Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Isha can finish a job in 15 days and Ishaan in 18 days. What fraction of the job do they finish if they work together for 3 days? =
- 2.Saanvi can finish a job in 12 days and Pooja in 24 days. Saanvi works alone for 6 days and then stops. Pooja finishes the rest. How many days does Pooja take?
- 3.Meera works twice as fast as Aarav. Together they finish a job in 10 days. How many days would Aarav take alone?
- 4.Kabir can finish a job in 17 days and Isha in 18 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 5.Aarav can finish a job in 10 days and Dev in 13 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 6.Aarav works three times as fast as Saanvi. Together they finish a job in 7 days. How many days would Saanvi take alone?
- 7.Meera can finish a job in 16 days and Manav in 12 days. Meera works alone for 4 days and then stops. Manav finishes the rest. How many days does Manav take?
- 8.Saanvi can finish a job in 7 days and Rohan in 8 days. What fraction of the job do they finish if they work together for 2 days? =
- 9.Isha can finish a job in 10 days and Diya in 25 days. Isha works alone for 2 days and then stops. Diya finishes the rest. How many days does Diya take?
- 10.Dev and Nisha together finish a job in 6 days. Dev alone takes 12 days. How many days would Nisha take alone?
- 11.Sneha works twice as fast as Karan. Together they finish a job in 2 days. How many days would Karan take alone?
- 12.Vivaan can finish a job in 8 days and Tara in 17 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 13.Diya can finish a job in 10 days and Isha in 15 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 14.Meera works three times as fast as Diya. Together they finish a job in 2 days. How many days would Diya take alone?
- 15.Dev can finish a job in 4 days and Arjun in 28 days. Dev works alone for 2 days and then stops. Arjun finishes the rest. How many days does Arjun take?
- 16.Manav can finish a job in 4 days and Kavya in 12 days. What fraction of the job do they finish if they work together for 2 days? =
- 17.Sneha can finish a job in 2 days and Meera in 18 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 18.Meera can finish a job in 20 days and Rahul in 10 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 19.Priya works twice as fast as Pooja. Together they finish a job in 8 days. How many days would Pooja take alone?
- 20.Sneha can finish a job in 20 days and Aarav in 15 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 21.Nisha can finish a job in 20 days and Arjun in 4 days. What fraction of the job do they finish if they work together for 2 days? =
- 22.Priya works twice as fast as Sneha. Together they finish a job in 5 days. How many days would Sneha take alone?
- 23.Tara can finish a job in 10 days and Arjun in 20 days. Tara works alone for 4 days and then stops. Arjun finishes the rest. How many days does Arjun take?
- 24.Tara can finish a job in 6 days and Sneha in 11 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 25.Karan works twice as fast as Vivaan. Together they finish a job in 12 days. How many days would Vivaan take alone?
- 26.Rahul works three times as fast as Aditya. Together they finish a job in 11 days. How many days would Aditya take alone?
- 27.Dev works twice as fast as Aarav. Together they finish a job in 2 days. How many days would Aarav take alone?
- 28.Zoya can finish a job in 9 days and Ananya in 12 days. Zoya works alone for 6 days and then stops. Ananya finishes the rest. How many days does Ananya take?
- 29.Pooja works twice as fast as Karan. Together they finish a job in 5 days. How many days would Karan take alone?
- 30.Aditya and Priya together finish a job in 2 days. Aditya alone takes 3 days. How many days would Priya take alone?
- 31.Kabir and Saanvi together finish a job in 4 days. Kabir alone takes 6 days. How many days would Saanvi take alone?
- 32.Diya and Rahul together finish a job in 6 days. Diya alone takes 7 days. How many days would Rahul take alone?
- 33.Priya can finish a job in 7 days and Tara in 4 days. What fraction of the job do they finish if they work together for 2 days? =
- 34.Dev can finish a job in 4 days and Pooja in 8 days. Dev works alone for 1 day and then stops. Pooja finishes the rest. How many days does Pooja take?
- 35.Rohan can finish a job in 12 days and Dev in 16 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 36.Aarav can finish a job in 14 days and Farhan in 28 days. Aarav works alone for 13 days and then stops. Farhan finishes the rest. How many days does Farhan take?
- 37.Priya and Dev together finish a job in 6 days. Priya alone takes 7 days. How many days would Dev take alone?
- 38.Aditya and Nisha together finish a job in 2 days. Aditya alone takes 4 days. How many days would Nisha take alone?
- 39.Vivaan can finish a job in 16 days and Manav in 6 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 40.Dev works twice as fast as Pooja. Together they finish a job in 10 days. How many days would Pooja take alone?
Answer key
- 11/30
- 12
- 30
- 306/35
- 130/23
- 28
- 9
- 15/28
- 20
- 12
- 6
- 136/25
- 6
- 8
- 14
- 2/3
- 9/5
- 20/3
- 24
- 60/7
- 3/5
- 15
- 12
- 66/17
- 36
- 44
- 6
- 4
- 15
- 6
- 12
- 42
- 11/14
- 6
- 48/7
- 2
- 42
- 4
- 48/11
- 30