Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Rahul can finish a job in 4 days and Rohan in 14 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 2.Rohan can finish a job in 6 days and Dev in 19 days. What fraction of the job do they finish if they work together for 2 days? =
- 3.Dev and Rohan together finish a job in 6 days. Dev alone takes 9 days. How many days would Rohan take alone?
- 4.Sneha can finish a job in 6 days and Meera in 12 days. Sneha works alone for 3 days and then stops. Meera finishes the rest. How many days does Meera take?
- 5.Rohan can finish a job in 5 days and Manav in 14 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 6.Ananya can finish a job in 4 days and Zoya in 28 days. Ananya works alone for 2 days and then stops. Zoya finishes the rest. How many days does Zoya take?
- 7.Vivaan works three times as fast as Sneha. Together they finish a job in 9 days. How many days would Sneha take alone?
- 8.Farhan can finish a job in 4 days and Kabir in 30 days. Farhan works alone for 2 days and then stops. Kabir finishes the rest. How many days does Kabir take?
- 9.Karan and Nisha together finish a job in 6 days. Karan alone takes 7 days. How many days would Nisha take alone?
- 10.Karan and Aditya together finish a job in 2 days. Karan alone takes 3 days. How many days would Aditya take alone?
- 11.Rahul can finish a job in 17 days and Zoya in 8 days. What fraction of the job do they finish if they work together for 1 day? =
- 12.Vivaan can finish a job in 11 days and Ananya in 6 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 13.Isha can finish a job in 9 days and Karan in 5 days. What fraction of the job do they finish if they work together for 1 day? =
- 14.Farhan can finish a job in 9 days and Sneha in 17 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 15.Kabir and Ananya together finish a job in 10 days. Kabir alone takes 30 days. How many days would Ananya take alone?
- 16.Karan can finish a job in 5 days and Manav in 15 days. What fraction of the job do they finish if they work together for 2 days? =
- 17.Vivaan can finish a job in 17 days and Nisha in 16 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 18.Pooja can finish a job in 4 days and Dev in 8 days. Pooja works alone for 3 days and then stops. Dev finishes the rest. How many days does Dev take?
- 19.Arjun can finish a job in 14 days and Aarav in 9 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 20.Arjun and Rohan together finish a job in 4 days. Arjun alone takes 6 days. How many days would Rohan take alone?
- 21.Pooja and Aarav together finish a job in 6 days. Pooja alone takes 7 days. How many days would Aarav take alone?
- 22.Nisha can finish a job in 6 days and Isha in 5 days. What fraction of the job do they finish if they work together for 1 day? =
- 23.Aarav can finish a job in 14 days and Kabir in 8 days. What fraction of the job do they finish if they work together for 3 days? =
- 24.Dev can finish a job in 24 days and Isha in 30 days. Dev works alone for 20 days and then stops. Isha finishes the rest. How many days does Isha take?
- 25.Ishaan and Tara together finish a job in 4 days. Ishaan alone takes 5 days. How many days would Tara take alone?
- 26.Farhan and Sneha together finish a job in 4 days. Farhan alone takes 5 days. How many days would Sneha take alone?
- 27.Diya can finish a job in 12 days and Nisha in 11 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 28.Aarav and Priya together finish a job in 2 days. Aarav alone takes 6 days. How many days would Priya take alone?
- 29.Rohan and Diya together finish a job in 4 days. Rohan alone takes 8 days. How many days would Diya take alone?
- 30.Farhan can finish a job in 16 days and Meera in 10 days. What fraction of the job do they finish if they work together for 2 days? =
- 31.Vivaan can finish a job in 28 days and Meera in 30 days. Vivaan works alone for 14 days and then stops. Meera finishes the rest. How many days does Meera take?
- 32.Kabir can finish a job in 14 days and Saanvi in 6 days. What fraction of the job do they finish if they work together for 2 days? =
- 33.Dev works twice as fast as Priya. Together they finish a job in 6 days. How many days would Priya take alone?
- 34.Pooja can finish a job in 3 days and Isha in 7 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 35.Dev can finish a job in 30 days and Nisha in 10 days. Dev works alone for 9 days and then stops. Nisha finishes the rest. How many days does Nisha take?
- 36.Farhan can finish a job in 20 days and Pooja in 13 days. What fraction of the job do they finish if they work together for 3 days? =
- 37.Rahul can finish a job in 11 days and Ishaan in 10 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 38.Aarav can finish a job in 14 days and Dev in 5 days. What fraction of the job do they finish if they work together for 1 day? =
- 39.Nisha can finish a job in 2 days and Saanvi in 6 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 40.Kabir can finish a job in 22 days and Dev in 8 days. Kabir works alone for 11 days and then stops. Dev finishes the rest. How many days does Dev take?
Answer key
- 28/9
- 25/57
- 18
- 6
- 70/19
- 14
- 36
- 15
- 42
- 6
- 25/136
- 66/17
- 14/45
- 153/26
- 15
- 8/15
- 272/33
- 2
- 126/23
- 12
- 42
- 11/30
- 33/56
- 5
- 20
- 20
- 132/23
- 3
- 8
- 13/40
- 15
- 10/21
- 18
- 21/10
- 7
- 99/260
- 110/21
- 19/70
- 3/2
- 4