a homework task
- MVP
- one the app cannot skip
- 4
- show arrival time
- 0
- missing a must-have
- 4
- 6
- see tasks by day
- see today’s total
- 4
- to learn from users soon
- pick a theme colour
- confetti effects
- add money received
- show a question
- a dark mode
- 3
- show the score
- 4
- water animations
- 1
- background music
- 1
- 4
- log a glass of water
- 5
- set a due date
- 0
- 4
- 6
- see where the bus is
- an avatar shop
- 4
Free app development lessons, practice and worksheets at talentjr.in/app-development-for-students