Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Arjun and Zoya together finish a job in 2 days. Arjun alone takes 3 days. How many days would Zoya take alone?
- 2.Diya can finish a job in 4 days and Dev in 20 days. Diya works alone for 2 days and then stops. Dev finishes the rest. How many days does Dev take?
- 3.Dev and Tara together finish a job in 2 days. Dev alone takes 3 days. How many days would Tara take alone?
- 4.Pooja can finish a job in 6 days and Meera in 9 days. Pooja works alone for 4 days and then stops. Meera finishes the rest. How many days does Meera take?
- 5.Dev and Pooja together finish a job in 16 days. Dev alone takes 24 days. How many days would Pooja take alone?
- 6.Tara works twice as fast as Ishaan. Together they finish a job in 5 days. How many days would Ishaan take alone?
- 7.Pooja and Isha together finish a job in 3 days. Pooja alone takes 12 days. How many days would Isha take alone?
- 8.Ishaan can finish a job in 15 days and Isha in 16 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 9.Meera can finish a job in 10 days and Diya in 15 days. What fraction of the job do they finish if they work together for 3 days? =
- 10.Pooja can finish a job in 10 days and Ishaan in 30 days. Pooja works alone for 9 days and then stops. Ishaan finishes the rest. How many days does Ishaan take?
- 11.Arjun can finish a job in 4 days and Ananya in 8 days. Arjun works alone for 3 days and then stops. Ananya finishes the rest. How many days does Ananya take?
- 12.Meera and Ananya together finish a job in 5 days. Meera alone takes 10 days. How many days would Ananya take alone?
- 13.Isha can finish a job in 4 days and Ishaan in 14 days. Isha works alone for 2 days and then stops. Ishaan finishes the rest. How many days does Ishaan take?
- 14.Manav can finish a job in 12 days and Farhan in 6 days. Manav works alone for 6 days and then stops. Farhan finishes the rest. How many days does Farhan take?
- 15.Sneha can finish a job in 7 days and Ishaan in 16 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 16.Arjun can finish a job in 4 days and Ananya in 15 days. What fraction of the job do they finish if they work together for 2 days? =
- 17.Arjun can finish a job in 16 days and Aarav in 20 days. Arjun works alone for 12 days and then stops. Aarav finishes the rest. How many days does Aarav take?
- 18.Aarav can finish a job in 15 days and Nisha in 2 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 19.Aditya can finish a job in 19 days and Meera in 4 days. What fraction of the job do they finish if they work together for 3 days? =
- 20.Diya can finish a job in 5 days and Vivaan in 25 days. Diya works alone for 4 days and then stops. Vivaan finishes the rest. How many days does Vivaan take?
- 21.Dev works three times as fast as Aditya. Together they finish a job in 2 days. How many days would Aditya take alone?
- 22.Diya can finish a job in 8 days and Ananya in 9 days. What fraction of the job do they finish if they work together for 3 days? =
- 23.Kabir works three times as fast as Karan. Together they finish a job in 8 days. How many days would Karan take alone?
- 24.Karan can finish a job in 13 days and Ishaan in 8 days. What fraction of the job do they finish if they work together for 1 day? =
- 25.Nisha works three times as fast as Pooja. Together they finish a job in 12 days. How many days would Pooja take alone?
- 26.Manav and Arjun together finish a job in 12 days. Manav alone takes 15 days. How many days would Arjun take alone?
- 27.Sneha can finish a job in 4 days and Manav in 28 days. Sneha works alone for 1 day and then stops. Manav finishes the rest. How many days does Manav take?
- 28.Zoya and Diya together finish a job in 6 days. Zoya alone takes 8 days. How many days would Diya take alone?
- 29.Rohan can finish a job in 8 days and Zoya in 16 days. Rohan works alone for 4 days and then stops. Zoya finishes the rest. How many days does Zoya take?
- 30.Arjun can finish a job in 4 days and Sneha in 8 days. Arjun works alone for 3 days and then stops. Sneha finishes the rest. How many days does Sneha take?
- 31.Sneha can finish a job in 7 days and Nisha in 11 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 32.Kabir works twice as fast as Karan. Together they finish a job in 4 days. How many days would Karan take alone?
- 33.Ishaan and Priya together finish a job in 2 days. Ishaan alone takes 4 days. How many days would Priya take alone?
- 34.Zoya and Priya together finish a job in 4 days. Zoya alone takes 8 days. How many days would Priya take alone?
- 35.Nisha can finish a job in 15 days and Pooja in 8 days. What fraction of the job do they finish if they work together for 2 days? =
- 36.Saanvi can finish a job in 15 days and Kabir in 2 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 37.Ishaan works three times as fast as Kavya. Together they finish a job in 8 days. How many days would Kavya take alone?
- 38.Vivaan can finish a job in 13 days and Nisha in 3 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 39.Nisha can finish a job in 9 days and Zoya in 15 days. Nisha works alone for 3 days and then stops. Zoya finishes the rest. How many days does Zoya take?
- 40.Pooja can finish a job in 7 days and Ishaan in 3 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
Answer key
- 6
- 10
- 6
- 3
- 48
- 15
- 4
- 240/31
- 1/2
- 3
- 2
- 10
- 7
- 3
- 112/23
- 19/30
- 5
- 30/17
- 69/76
- 5
- 8
- 17/24
- 32
- 21/104
- 48
- 60
- 21
- 24
- 8
- 2
- 77/18
- 12
- 4
- 8
- 23/60
- 30/17
- 32
- 39/16
- 10
- 21/10